Networks and Critical Paths Flashcards
Networks provide a visual representation of?
of projects
Networks documents ?
The dependencies between all the activities necessary to complete the project
Networks provide ?
A useful tool to discuss the progress with the project team and stakeholders
When a network is created the duration of the activities or resources are not
Considered
The network is refined with these considerations in a later step.
In summary a network documents the ________ between _____ assuming Infinite _________. The practicalities are dealt with later
Dependencies
Activities
Infinite
The activities are taken from _______ and out into order
WBS
There are 3 main dependencies types which are ?
Finish to start
Start to start
Finish to finish
The most common type of dependency is ?
Finish to start
FINISH TO START
Activity B Can start when activity A has been completed
START TO START
Once and activity has started another activity has started
FINISH TO FINISH
Once an activity has finished another activity can finish
Common Faults when establishing a network : avoid loops
Many operation require rework , it seems easy to put in a loop , in scheduling terms it defies logic.
It is better to have one activity and describe it in great detail as loops require careful consideration when estimating their duration.
Common Faults when establishing a network : avoid Danglers
Where networks have two ends
They can cause problems when calculating the project duration
If there are two or more endpoint a dummy activity should be inserted which can have zero duration instead and link the danglers into it
It is acceptable to have multiple start activities
Common Faults when establishing a network :ensure correct entry and exit points
For finish to start dependencies ensure the linking arrows exit from the right hand side of the activity and enter into the left hand side of the activity
This helps to avoid problems when calculating the project duration in a later step
Network boxes are known as ______ and each box can be divided into ______ areas
Node
7
The project schedule is created by defining all the _______ to be performed taking account of their _________________
Their relationship, estimated durations and the resources required within the project calendar
There are 7 steps in the schedule development process :
- Identifying the task from the WBS
2.Estimating the duration (effort) of each tasks
3.determining the logical relationship between tasks (dependencies) in relation to their delivery - Carrying out optimisation of the schedule and testing the logic
5.assigning resources that are required to carry out work
6.checking that the defined schedule meets the target success criteria for cost and time
7.baseline the schedule and monitoring during its deployment
There are two principle types of scheduling ?
Critical path and critical chain
The critical path approach places _______ on the activities in a project and understanding the _______ time to complete all activities in a logical order.
Emphasis
Shortest
To do this dependencies between each activity that forms the scope of work to be completed need to be agreed.
Establishing the logic between the activities enables a _____________ to be determined. Then estimates of duration (based on the effort required) can be made.
Precedence network
The resulting _________ can be identified as the sequence of activities through the precedence network from start to finish whose duration when summed determines the _________.
Critical path
Overall duration
Within a large project , there can be a number of individual _________ to deal with different aspects of project. The mater schedules combines ________ and keeps track of all _______ schedules within the overall project scope
Schedules
Coordinates
Subordinate
When using an iterative lifecycle rather than considering scope and quality as fixed and estimating time and cost , a _______ approached it Is used.
Time box
A fixed period of
Time with determined resources , during which scope is completed to quality as efficiently as possible
Time boxes =
Sprints