Integration Flashcards

(40 cards)

1
Q

the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the project management process groups.

A

Project Integration Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

A

Develop project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.

A

Develop project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives

A

Direct and manage project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning

A

Manage project knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process of tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan.

A

Monitor and control project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating the decisions

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The process of finalizing all activities for the project, phase, or contract.

A

Close project or phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the processes for program integration

A
Develop project charter
Develop project management plan
Direct and manage project work
Manage project knowledge 
Monitor and control project work
Perform integrated change control
Close project or phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are inputs to project charter

A
Business documents
    Business case
     Project benefits management plan
Agreements
EEF
OPA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the tools and techniques to develop project charter

A
Expert judgement
Data gathering
   Brainstorming
   Focus groups
   Interviews
Interpersonal and team skills
   Conflict management
   Facilitation
   Meeting management
Meeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the outputs to develop project charter

A

Project charter

Assumption log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are inputs to project management plan

A

Project charter
Outputs from other processes
EEF
OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are tools and techniques to project management plan

A
Expert judgement
Data gathering
   Brainstorming
   Checklist*
   Focus groups
   Interviews
Interpersonal and team skills
   Conflict management
   Facilitation
   Meeting management
Meeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which process providework performance reports

A

Monitor and control project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What process provides deliverables and what else in produced

A

Direct and manage project work

Work performance data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What process provides lessons learned

A

Manage project knowledge

18
Q

What process provides approved change requests

A

Perform integrated change control

19
Q

What provides final product, service, or result transition, what also are output of the process

A

Close project or phase, final report, update documents

20
Q

In direct and manage project work output is work performance data. How does this turn into work performance information for input monitor and control project work

A

Work performance data is raw data of where the project is, this information gets compared to control scope, control schedule, control costs, control quality, control resources, monitor communications, monitor risks, control procurement and manage stakeholders to determine planned vs. actual which is work performance information used in monitor and control project work as input and Output is work performance reports. Analyze impact on project resulting work performance report.

21
Q

What is output of develop project management plan

A

Project management plan

22
Q

What are inputs for direct and manage project work

A
Project management plan
Project documents
    Change log
    Lessons learned register
    Milestone list
    Project communications
    Project schedule
    Requirements traceability matrix
    Risk register
    Risk report
Approved change request
EEF
OPA
23
Q

What are tools and technology for direct and manage project work

A

Expert judgement
PMIS
Meeting

24
Q

What are outputs for direct and manage project work

A
Deliverables*
Work performance data*
Issues log
Change request
PMP updates
Project document updates
   Activities list
   Assumption log
   Lessons learned
   Requirement documents
   Risk register
   Stakeholder register
OPA updates
25
What are inputs for mange project knowledge
``` PMP Project documents Lessons learned Project team assignments Source selection criteria Resource breakdown structure Stakeholder register Deliverables EEF OPA ```
26
What are tools and techniques for mange project knowledge
``` Expert judgement Knowledge management Information management Interpersonal and team skills Active listening Facilitation Leadership Networking Political awareness ```
27
What are outputs for mange project knowledge
Lessons learned register* PMP updates OPA updates
28
What are inputs to monitor and control project work
``` PMP Project documents Assumption log Basis of estimates Cost forecasts Issue log Lessons learned register Milestone list Quality reports Risk register Risk report Schedule forecasts Work performance information Agreements EEF OPA ```
29
What are tools and technology to monitor and control project work
``` Expert judgment Data analysis Alternative analysis Cost benefit analysis Earned value analysis Root cause analysis Trend analysis Variance analysis Decision making Voting Meetings ```
30
What are outputs to monitor and control project work
``` Work performance reports* Change requests PMP updates Project documents update Cost forecasts Issues log Lessons learned register Risk register Schedule forecasts ```
31
What are inputs to perform integrated change control
``` PMP Change management plan Configuration management plan Scope baseline Schedule baseline Cost baseline Project documents Basis of estimates Requirements traceability matrix Risk reports Work performance reports Change requests EEF OPA ```
32
What are tools and techniques to perform integrated change control
``` Expert judgement Change control tools Data analysis Alternative analysis Cost benefit analysis Decision making Voting Autocratic decision Multicriteria decision Meetings ```
33
What are outputs to perform integrated change control
Approved change requests PMP updates Project document updates Change log
34
What are inputs to close project or phase
``` Project charter PMP - all components Project documents Assumption log Basis of estimates Change log Issues log Lessons learned register Milestone list Project communication Quality control measures Quality reports Requirements documentation Risk register Risk report Accepted deliverables* Business documents Business case Benefits management plan Agreements Procurement documentation OPA ```
35
What are tools and techniques to close project or phase
``` Expert judgement Data analysis Document analysis Regression analysis Trend analysis Variation analysis Meeting ```
36
What are outputs to close project or phase
``` Project documents update Lessons learned register Final product, service, or result transition Final report OPA updates ```
37
Who responsible to decide change request
Change control board committee made up key stakeholders, sponsor, some, etc. Not project manager, project manager request change and validates if approved or rejected but never part of voting team, conflict of interest
38
What is included on project management plan
Subsidiary plans (9) Requirements management plan Change management plan Configuration management plan Baselines - scope, schedule, costs, performance measurement Project life cycle description Development approach
39
Which process does not have EEF as input
Close project or phase
40
Which process does not have meetings as tool and technique
Manage project knowledge