IDPX Questions Flashcards
The two primary methods of measuring space are based on the standards of what two organizations?
BOMA (Building Owners and Managers Association) and IFMA (International Facility Management Association)
What is the efficiency factor of a single leased space?
the ratio of the net area or net assignable area to the usable area
With whom should the interior designer consult to put additional stacks of shelves and books in a library?
(A) Mechanical Engineer
(B) Library Planner
(C) Structural Engineer
(D) Fire Protection Designer
Structural engineer
Which of the following provides the MOST accurate basis for estimating project costs
(A) Square Footages
(B) Functional Unit
(C) Parameter
(D) Quanity Takeoff
Quanity Takeoff
ASTM is a(n)
(A) Model Code Group
(B) Industry Standard-Writing Organization
(C) Test Labatory
(D) Federal Code-Writing Agency
Industry Standard-Writing Organization
Core drilling would be MOST difficult in which type of situation
(A) Concerte over steel deck
(B) Flat Slab Concerte
(C) One-way pan joist concerte
(D) Post-tensioned concerte
Post-tensioned concrete
Why: Because there is a lot of reinforcements. You would literally have to x-ray your slab
As it relates to leased space, which of the following would not be considered primary circulation space?
Main corridors in each private leased area
Primary = what can be considered public
Secondary = within private areas
The two most important factors in determining the number of exits required for a particular room or space are:
occupancy and occupant load
What is included in net floor areas?
spaces for a clients specific program function
Ex. offices, breakrooms, conference room,
Not space for circulation or amenities
The occupant load of any portion of a building is allowed to increase as long as all other requirements are met and it does not exceed 7sf of occupicable floor space. True or False?
True
The minimum number of toilet fixtures required is determined by occupant load and
occupancy group
Following the final design development meeting, the client has requested to see a revised budget.
At this point in the design process, what estimating method would provide the most appropriate budget for the client’s review?
(A) parameter method
(B) square footage cost
(C) detailed quantity takeoffs
(D) matrix costing
Parameter Method
The parameter method using the totaled unit pricing per material type would provide the most accurate pricing at this point until all selections have been finalized.
Quantity takeoffs would be used once all specifications have been finalized.
Which interior design service is specific to the contract administration phase of a project?
(A) Develop budget
(B) Review shop drawings
(C) Provide installation details
(D) Review consultant contracts
Review shop drawings
at the beginning or during the course of this phase, shop drawings from trades may be submitted for review
What is a line chart or a line sheet?
list the various product lines an independent sales representative handles
The bid form sent to all bidders should ask for the following information?
-the amount of the base bid,
-the price for alternates (if any),
-unit prices (if any)
-the number of calendar or work days in which the bidder proposes to complete the work.
Space should be provided for the bidder to acknowledge receipt of any addenda.
The bid form must be signed by someone legally empowered to bind the contractor to the owner contract.
What can the designer do if the dollar amount requested on the contractors application for payment exceeds the work completed and materials stored?
The designer may certify an amount less than what is requested as long as a written explanation is attached.
Which of the following would not be included in the project notebook?
(A) punch list
(B) copy of all bonds
(C) shop drawings
(D) submittals
Copy of all bonds
the project notebook is something the interior designer is responsible for. Since the designer does not have responsibility over bonds, they will not be in the notebook
What are change authorization and minor work orders for?
only for minor changes that do not require a change in contract cost or time
If a project is going to be submitted for LEED Certification, all of the requirements would be listed in which division?
(A) Division-13
(B) Division-01
(C) Division-10
(D) Division-09
Division -01 (General requirements)
What is a project progress report?
The project progress report shows the hours and labor costs for each phase of a project for the current reporting period as well as the amount to date and compares these numbers with estimated hours and dollars. Direct costs for consultants, overhead allocations, and reimbursable expenses, are also shown.
one of the most important reports used by an interior design firm to monitor project progress, revenue and expenses and can be used to take corrective action for finances
When preparing bid documents, what can be included to allow the owner some flexibility in modifying the cost of the project when the bids are submitted?
(A) substitution
(B) base bid
(C) alternative
(D) allowance
Alternative
a request included in the bid documents asking the contractor to supply a price for some type of variation from the base bid.
Alternatives allow the owner some flexibility in modifying the cost of a project when the bids are submitted.
What is the primary advantage of reference specifications?
(A) products and workmanship will meet the designer’s specific requirements
(B) standards reduces chances of error and maximizes liability
(C) designer does NOT have to be fully aware of the up to date testing
(D) saves time
Saves time
In which division of the CSI Master Format would you find the specifications for typical structural wood framing, rough and finish carpentry and architectural woodwork?
(A) Division 12
(B) Division 06
(C) Division 01
(D) Division 05
Division-06 Wood, plastics
*You can review a clickable index of the MasterFormat divisions and what they include at Sweets Catalog
To encourage competitive bidding, public projects usually require what type of construction specifications?
(A) base – bid specifications
(B) prescriptive specifications
(C) proprietary specifications
(D) performance specifications
(D) performance specifications
tell what results the final construction assembly must achieve, but they give the contractor some choice in how they will be achieved.