MONITORING and CONTROL 25% slide 560 Flashcards
(102 cards)
Which of the following is not an objective of the
Monitoring and Controlling Process Group?
A) Track, review, and regulate project progress
and performance
B) Identify areas in which changes to the plans
are required and initiate change requests
where needed
C) Objectively evaluate and formally accept
project deliverables
D) Deliver project deliverables, once completed,
to the customer
M/C • Integration Management • General
D) Deliver project deliverables,
once completed, to the customer
While the project team does ensure that
all deliverables meet the quality standards
(Control Quality) and are approved by the
customer (Validate Scope), no deliverable
is officially transferred to the customer
until the end of the project in the Close
Project or Phase process.
Which of the following is not produced during the Monitoring and Controlling Process Group? A) Work performance data B) Work performance information C) Work performance reports D) Schedule and cost forecasts
M/C • Integration Management • General
A) Work performance
data
Work performance data are produced during the Executing Process Group by the Direct and Manage Project Work process. The data are a valuable input to the processes in the Monitoring and Controlling Process Group.
The Monitor and Control Project Work process provides insights into the health of a project by tracking, reviewing, and reporting on actual vs. expected progress. True or False:
M/C • Integration Management • Monitor & Control Project Work
True The focus of the Monitor and Control Project Work process is to maintain a clear understanding of how the project is progressing against the project baselines and project plans.
Which document, produced as a key
output of the Monitor and Control
Project Work process, summarizes
project performance and forecasts?
M/C • Integration Management • Monitor & Control Project Work
Work performance reports
Work performance reports summarize work performance information concisely and are critical to keep stakeholders aware of the project’s progress and to generate decisions or action.
_______are submitted to correct current and potential
project performance issues.
M/C • Integration Management • Monitor & Control Project Work
Change requests
How are work performance data translated into work performance information?
M/C • Integration Management • Monitor & Control Project Work
Data analysis It is through data analysis that the raw work performance data are translated directly into work performance information. This is one of the primary activities that occurs in the M/C Process Group.
What is the desired impact of the work performance reports generated as an output of the Monitor and
Control Project Work process?
M/C • Integration Management • Monitor & Control Project Work
To maintain stakeholder awareness
and generate decisions or action
Which of the following is not a type of action that would initiate a change request? A) Corrective actions B) Preventative actions C) Defect repairs D) Progress updates
M/C • Integration Management • Monitor & Control Project Work
D) Progress updates The three main drivers for change requests to improve performance are corrective actions, preventative actions, and defect repairs. Progress updates alone are not drivers for change requests, but they may convey information that drives the need for a change request.
Work performance information
provides insights into the
effectiveness in meeting project _______.
M/C • Integration Management • Monitor & Control Project Work
Objectives Work performance information indicates how the project is performing in scope, schedule, budget, quality, etc. These results are compared against the project plan to determine the degree of variance from the plan and if preventative/ corrective actions are required.
Which three types of documents
provide the baseline standards
and additional performance data
needed to assess project progress?
M/C • Integration Management • Monitor & Control Project Work
Project plans, project documents, and agreements
The project plans provide the expected plans and baselines by which progress is
evaluated.
The documents can provide progress reports, forecasts, logs, and
standards.
The agreements define what contractors must deliver.
Which type of analysis identifies the difference between planned performance and actual performance?
M/C • Integration Management • Monitor & Control Project Work
Variance analysis
Variance analysis is a key tool
and technique used during the Monitor and Control Project Work process to determine the condition of the project.
What is the difference between root cause analysis and alternatives analysis?
M/C • Integration Management • Monitor & Control Project Work
Root cause analysis identifies the main reasons
for an issue or variance between planned and actual performance.
Alternatives analysis is used to evaluate and select
the best corrective or preventative action
to improve project performance.
Any change request that potentially impacts a project baseline must be evaluated using the formal
process.
M/C • Integration Management • Perform Integrated Change Control
Perform Integrated Change Control
In which process are the approved change requests implemented?
M/C • Integration Management • Perform Integrated Change Control
Direct and Manage Project Work
All approved change requests
flow back to the Direct and
Manage Project Work process as
inputs to be implemented.
Describe the method by which change requests are recorded and submitted.
M/C • Integration Management • Perform Integrated Change Control
Change requests must be recorded in written form and entered into the change management system in order to be eligible for evaluation.
Data analysis is used by the ________ to evaluate the impact of each change request.
M/C • Integration Management • Perform Integrated Change Control
Change control board (CCB)
All change requests submitted must be evaluated by a CCB. This
board evaluates the total impact of the proposed change and renders a decision.
Name the three options that the change control board has when evaluating a change request.
M/C • Integration Management • Perform Integrated Change Control
Approve, defer, or reject
Every change request must be
approved, deferred, or rejected
by the change control board
(CCB).
What are the three most common
decision-making techniques used by a
change control board to render a final
decision on a change request?
M/C • Integration Management • Perform Integrated Change Control
- Voting,
- autocratic decision making, and
- multicriteria decision making
Change requests can only be implemented after they are transformed into _____.
M/C • Integration Management • Perform Integrated Change Control
Approved change requests Change requests can only be implemented after they are transformed into approved change requests
Which portion of the project management plan must be updated if a change request is submitted, approved, and results in additional costs? A) WBS dictionary B) Cost baseline C) Schedule baseline D) Communication plan
M/C • Integration Management • Perform Integrated Change Control
B) Cost baseline The approved change request authorizes the increase of additional costs for the project. The cost baseline must be adjusted to reflect the increase.
If a potential problem is identified in a project, but the team does not believe it justifies the creation of a change request at the present time, where should the information be recorded?
M/C • Integration Management • Perform Integrated Change Control
Issue log The issue log is used to record and track issues of all magnitudes in the project. While the issue identified may not currently require a change request, it is prudent to record it on the issue log so that it may be tracked going forward.
_______ is the process of obtaining the customer’s formal acceptance of completed project
deliverables.
M/C • Scope Management • Validate Scope
Validate Scope The purpose of the Validate Scope process is to obtain the customer’s formal acceptance of the completed project deliverables.
The verified deliverable that are produced as outputs by the _____________ process are the main inputs leveraged by the Validate Scope process.
M/C • Scope Management • Validate Scope
Control Quality The verified deliverables produced by the Control Quality process are what are evaluated for formal customer acceptance in the Validate Scope process.
What is the difference between the
Control Quality and Validate Scope
processes?
M/C • Scope Management • Validate Scope
Control Quality confirms that
quality standards are met.
Validate Scope confirms
the customer accepts the
deliverables.