Knowledge areas Flashcards

(51 cards)

0
Q

EVM Terms

  • PV
  • EV
  • AC
  • BAC
  • EAC
  • ETC
  • VAC
A

– PV: plan to value (budgeted value of work planned to be done)
– EV: earned value (budgeted value of work completed)
– AC: actual costs (actual cost of work completed – total)
- BAC: budget at completion (cost baseline)
– EAC: estimate at completion (expected total cost aka: forecast)
- ETC: estimate to complete (expected remaining cost, from now)
- VAC: variance at completion (expected variance over or under budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

How many knowledge areas are there and what are they?

A

I Saw Tom Chucking Quails Happily while Conversing with Rogue Penguins Swimming.

– Project integration management
– Project scope management
– Project time management
– Project cost management
– Project quality management
– Project human resource management
– Project communication management
– Project risk management
– Project procurement management
– Project stakeholder management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EAV Terminology

  • CV
  • SV
  • CPI
  • SPI
  • EAC
  • ETC
  • VAC
  • TCPI
A

-CV: cost variance. EV-AC (negative is bad positive good)
-SV: schedule variance. EV-PV (negative is bad positive good)
-CPI: cost performance index. EV/AC (under 1 is bad, over 1 is good)
-SPI: schedule performance index. EV/PV (under 1 is bad, over 1 is good)
-EAC: estimate at completion.
AC+(BAC-EV) - atypical
BAC/CPI - assumes rate of spending will continue – typical)
-ETC: estimate to complete. EAC-EC (value of work remaining)
-VAC: variance at completion. BAC-EAC (negative is bad, positive is good)
-TCPI: to complete performance index.
(BAC-EV)/(BAC-AC) (optimal rate to complete budget)
(BAC-EV)/(EAC-AC) (original budget can’t be achieved)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Point of total assumption

A

Point at which the seller has to pay for any further cost overruns

PTA = Target price + ((ceiling price-Target price)/buyers share)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Procurement management

– FFP
– FPIF
– FP–EPA
– CPPC
– CPFF
– CPIF
– CPAF
– T&M
A

– FFP: Firm fixed price (most common, solar covers cost increases)
– FPIF: Fixed price plus incentive fee (includes performance bonus)
– FP–EPA: Fixed price with economic price adjustment (used on long-term projects. Buyer covers inflation costs. Buyer has some risk)
– CPPC: Cost plus percentage of cost (seller reimburses plus a percentage)
– CPFF: Cost plus fixed fee (reimbursed for cost plus fixed $ fee)
– CPIF: Cost plus incentive fee (reimbursed for cost-plus objective bonus)
– CPAF: Cost plus award fee (reimbursed for cost plus objective bonus)
– T&M: Time and Materials (moderate risk to buyer)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop project charter

A

Initiating– Project integration management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identify stakeholder

A

Initiating – project stakeholder management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Develop project management team

A

Planning – project integration management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Plan scope management

A

Planning – project scope management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Collect requirements

A

Planning – project scope management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define scope

A

Planning – project scope management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Create WBS

A

Planning – project scope management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Plan schedule management

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define activities

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sequence activities

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate activity resources

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Estimate activity duration

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Develop schedule

A

Planning – project time management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Plan cost management

A

Planning – project cost management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Estimate cost

A

Planning – project cost management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Determine budget

A

Planning – project cost management

21
Q

Plan quality management

A

Planning – project quality management

22
Q

Plan human resource management

A

Planning – project human resource management

23
Q

Plan communication management

A

Planning – project communication management

24
Plan risk management
Planning – project risk management
25
Identify risks
Planning – project risk management
26
Perform qualitative and or quantitative risk analysis
Planning – project risk management
27
Plan risk responses
Planning – project risk management
28
Plan procurement management
Planning – project procurement management
29
Plan stakeholder management
Planning – project stakeholder management
30
Direct and manage project work
Executing – project integration management
31
Perform quality assurance
executing – project quality management
32
Acquire project team
Executing – project human resource management
33
Develop project team
Executing – project human resource management
34
Manage project team
Executing – project human resource management
35
Manage communication
Executing – project communication management
36
Conduct procurement
Executing – project procurement management
37
Manage stakeholder engagement
Executing – project stakeholder management
38
Monitor and control project work
Monitoring and control – project integration management
39
Perform integrated change control
Monitoring and controlling – project integration management
40
Validate scope
Monitoring and controlling – project scope management
41
Control scope
Monitoring and control – project scope management
42
Control schedule
Monitoring and control – project schedule management
43
Control costs
Monitoring and control – project cost management
44
Control quality
Monitoring and controlling – project quality management
45
Control communication
Monitoring and controlling – project communication management
46
Control risk
Monitoring and controlling – project risk management
47
Control procurements
Monitoring and controlling – project procurement management
48
Control stakeholder engagement
Monitoring and controlling – project stakeholder management
49
Close project or phase
Closing – project integration management
50
Close procurements
Closing – project procurement management