misc Flashcards

(82 cards)

1
Q

Who is responsible for coordinating with agencies when testing must be conducted?

A

The contractor is responsible for coordinating with agencies when testing must be conducted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are two components that have the greatest impact on a contractor’s bid?

A

Labor and materials have the greatest impact on a contractor’s bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

As-built drawings

A

As-built drawings are typically prepared by the general contractor to the original drawings indicating on-site changes made to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Record drawings

A

Record drawings are drawn and compiled by the architect as a set of on-site changes made specifically for the owner as per the architect and owner contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

4 types of SCHEDULES:

A

BAR / GANTT CHARTS: BIG PROJECTS, most often used type, also during construction
The disadvantage of the Gantt chart is that it does not show the dependency of tasks to each other and it does not show which tasks are ‘critical’ to finishing the project on time. This is where the Critical Path Method (CPM) comes in.

(CPM) CRITICAL PATH METHOD:
this process determines which activities are “critical” (i.e., on the longest path) and which have “total float” (i.e., can be delayed without making the project longer)
-Critical path drag analysis allows managers to prioritize activities for the effective management of project, and to shorten the planned critical path of a project by pruning critical path activities, by “fast tracking” (i.e., performing more activities in parallel), and/or by “crashing the critical path” (i.e., shortening the durations of critical path activities by adding resources).

MILESTONE CHARTS: SMALL PROJECTS

WALL SCHEDULE: analog, whole project team, pm prepares major items to be placed on wall, at beginning of medium to big project, not during construction, converted to bar chart when set

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Statute of limitations

A

Statute of limitations - only starts after the defect is discovered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Statute of repose

A

Statute of repose - timeframe in which claims must be made, begins on the date of substantial completion. Time limits for each statute are quite different across all states, but usually, the statute of repose has a longer time frame than the statute of limitations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Agency

A

Agency - For agency to occur there must be 3 parties: principal, agent, and a third party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Negligence

A

Negligence
legal duty established between 2 parties
BREACH OF THAT DUTIE
BREACH OF DUTIE CAUSED DAMAGE OR INJURY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Betterment

A

Betterment is an improvement that adds value to a property or facility.
It involves consideration of both measure of damages and mitigation. Generally, if repair works are carried out to a higher standard than was necessary, the betterment will be deducted from any damages claimed. However, if the claimant had no choice other than to carry out the works in that way, then no deduction will be made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Privity

A

Privity - a contract cannot be used for a legal claim except by those who are parties to it.

a contract cannot confer rights or impose obligations upon any person who is not a party to the contract. The premise is that only parties to contracts should be able to sue to enforce their rights or claim damages as such.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Vicarious liability

A

Vicarious liability is a form of a strict, secondary liability that arises under the common law doctrine of agency, respondeat superior, the responsibility of the superior for the acts of their subordinate or, in a broader sense, the responsibility of any third party that had the “right, ability or duty to control” the activities of a violator.
Typically, the architect’s project representative can handle most tasks with the exception of approving and rejecting work, which remain part of the architect’s authority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Indemnity clauses

A

Indemnity clauses are intended to keep parties from being brought into lawsuits for issues that arise which are beyond their control. Indemnification clauses hold harmless both owner and architect for claims resulting from the performance of work by the contractor or others with whom the architect has no contractual relationship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The Spearin Doctrine

A

The Spearin Doctrine is the difference between defect-free documents and an architect’s professional standard of care. Costs associated with the Spearin Doctrine are borne by the owner, as the architect developed them in accordance with the standard of care and not as a result of negligence. This is not a case where betterment comes into play. The contractor is not liable for loss or damage as a result of defective designs, plans, or specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is the architect responsible for meeting performance standards?

A

No, Meeting performance standards depends on many factors outside the architect’s control, including maintenance and operations, manufacturing, and installation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Mediation

A

Mediation
Per aia required first step
Not legally binding
Parties try to come to a settlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Arbitration

A

Arbitration
Select decision maker / no juries
Private
Faster
Limited discovery
Lower attorney fee
Higher hard cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Litigation

A

Litigation
Appointed decision maker
Public
slower
Unlimited discovery
Higher attorney fee
Lower hard cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

general obligation bond

A

general obligation bond is a municipal bond backed by the credit and taxing power of the issuing jurisdiction, rather than the revenue from a given project. Big Public projects are usually financed like that. General obligation bonds are issued with the belief that a municipality will be able to repay its debt obligation through taxation or revenue from projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

performance bond aka contract bond

A

performance bond aka contract bond - guarantee by surety that sufficient funds will be available to complete the project, should contractor default during construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Bid Bond

