Mock Interview (PK & Doug) - Competencies Flashcards

(82 cards)

1
Q

Building Pathology

\what is the definition of subsidence?

A

Sinking of the ground because of underground material movement. It’s due to external factors such as defective drains or tree roots

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Building Pathology

What would settlement be; what is the difference between subsidence and settlement?

A

Subsidence is due to external factors where as settlement is a design flaw.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Building Pathology

Have you looked at subsidence issues before; what are the typical symptoms?

A

Tapered cracking
Cracking both internally and externally
Cracks are wider at the top then the bottom

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Building Pathology

How are you going to assess that once you suspect that their is subsidence?

A

Monitor for 12 months
Calipers to see if the movement was on-going

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Building Pathology

Subsidence - what about further investigations?

A

Dig out around the foundation
CCTV survey of the drains
Check for leaking water/waste pipes
Nearby trees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sulphate Attack at Withernsea

How was that concluded what happened in the end?

A

Following an on-site inspection I advised my client to remove the floor slab and sub-base.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sulphate Attack at Withernsea

What was your diagnosis?

A

Visual assumption indicated towards sulphate attack to the concrete floor slab. The slab was at a point in which immediate replacement was required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Sulphate Attack at Withernsea

Are there any other further investigations you could be doing before going from a visual analysis to breaking out the slab?

A

You could undertake a test. ???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Construction Technology

How do you calculate the u-value?

A

First you work out the R-value of each material by doing the following:

You workout the resistance of a material by dividing the thickness by the thermal conductivity.

The U-value is then worked out by adding up all the total R-value and dividing by 1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Construction Technology

What checks might you do for a flat roof build-up?

A

U-value
Interstitial condensation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Construction Technology

Did you think the lightweight walls are relevant to a raft foundation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Construction Technology

What is the primary reason you might use a raft foundation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Contract Administration

What is the differences between NEC and JCT?

A

NEC:

Project Manager
Programme always need to be up-to-date
Early Warnings for both PM and Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contract Administration

You recommended a tender evaluation of 90/10 split. How did you evaluate the quality element?

A

I evaluated the contractor on his employment skills plan, method statement and programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contract Administration

How did you work out the tender evaluation scoring?

A

There’s an equation that you follow i.e:

very good programme you may give them a 9 or 10. Very poor you may give them a 2 or 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contract Administration

Are there any rules outside of the contract that are applicable to payments within construction projects?

A

The ‘Housing Grants, Construction & Regeneration Act 1996’ also known as the ‘Construction Act’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Contract Administration

How does the Housing Grants, Construction & Regeneration Act 1996 affect you in terms of payments?

A

If the work is expected to be longer than 45 days, interim payments must be made under the act.

Under the NEC (21 day cycle)

  1. Contractor submits their application for payment
  2. Over next 7 days, PM assess the application
  3. PM has 5 days as stated in the act to submit their interim payment certificate to the contractor (Notified sum and final date for payment)
  4. 9 days Final date for payment. Final date before a contract can envoke section 112 of the HGCR Act (right to suspend performance due to non-payment)

If the employer/PM fails to provide an interim payment certificate within 5 days of the due date, the contractor application for payment becomes known as a ‘default payment notice’ under the HGCR Act

Assessment Period - 7 days
Prescribed Period - 14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Contract Administration

What is a Payless notice?

A

If a client intends to pay less than the sum assessed or provided in a valuation then there is a statutory requirement under the HGCR Act 1996 that any party intending to pay less, has to present a pay less notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Contract Administration

You have a job on-site and an interim payment lands on your desk the day you’re due to go on holiday. What is the primary risk under this legislation?

A

Default payment notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Design and Specification

Can you tell me the difference between a performance specification & prescriptive specification?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Design and Specification- Prescriptive/Performance

What are the pros and cons; when might you use one over the over?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Design and Specification

At Hallgate Primary School, you said you did a disabled WC; did you get involved in the drainage?

A

Yes - drainage was already in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Design and Specification

Do you get involved in ramps; what is the building regulations requirement for external ramps?

