Integration Management Flashcards

Integration Management chapter of PMBOK workbook

1
Q

The processes and activities needed to identify, define, combine, unify and coordinate the processes and activities within all process groups.

A

Project Integration Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The process for creating a charter that formally authorizes the project and provides the project management the authority to use resources for project activities.

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3 items that a SOW covers (statement of work)

A
  1. Business Need
  2. Product or Project Scope
  3. Strategic Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are created as a result of: Market Demand, Organizational Need, Customer Request, Technological Advance, Legal Requirement, Ecological Impacts, Social Need

A

Business Case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Used to define the initial project intentions

A

Contracts, MOUs, SLAs, Letters of Agreements, Letters of Intent, Verbal Agreements, Email, Other written agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Formal authorization for PM to initiate a project/phase. Developed prior to planning and contains information to understand, scope, time, and cost….

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A condition or occurrence that might restrict, limit, or regulate the project. Generally outside the control of the project team.

A

Constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Circumstances and events that are expected to occur for the project to be successful. Outside the total control of the project team.

A

Assumptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The Process of Defining, Preparing, and Coordinating all subsidiary plans and integrating them into the Project Management Plan.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Charter Baseline (3)

A
  1. Scope
  2. Schedule
  3. Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Subsidiary Management Plans:

Scope Management

A
  1. Scope Management
    1a. Scope Management Plan
    1b. Requirements Management Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Subsidiary Management Plans:

Time Management

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Subsidiary Management Plans:

Cost Management

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Subsidiary Management Plans:

Quality Management

A

Quality Management Plan

Process Improvement Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Subsidiary Management Plans:

Human Resource Management

A

Human Resource Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Subsidiary Management Plans:

Communications Management

A

Communications Management Plan

17
Q

Subsidiary Management Plans:

Risk Management

A

Risk Management Plan

18
Q

Subsidiary Management Plans:

Procurement Management

A

Procurement Management Plan

19
Q

Subsidiary Management Plans:

Stakeholder Management

A

Stakeholder Management Plan

20
Q

The Project Management Plan defines HOW a project is ______, ______ and ______.

A

Executed, Monitored and Controlled

21
Q

The process of managing and performing work defined in the Project Management Plan and implementing approved changes to achieve project objectives.

A

Direct and Manage Project Work

22
Q

Processes identifies what change requests are approved, declined or rejected.

A

Perform Integrated Change Control Process

23
Q

Monitors and controls progress to meet performance objectives by _____, _____, and _____.

A

Tracking, reviewing and reporting.

24
Q

What are the physical or electronic representation of Work Performance Information and are subset of Project Documents? Aids in the decision making process when evaluating change requests.

A

Work Performance Reports

25
What reviews all Change Requests, and approved changes, manages changes to deliverable organizational process assets, project documents and the project management plan; and communicates their disposition.
Perform Integrated Change Control
26
What is the idea of seeing if the plan is in alignment of the scope. "Piece of keeping the wheels on."
Change Control
27
3 Configuration Management Activities
1. Configuration Identification 2. Configuration Status Accounting 3. Configuration Verification and Audit
28
Process to finalize all activities across all Process groups to formally complete the project or phase.
Close Project or Phase Process
29
2 Analytical Techniques used in project closeout...
Regression and Trend Analysis. | Helps you go back and analyze the projects. Give you raw data to use in next project.