Lectures 3-4 Flashcards

1
Q

What are the first four elements that form a Project Definition?

Please Give Sam Cold drinks

A
  1. Purpose (why) repeat the mission of the
    organization and purpose of the RFP
  2. Goals and objectives - state the problems to be solved and the outcomes of the project (SMART)
  3. Success criteria – list the measurable,
    verifiable results that determine the
    success of the project
  4. Project context – if applicable, state how
    this project relates to others in the
    program (identify added value/synergies)
  5. Project dependencies – if applicable, document dependencies that
    may affect the outcome of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the seven other elements that form a project definition?

SARS AC

A
  1. Scope – clearly defines the boundaries of the project and also what
    is out of scope (optional)
  2. Project assumptions – communicate the underlying assumptions of
    the presented scope of work is dependent upon .
  3. Constraints and risks – list factors that will limit options of the
    project and uncertainties that may change the scope of work
    (weather)
  4. Identify the key stakeholders – First Nations, local residents, NGOs,
    regulators.
  5. Define the key approach – why use this approach and not an
    alternate approaches, if applicable
  6. Preliminary cost estimates, schedule and resources required to
    complete the Project
  7. References
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do we define a Project?

A

Preliminary Site Analysis
Construct Conceptual Model of Site
Identify Stressors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Work Breakdown Structure?

A

WBS is a logical, hierarchical breakdown and representation of the work required by the project.

Purpose is to breakdown the project into smaller, more manageable components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimating Costs - Approaches?

A
  • Bottom-up: detailed estimates from the lowest task of the WBS
  • Effort distribution by phase: 10% Initiation, 10%Planning, 40% Construction….
  • Heuristic: based on experience, no historical data. Expert judgement
  • Parametric: historic data statistical relationships. Number of work units * duration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly