Midterm Flashcards

1
Q

Value is an interplay between ___ & ___

A

price & quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You must be on the same side as ___, or your supply chain doesn’t exist.

A

Government/ regulators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NGO stands for

A

non-governmental organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Helping set the strategy for how demand will be met (long term/ product categories) is called

A

Strategic forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimating demand in the short term (weeks or months/ product lines) is called

A

Tactical forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Dependent demand is

A

Demand for a product or service caused by the demand for other products or services. (Smores- package deals)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Capacity is

A

the ability to hold, receive, store or accommodate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To minimize costs, you should utilize ___% capacity

A

100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Every project begins with

A

a statement of work ( a written description of objectives)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The 4 things that make up a statement of work are

A

Specific start/ end dates. Specifications of outcomes. Budget. Milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project creep is

A

extra funds just in case we need to crash a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BCWS stands for

A

Budgeted cost of work scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

BCWP stands for

A

Budgeted cost of work performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Schedule variance: If BCWP-BCWS is negative, that means

A

the project is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Schedule variance: If BCWP-BCWS is positive, that means

A

the project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The schedule performance index=

A

% of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

If cost variance is negative, that means

A

the project is over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

If cost variance is positive, that means

A

the project is under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

If (cost performance index) BCWP/ AC is < 1, that means

A

the cost of completing the work is higher than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

If BCWP/ AC is = 1, that means

A

the cost of completing the work is as planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

If (cost performance index) BCWP/ AC is > 1, that means

A

the cost of completing the work is lower than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the most important tool for project management?

A

EVM- earned value management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

EVM is a tool that manages

A

the time and money of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Lead time is