A

Domestic - its Approved Document M Volume 1

Non-Domestic - Its Approved Document M Volume 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Design and Specification

You said you were involved in specifying some internal work to a corridor; what did you do?

A

To get to one of the classroom you have to pass through another classroom.

The school wanted to introduce a corridor but no impede on the existing classrooms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Design and Specification - Hallgate What materials did you specify for the new corridor?
30 minute fire performing Knauf Partition Wall System - Overall partition width is 102mm - 70mm Knauf C Stud at 600mm centres - 1 layer of 15mm Knauf Performance Plus boarding to each side - 50mm Knauf Insulation Acoustic Roll.
26
Design and Specification - Hallgate Did you consider acoustic performance for the classroom?
I referred to Building Bulletin 93 and Approved Document E.
27
Design and Specification - Hallgate Why did you use timber and not metal stud?
Personal preference. I find the C-studs to be quite flimsy and comparable to timber.
28
Design and Specification - Hallgate What about services; where they go through the wall how did you seal them??
Yes, some services did pass through a compartmentation wall. I ensured the holes which allowed the services to pass through were sealed using intumescent fillers and sealant.
29
Design and Specification - Hallgate How did you specify the fire doors?
I specified BM Trada Certified Fire Doors. The doors specified providing a the contractor with a list of items for the proposed fire doors. It was stipulated that the contractor refers to the Global Assessment to provide a compliant fire door for BM Trada Certification.
30
Design and Specification - Hallgate To sign-off completion of the fire doors is there anything in particular you'd be looking?
I received a certification for the fire doors The doors are also stamped to the head of the door.
31
Design and Specification - Hallgate Where are the fire doors stamped?
Top of the door.
32
Design and Specification - Hallgate What are the main components of a fire door?
- Door core - Glazing and beads - Hinges - Intumescent strips and smoke seals - Door Closer - Handles - Locks - Signage
33
Design and Specification - Hallgate Anything special about the ironmongery?
Hinges are to be grade 13 stainless steel All products to be kitemarked
34
Inspection You said you're used to using moisture meters. When might they give a false reading?
1. Ensuring the meter is calibrated before use. Refer to the manufacturer guidance on calibration. 2. Incorrect use of the equipment i.e. prongs to measure moisture in masonry 3. Presence of salts 4. Foil back plasterboard and services
35
Inspection What are hygroscopic salts?
They are salts which absorb water.
36
Inspection How are you going to separate out what is hygroscopic and what is moisture?
37
Inspection When you say profiling what instruments are using?
38
Inspection How would you prove if it was condensation?
39
Legal and Regulatory Compliance What are the duties of a Principal Designer?
- Compiling the pre-construction information - Preparing the health and safety file
40
Legal and Regulatory Compliance What is in the health and safety file?
Everything to do with the project. - Project Location and Description - Key Dates - As built drawings - O&M
41
Legal and Regulatory Compliance What is in a heritage statement?
- It describes the heritage asset, its significance and the proposed works that are being applied for. - A Heritage Statement would be required to justify the impact upon the value or ‘significance’ heritage asset and its setting.
42
Legal and Regulatory Compliance When is it necessary to submit a heritage statement?
- Development to a Listed building - Development in the setting/adjacent to a listed building - Development to properties (Inc. outline) in a conservation area - A development in the setting of, or adjacent to a conservation area
43
Legal and Regulatory Compliance What is a design and access statement? How does it differ from a heritage statement?
44
Works Progress and Quality Management You said you did some flooring replacement inspections; what was that involved in?
45
Works Progress and Quality Management What did you inspect; what were you looking for?
46
Measurement How do you calibrate a laser tape?
- Check against a known distance.
47
Measurement How would you measure the verticality of an external wall?
- Count bricks on an average - Theodolite
48
Measurement How would you check if the wall was plumb?
- Cross laser - Theodolite - Long straight edge
49
Health and Safety Job at Aldbrough Primary School, you said you prepared the PCI, can you give me some hazards you identified?
