Level 1,2,3 Questions Flashcards
Can you tell me how you’ve advised a client on the foundation selection?
Outside area of competence BUT:
Soil type
Cost/Time
Type of structure
Buildaibility (access, proximity, site conditions)
What is piling?
Where RC concrete is in the ground to take the load of the structure
Typically reinforced
Used on large buildings with heavy load and subsoil is not able to take the load
What are the advantages of CFA piling?
Low levels of noise and vibration
High load bearing
Suitable for a wide range of ground conditions
What is a typical ground floor slab build up?
Finish
Screed
DPM
Insulation
Slab
Sand/Blinding
DPM below slab
Tell me about the two ways basements can be constructed?
1) retaining wall and raft basement
2) Piled basement
What are the different basement grades? How might these be achieved?
Grade 1 - Some leakages and damp areas tolerable. Local drainage may be required.
Grade 2 - No water penetration but damp areas tolerable dependant on the intended use. Ventilation may be required to control condensation.
Grade 3 - Dry environment. No water penetration. Additional ventilation, dehumidification or air conditioning appropriate to intended use.
Grade 4 - Totally dry environment. Requires ventilation, dehumidification, or air conditioning appropriate to intended use.
They could be achieved through mastic asphalt tanking, cavity drain installation and waterproofing concrete
Tell me the 7 stages of the RIBA Plan of Work
0 - Strategic Definition
1 - Preparation and Briefing
2 - Concept Design
3 - Spatial Coordination
4 - Technical Design
5 - Manufacturing and Construction
6 - Handover
7 - Use
When was it (RIBA plan of work) published?
2020 was the latest, 2013 before that
How does the RIBA plan of work relate to your role?
It relates to my role as a QS because it sets out clearly what is required as an output from myself at each RIBA Stage, as well as overall project milestones/outputs.
What happens in Stage 0 of RIBA plan of work?
Client requirements are established and business case is drafted
What happens in Stage 1 of RIBA plan of work?
1) Project brief is established
2) Undertake Feasibility Studies
3) Agree Project Budget
4) Source Site Information including Site Surveys
5) Prepare Project Programme
6) Prepare Project Execution Plan
7) Discussions around procurement strategy
What happens in Stage 2 of RIBA plan of work?
1) Prepare Architectural Concept incorporating Strategic Engineering requirements and aligned to Cost Plan, Project Strategies and Outline Specification
2) Agree Project Brief Derogations
3) Undertake Design Reviews with client and Project Stakeholders
4) Prepare stage Design
5) Programme
6) Obtain pre-application Planning Advice and possibly submit planning app
What happens in Stage 3 of RIBA plan of work?
1) Cost plan
2) Further design coordination
3) Definitely submit detailed planning app
What happens in Stage 4 of RIBA plan of work?
1) Prepare Construction Phase Plan
2) Submit F10 if applicable
3) Finalise design
4) Tender to contractors or PCSA if two stage
5) Typically a PTE is done
What happens in Stage 5 of RIBA plan of work?
Construction
How many units was LTH?
54 units
How many units was QSL?
110
What is MMC?
Modern methods of construction - is a fast way of delivering new buildings, by maximising the efficiency of material and human resources.
Which worked out better in terms of cost between Brick Slip and Traditional Brick Masonry
Typically 150/200 more than a traditional brick masonry wall
What would have been the build up for brick slip?
brick slip like 25mm
rails that brick slips are hung onto
brackets
then standard wall build up e.g.
minerall wool insulation
breather membrane
Cement board
SFS stud with insulation inside
2 layers plasterboard
What is the build up for traditional brick masonry?
Traditional brickwork with brick ties 102.5mm
50mm cavity
120mm rigid insulation,
12.5mm Siniat Weather Defence Board
100mm Metsec with 100mm mineral wool insulation within
Vapour control layer
2nr layers plasterboard
overalll thickness 415mm
What was the cost/m2 difference between brick slip and traditional masonry?
ANSWER
How would the bathroom pods have been stored?
Offsite typically then just in time delivering for installation
How did you account for programme when comparing the two methods (traditional vs MMC)?
Programme for traditional was circa 90 weeks, MMC contractor provided an 82 week programme.