A

Bid Bond - type of bid security that bidders submit along with their bid. Gets returned if not selected. If selected contractor does not do work according to bid, owner gets to keep it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Payment bond

A

-Payment bond: labor & materials payment bond - guaranteeing that contractor will pay subs and vendors - protects against mech liens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Revenue bonds

A

Revenue bonds finance projects that generate revenue. The money made by the project goes to paying off the bonds. Toll roads and bridges are examples of projects paid for by revenue bonds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

mill levy

A

-A mill levy is used to set property tax rates. For example, if the mill levy is 20, the tax is $20 for every $1000 of assessed property value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Phases of IDP Project Delivery
Phases of IDP Project Delivery Conceptualization This is when collaboration is most crucial. The key project participants will assemble to analyze any potential issues relying on each others’ various fields of expertise. Design All the evaluations from the conceptualization phase are now integrated with the main project goals and regulatory considerations to optimize costs and reduce waste. Implementation It’s during this phase where the computer-modeling software comes into play. By inputting all the information gathered from the project teams and the design phase, the software will then crunch the raw data and predict the project’s performance and outcome. Construction This is when all the benefits of collaboration and careful planning comes to fruition. If the previous phases were performed properly, this phase should be relatively painless, resulting in minimal delays, waste, and scheduling problem
26
IDP - During pre-construction architect is involved in?
Agency review - includes early involvement of permitting agencies, authority have a dress diction a HJ in the building code review process. Tim data may be shared to streamline process. Architect would work with a HJ to ensure code compliance. Buyout - selecting suppliers and finalizing prices from any remaining subcontractors and vendors not part of IPD. No bidding, negotiating, because key stakeholder is already involved.
27
B101 Basic services: (outside of design phases)
Research applicable design criteria Attend project meetings Comunicate w members of the project team Report progress to the owner Coordinate arch’s services w/owners provided services/ consultants Schedule for arch services, as soon as applicable after signing of contract
28
Surety
-Surety - bonding agency, company that puts up money (gc is licensed and bonded, have a license and have surety)
29
Responsible bidder:
-Responsible bidder: demonstrates financial capacity to do the work
30
Responsive bid
-Responsive bid: all bidding requirements have been met
31
VBS
-VBS - value based selection - multiple criteria
32
QBS
-QBS - qualifications based selection
33
-Bid shopping
-Bid shopping is when a general contractor discloses a subcontractor's bid to another subcontractor in the attempt to get a better price. Bid shopping lowers construction quality, worsens the business environment, and is considered unethical. In some instances, bid shopping can be illegal.
34
-Bid soliciting
-Bid soliciting is when an architect or owner puts a project out to bid by announcing it in the media or by private channels through invitations or requests for proposals.
35
-Bid fraud
-Bid fraud is the same as bid tempering and bid rigging.
36
waiver of subrogation
A waiver of subrogation means that the architect and the owner cannot sue each other for items covered by their property insurances.
37
Indemnification would be in effect in the following situations:
Indemnification would be in effect in the following situations: Protection against damage to the site by the contractor’s work Injury of staff at construction site Claims by the neighbors on adjoining site
38
Consequential damages waived by the owner would include:
Consequential damages waived by the owner would include: Loss of profit due to delays in the work Loss of income due to delays in the work Rental on the property being built on
39
When submitting, for the owner's approval, a schedule for the performance of his services, which of the following should the architect include?
- Commencement of construction date - Substantial completion date - Allowance for the owner's review - Allowance for the owner's consultants performance - Allowance for approval of submissions by AHJ's.
40
During the procurement phase, the architect shall assist the owner with which of the following?
- Procuring the reproduction of Bidding Documents - Maintaining a log of distribution and retrieval of the amounts of deposits - Organizing and conducting the opening of the bids - Participating in negotiations with prospective contractors
41
When does title-ship of the Work start to transfer from the contractor to the owner?
-With each application for payment
42