50
Health and Safety When you go to site to check the work, what sort of checks are you making?
- Segregation - Signage - Contractors site set up - F10 displayed - First Aid - Toilet facilities
51
Health and Safety What you check for if there was scaffolding on-site?
- Scaffold tag (Every 7 days for inspection: HSE)
52
Client Care Green Lane, what were your clients requirements?
The building to be demolished due to coastal erosion and prevent it from falling on to the beach
53
Client Care Green Lane, what was included in your letter of appointment?
- The scope of work - Agreed the timescales - Agreed the fee
54
Client Care Green Lane, in terms of the fee, how was it calculated for this particular job; what basis was the fee?
Percentage fee
55
Client Care What other types of fee have we got?
- Percentage - Fixed - Hourly
56
Client Care Can you give me an example of when you might use an hourly rate?
57
Data Management You said you are aware of BCIS, can you tell me how you use BCIS and what you do with the data you get from it to make it more accurate for the jobs you're doing?
- Time (Inflation) - Location - Quality
58
Data Management In terms of data that falls under GDPR, do you come into contact with that data?
59
Inclusive Environments Give me an example of some alterations that you can do to make them more accessible to everybody?
- Accessibility - Hearing loop - Contrasting colours - Wider opening - Ramps - Landing spaces
60
Inclusive Environments Where would you go for design guidance on these alterations?
Approved Document M Volume 2
61
Sustainable Technology Give me an example of a sustainable technology
- Photovoltaics - Air Source and Ground Source Heat Pumps
62
Rules and Ethics Give me an example of one of those rules?
Professional Competence & Expertise
63
Rules ands Ethics What do you mean by Professional Competence and Expertise
64
Rules ands Ethics What is the purpose of a responsible principal within a regulated firm?
A point of contact between the firm and the RICS
65
Rules ands Ethics What are the benefits of having a responsible principal?
Streamlined service Makes it easier in terms of communication with the RICS
66
Rules ands Ethics What is the responsible principals primary role within the firm?
- To provide information requested by the RICS - Ensuring that RICS' professional, technical and ethical standards are applied, upheld and supported by an appropriate assurance framework within a regulated firm.
67
Rules ands Ethics What is the purpose of the RICS Decision Tree?
When you come up with an ethical issue it is a flow chart which helps you.
68
Rules ands Ethics How many different types of conflict of interest are there?
3 types: 1. Own interest 2. A party conflict 3. Confidential Information
69
Rules ands Ethics Give me an example of a conflict of interest that a surveyor might come across?
70
Rules ands Ethics CPD requirements for full members, what are they?
20 hours minimum 10 formal (minimum) 10 informal (minimum)
71
Rules ands Ethics CPD, anything else we must do on a regular basis?
Yes, RICS members must complete CPD relating to ethics every 3 years.
72
Rules ands Ethics Professional Indemnity Insurance; who does it protect?
Firm Surveyor Client
73
Rules ands Ethics How does a firm workout how much Professional Indemnity Insurance it needs?
Based off the previous years turnover.
74
Rules ands Ethics (PII) Give me an example of one of the insurance bands?
£100,000 or less turnover is £250,000 minimum level of indemnity cover.
75
Rules ands Ethics Where would you find a list of firms who could provide a compliant PI policy.
RICS website has a list of approved insurers.
76
Rules ands Ethics In terms of run-off insurance; how long must a firm have run-off cover for?
minimum of 6 years.
77
Rules ands Ethics What is the purpose of run-off cover?
If a firm ceases to trade
78
Rules ands Ethics What value must a firm have for run-off cover?
£1,000,000
79
Rules ands Ethics If you were found guilty of a disciplinary offence by the RICS; give me some examples of the different penalties that could be applied?
Fixed penalty Regulatory Compliance Order Sanctioning
80
Rules ands Ethics (RICS Penalties) What if you have done something really bad; what is the ultimate sanction they can make against you?
Remove your membership.
81
Rules ands Ethics Why do the RICS feel it necessary to provide guidance on the use of social media?
What you as an individual as member of the RICS can reflect poorly on the profession
82
Rules ands Ethics Give me an example of something a member could publish that would be found to represent poorly on the RICS?
Some form of illegal activity which is published in the media which reflects poorly on the RICS.