Module 05 Flashcards

1
Q

Project Consists of Two Main Components. What components?

A

The project work that needs to be performed

The schedule to perform the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What makes up the the Project Work (Scope)

A

The Project Charter
The Scope Statement
Work Breakdown Structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What makes up the the Project Schedule

A

What activities need to be performed
Who will perform them
When will the activities be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Output of Activity Definition?

A

Activity List
Activity Attributes
Milestone List and Requested Changes to WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an Activity List

A

All activities necessary and sufficient to produce the product deliverables

Defined in sufficient detail to promote understanding by project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do we identify activities?

A

Select systems development life cycle model (SLCM)

Map life cycle process activities to SLCM using available standards and guidelines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Activity Sequencing

A

Identifies the dependencies among the schedule activities and orders the activities accordingly

Tasks may have dependencies because they require the same resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Precedence Relationships?

A

Finish to Start
-Initiation of the successor activity depends upon completion of the predecessor activity

Finish to Finish
-The completion of the successor activity depends upon the completion of the predecessor activity

Start to start
-The initiation of the successor activity depends upon the initiation of the predecessor activity

Start to finish
-The completion of the successor activity depends upon the initiation of the predecessor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Three Types of Dependencies, what are they?

A

Mandatory Dependencies

Discretionary Dependencies

External Dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Mandatory Dependencies

A

Inherent to the schedule activities (e.g. software must be developed before it can be tested)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Discretionary Dependencies

A

Dependencies at the discretion of the project team (e.g. acceptance test with marketing before accounting)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External Dependencies

A

Involves a relationship between a project activity and a non-project activity (e.g. Windows Vista Delivered)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path

A

The longest path (sequence of activities) in a project schedule network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Early Start

A

The earliest an activity can start. It is the largest early finish time of all its immediate predecessors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Early Finish

A

The earliest an activity can finish if all its preceding activities are finished by their early finish times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Late Start

A

The latest an activity can start and not delay a succeeding activity

17
Q

Late Finish

A

The latest an activity can finish and not delay a succeeding activity

18
Q

Float Time (Slack)

A

Time an activity can be delayed and not become critical

19
Q

Project Network Calculations

A
Early Start and Early Finish
-Forward Pass Through the Network
Late Start and Late Finish
-Backward Pass through the Network
Slack or Float
-Late Start – Early Start
20
Q

Critical Path Method? (Schedule Network Analysis)

A

Used to identify the schedule flexibility

The critical path is the longest path (sequence of activities) in a project schedule network diagram

Determines the length of the project

21
Q

Resource Leveling (Schedule Network Analysis)

A

Involves taking a part of the resources from one activity and assigning it to another

Change the durations and possible the critical path

22
Q

Crashing (Schedule Compression)

A

Used to decrease the project duration with minimal additional cost

A number of alternatives are considered, including adding additional resources

23
Q

Fast Tracking (Schedule Compression)

A

Decrease project duration by performing project phases or some schedule activities within a phase in parallel that would normally be performed in sequence

24
Q

Schedule Development Output

A

Project Schedule Network Diagram
Gantt Chart
Milestone Chart
Schedule Baseline

25
How are project schedule represented?
The Gantt chart
26
What is a Gantt chart
The Gantt chart shows tasks, dependencies and milestones using different shapes
27
Schedule Development Concerns
Actual start date Uncertainty on the availability of resources Identification and preparation for activities on the critical path Risks involved or “what if” scenarios The hard start/finish dates for activities or for the project that came down the pipeline from important stakeholders