Construction typically begins when?
Construction typically begins when owner issues notice to proceed, which is a letter notifying the contract and they're authorized to proceed with work. Letter can be sent by architect and owner's direction, but I take themselves cannot direct the work to begin.
43
Construction phase ends when?
Construction phase ends when the contractor received the final payment.
44
If the architect withholds certification for payment from gc for not paying the subcontractor, the owner may ...
If architect withholds certification for payment owner may at his sole option, issued joint checks to the contractor into any subcontractor or supplier to whom the contractor failed to make payment. If owner makes payment by joint check on her she'll notify architect and contractor shall reflect the payment on its next application for payment.
45
Within 10 days of receiving a dispute a claim from owner or contractor, initial decision maker must: (4options)
- Suggest a compromise - Except or reject the claim - Advised the parties that initial decision maker is unable to resolve the claim due to a conflict of interest or lack of sufficient information - Request additional supporting data from the claimant
46
Product substitutions
Product substitutions can be managed with CSI Form 13.1A standards substitution request format
47
Two scenarios when substitutions during the construction phase be required or allowable:
The owner initiates a substitution The product is unavailable
48
Action submittals
Action submittals: Shop drawings Coordination drawings Product data Samples
49
Informational QAQC submittals:
Informational QAQC submittals: Design data Test reports Certificates Manufacturer’s instructions
50
Project record documents
Contract drawings Project manual Agenda Contract modification Submittals Product data Shop reports Samples Test reports Other documents from the contractor
51
Scope creep
Scope creep may occur if the architect does not closely monitor change orders or construction change directive
52
Substantial completion
Substantial completion: - Sufficiently complete according to contract documents to allow owner use of intended purpose - Often C of O - Punch-list is compiled by contractor and maintained by architect - The warranties begin
53
Final completion
Final completion: -Complete according to contract documents. -Date of application for final payment becomes the date of final completion -Punchlist is completed by contractor Closeout documents are submitted -Owner takes full responsibility for project unless otherwise agreed upon
54
Submittals near completion of project
- Written notices of substantial and final completion - Final application for payment - Record documents - Maintenance or attic materials - Certificates of payment - Operations and maintenance data - Releases of liens - Consent of surety to final payment - Contractor certificate of substantial and final completion - Outstanding items that have not been included in previous change order, architect needs to prepare a final change order. Used to make needed adjustments in contract sum.
55
Procurement Documents
The project manual Construction drawings Addenda
56
The project manual
Bidding requirements Contract forms Specifications
57
Bidding requirements
Invitation to bidders Pre-qualification forms Instructions to bidders Additional information Bid forms Supplements to bid forms Bid security form Subcontractor list Substitution request form Request for information form
58
Contract forms
Contract forms Sample agreement contractor owner Sample performance bond Sample labor and materials payment bond Sample certificate or insurance and list of insurance requirements Simple general conditions of the contract Supplementary conditions
59
types of Specifications
- Proprietary (Closed) Spec: does not allow for substitution, and typically used to control aesthetics, function, and quality. 
• Identify name, model number, finish type, and submittal requirement. - Descriptive (Open) Spec: used in competitive bidding, and does not give level of control in closed spec.
• Describe characteristics, materials, finishes, workmanship, and fabrication of products and give list of comparable manufactures. - Performance Spec: used with vendors who propose products they think will meet requirements
• Describe only the desired/required results. Give no characteristics or manufactures. - Reference standard spec: description based on performance of material/assembly in comparison to reference standards set by accepted authority. For example ASTM (American standard for testing and materials), ANSI , UI
60
Construction drawings
contract drawings are bound separately from project manual, and show size form and the presentation of materials and systems and the relationships between them
61
Addenda
Issued to all registered bidders no later than 5 days before receipt of bids to get the bidders in proper opportunity to study it and modify the proposals accordingly
62
Contract documents
Contract forms Specifications Construction drawings Addenda NOT the bidding requirements
63