A

the time needed to respond to a customer order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Lead time is dependent on
raw materials & customization
26
Producing a certain quantity based on a forecasted production plan is called
Push
27
Producing a certain quantity based on orders from a customer is called
Pull
28
Most companies are moving away from (push/pull) and toward (push/pull) Because:
away from push to pull Because: it creates more value in customization, produces less waste, and minimizes downtime, etc.
29
Little's Law says there is a relationship between
inventory, throughput, and flow time
30
Little's Law is
Inventory= Throughput rate X flow time
31
What are some things you can do to lower task times?
Split the task. Share the task. Parallel workstations. Hire more skilled workers. Work overtime. Redesign.
32
Service organizations are classifies according to
who is the customer
33
Service-System Design Matrix Chart
High customer contact= high sales opportunity but low efficiency. Low customer contact= low sales opportunity but high efficiency
34
Poka Yokes are
Procedures that block the inevitable mistake from becoming a service defect.
35
What are the 3 Ts of Poka Yokes?
1. Task to be done 2. Treatment accorded to the customer 3. Tangible features of the service facility
36
λ=
Arrival time
37
μ=
service rate
38
Average utilization of the teller=
p which = ratio of total arrival rate to service rate
39
Average number=
L
40
Average wait=
W
41
What is Operations and Supply Management?
Operations and supply management (OSM): the design, operation, and improvement of the systems that create and deliver the firm’s primary products and services
42
Efficiency is
Doing something at the lowest possible cost or using the smallest input of resources
43
Effectiveness is
Doing the right things to create the most value for the company
44
Value is
Quality and Price…the attractiveness of a product relative to price.
45
What is Operations and supply strategy?
: setting broad policies and plans for using the resources of a firm and must be integrated with corporate strategy.
46
What are the 7 competitive dimensions?
Price: make the product or deliver the service cheap Quality: make a great product or deliver a great service (design and process) Delivery Speed: make the product or deliver the service quickly Delivery Reliability: deliver it when promised Coping with Changes in Demand: change its volume Flexibility and New Product Introduction Speed: change it Other Product Specific Criteria: support it (tech support, meeting a launch date, customizable etc.)
47
What is straddling?
When a company tries to match benefits of one successful position while maintaining its existing position. This often creates a problem if trade-offs need to be made.
48
What is Independent demand?
the demand for a product or service that cannot be derived directly from that of other products
49
What are the 6 components of demand?
``` Average demand for a period of time Trend Seasonal element Cyclical elements- elections, wars, economic conditions Random variation Autocorrelation ```
50
What are the Three basic types of forecasts?
Qualitative Time series analysis Causal relationships
51
Time series analysis is based on the idea that
data relating to past demand can be used to predict future demand
52
Strategic capacity planning is
an approach for determining the overall capacity level of capital intensive resources, including facilities, equipment, and overall labor force size
53
The basic notion of economies of scale is
that as a plant gets larger and volume increases, the average cost per unit of output drops.
54
Planning service capacity is different from Manufacturing capacity because: (3)
Time: goods can not be stored for later use and capacity must be available to provide a service when it is needed Location: service goods must be at the customer demand point and capacity must be located near the customer Volatility of demand: much greater than in manufacturing
55
What are the key themes of the audit in the Apple supplier responsibility report?
``` Worker empowerment Protection of worker rights Worker health and safety Environmental impact Ethics Management Systems (self and supplier accountability) ```
56
What are the 4 perspectives on the balanced scorecard?
Financial: encourages the identification of a few relevant high-level financial measures. In particular, designers were encouraged to choose measures that helped inform the answer to the question "How do we look to shareholders?" Customer: encourages the identification of measures that answer the question "How do customers see us?" Internal business processes: encourages the identification of measures that answer the question "What must we excel at?" Learning and growth: encourages the identification of measures that answer the question "How can we continue to improve, create value and innovate?".
57
What is project management?
Planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project.
58
What are the 4 steps to CPM?
Identify each activity to be done and estimate how long it will take Determine the required sequences and construct a network diagram Determine the critical path Determine the early start/finish and late start/finish schedule
59
What is a Customer order decoupling point?
where inventory is positioned to allow entities in the supply chain to operate independently
60
What are the 4 types of firms? describe them
Make-to-stock firms: Firms that serve customers from finished goods inventory Assemble-to-order firms: firms that combine a number of preassembled modules to meet a customer’s specifications Make-to-order firms: that make the customer’s product from raw materials, parts, and components Engineer-to-order firm: firm that will work with the customer to design and then make the product
61
What are the 5 differences between a good and a service?
Tangible vs intangible Service requires Interaction with the customer Services are inherently heterogeneous- they vary from day to day and even hour by hour as a function of the attitudes of the customers and the servers. Services as a process are perishable and time dependent, and can't be stored. Services must comply with the package of features that affect the five senses.
62
What is sustainability?
The ability to meet current resource needs without compromising the ability of future generations to meet their needs.
63
What is the triple bottom line?
Evaluating a firm against social, economic, and environmental criteria p. 26
64
What is project layout?
Where products are made p. 180
65
What is a work center?
a job site where functions are grouped together p. 180
66
What is a manufacturing cell?
a dedicated area where products that are similar in processing requirements are produced. p.180
67
What is a continuous process?
Similar to an assembly line in that production follows a predetermined sequence of steps, but the flow is continuous such as with liquids, rather than discrete. p. 180
68
What is a product-process matrix?
A framework depicting when the different production process types are typically used depending on product volume and how standardized the product is p. 181
69
What is the difference between a functional project and a matrix project?
Functional- each department works on a few projects. | Matrix- each department works on all projects.
70
What is the greatest challenge of a pure project?
Organizational goals and policies ignored, removed from headquarters
71
What is the greatest limitation of a functional project?
Little to no cross utilization of resources
72
What is the greatest challenge of a matrix project?
Agreement on the strength of the relationship or who owns the human resource
73
What are the 4 samples of qualitative forecasting techniques? p.75
Market research. Panel Consensus Historical Analogy Delphi Method- Conceals the identity of the individuals participating in the study. Everyone has the same weight.
74
What is Workstation cycle time?
a uniform time interval in which a moving conveyor passes a series of workstations
75
What is Assembly-line balancing?
assigning all tasks to a series of workstations so that each workstation has no more than can be done in the work station cycle time
76
What decides if something is co-productive? (and therefore a service)
Involvement of customer in interaction
77
An entity’s Process Domain includes
all processes that are directly performed, directed, controlled by the entity.
78
PCN stands for
Process Chain Networks
79
Suggestions for managing queues include:
Segment the customer Train your servers to be friendly Inform your customers of what to expect Try to divert the customer’s attention when waiting Encourage customers to come during slack periods
80
An example of a single channel, multiphase is
A car wash
81
An example of a multichannel, single phase is
Waiting to buy football tickets.
82
What is the main difference between single channel, multiphase / and multichannel, single phase?
Multichannel, single phase- some customers could be served before others who arrived earlier.
83
Formula for exponential smoothing is | Interpret: Ft-1 + alpha (A- Ft-1)
last forecast + alpha (actual quantity demanded- last forecast)