3 modifications to the contract:
- G701 Change order: change to contract documents to time or money or scope or combination - G710 architect's supplemental instructions (ASI). when would not affect project time or cost, i.e. scope. the architect is able to issue a change in the work without further approval needed. - G714 Construction change directive: construction continues as directed, issue moves to Mediation/arbitration after, gets put into contract documents after resolution as regular change order
64
4 phases of building commissioning:
4 phases of building commissioning: Design Phase Construction Phase Acceptance Phase Post-Acceptance Phase
65
commissioning
Commissioning of the energy system as a prerequisite for LEED certification OPR owners project requirements, a summary of the critical planning requirements and owner expectations OPR is developed into a basis of design BOD document during the design phase. The BOD explains how the OPR have been satisfied by the proposed design.
66
submittals, according to SectionFormat:
Product Data Shop Drawings Samples Design Data Test Reports Manufacturers' Certificates and Instructions Closeout Submittals Although mock-ups and field samples are usually required in the specifications and also need to be approved by the architect, they are not considered to be submittals. According to SectionFormat, Mock-ups and Field Samples are considered Quality Assurance items, not submittals.
67
who is the initial decicion maker in a CM-A contract
Similarly to a traditional design-bid-build delivery method, using an AIA Document A201, the architect is also the IDM, when using a CMa delivery method.
68
who is preparing change orders in a cm-a contract
Contrary to the typical design-bid-build delivery method, the CMa prepares change orders and construction change directives. Change orders must be signed by the CMa, the architect, the owner and contractor as well.
69
supplemental services
Providing facility support services Providing Fast-track design services Preparing multiple bid packages Post-occupancy evaluation (Supplemental Services are services that are not included as Basic Services but are identified as the architect's responsibility at the time the agreement is executed. Additional Services are services that may arise as the project proceeds.)
70
additional services
- Changing or editing previously prepared Instruments of Service - Assistance to the Initial Decision Maker, if other than the Architect (**Supplemental Services** are services that are not included as Basic Services but are **identified** as the architect's responsibility **at the time the agreement is executed**. **Additional Services** are services that may **arise as the project proceeds**.)
71
Which parties need to sign a G704 – Certificate of Substantial Completion? Select all that apply.
Architect Owner Contractor
72
According to AIA document B133, when does the architect's construction administration role start?
CMC Per AIA documents B101, the architect's CA responsibilities start when the owner awards the contract for construction. However, per AIA document B133, only below would mean the beginning of these functions by the architect. - After the owner's approval of the CM's Guaranteed maximum price (GMP) - After the owner's approval of the CM's control estimate - After the owner issues a notice to proceed
73
Which documents must the contractor submit to the architect, before a certificate for the final payment can be issued?
- Consent of surety to final payment - Affidavit stating that payrolls and materials have been paid The contractor must only submit a waiver of liens, if required by the owner, it is not mandatory.
74
If the Contractor encounters conditions at the site that... differ materially from those indicated in the Contract Documents..., the Contractor shall...?
If the Contractor encounters conditions at the site that... differ materially from those indicated in the Contract Documents..., the Contractor shall promptly provide notice to the Owner and the Architect before conditions are disturbed and in no event later than **14 days** after first observance of the conditions". Only upon the architect's investigation and determination if the conditions were, in fact, different from those indicated in the contract documents, would the contractor be entitled to a change to the contract sum and/or time. The contractor should not have disturbed the conditions without notifying the owner and the architect, so he/she would probably be responsible for the extra time/cost incurred.
75
Who is (are) the party (ies) responsible for contacting entities providing utilities to the Project?
Architect B101-2017 Standard Form of Agreement Between Owner and Architect states that "The Architect shall contact governmental authorities required to approve the Construction Documents and entities providing utility services to the Project. **The Architect shall respond to applicable design requirements imposed by those authorities and entities."**
76
Who is usually responsible for providing and paying for test borings, test pits and percolation tests?
The owner, as the party responsible for providing services of geotechnical engineers, is usually responsible for providing these services. See article 5.5 of AIA Document B101-2017 Standard Form of Agreement Between Owner and Architect. It states the following: "The Owner shall furnish services of geotechnical engineers, which may include test borings, test pits, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, seismic evaluation, ground corrosion tests and resistivity tests, including necessary operations for anticipating subsoil conditions, with written reports and appropriate recommendations."
77
How should the contractor proceed if, while doing some earthwork in preparation for the foundations, he discovers conditions that are substantially different than the ones stated in the contract documents?
Stop work and notify the owner and architect within 14 days
78
At which point does the AIA B101 agreement terminate?
The contract terminates **one year after substantial completion**. Refer to AIA Document B101 Standard Form of Agreement Between Owner and Architect , Article 9.8 Termination or suspension
79
What is the deadline before which GC has to address all issues on the punch list?
The architect makes an assessment and determines how long the contractor has to address all items on a punch list.
80
the Owner occupies a portion of the building after the Architect has deemed the project is substantially complete. The Owner notices a hole in the wall that wasn't noted on the Architect's punch list. Who is responsible for fixing the issue?
When an Owner occupies the building after substantial completion, any error or mistake not noted in the punch list is the Owner’s responsibility.
81
What is a proctor test?
A proctor test is a method of experimentally determining the optimal moisture content at which a given soil type will become most dense and achieve its maximum dry density. The term Proctor is in honor of R. R. Proctor, who in 1933 showed that the dry density of a soil for a given compactive effort depends on the amount of water the soil contains during soil compaction
82