MONITORING and CONTROL 25% slide 560 Flashcards

(102 cards)

1
Q

Which of the following is not an objective of the
Monitoring and Controlling Process Group?

A) Track, review, and regulate project progress
and performance
B) Identify areas in which changes to the plans
are required and initiate change requests
where needed
C) Objectively evaluate and formally accept
project deliverables
D) Deliver project deliverables, once completed,
to the customer

M/C • Integration Management • General

A

D) Deliver project deliverables,
once completed, to the customer
While the project team does ensure that
all deliverables meet the quality standards
(Control Quality) and are approved by the
customer (Validate Scope), no deliverable
is officially transferred to the customer
until the end of the project in the Close
Project or Phase process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Which of the following is not produced
during the Monitoring and Controlling
Process Group?
A) Work performance data
B) Work performance information
C) Work performance reports
D) Schedule and cost forecasts

M/C • Integration Management • General

A

A) Work performance
data

Work performance data are produced
during the Executing Process Group by
the Direct and Manage Project Work
process. The data are a valuable input
to the processes in the Monitoring and
Controlling Process Group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
The Monitor and Control Project
Work process provides insights into
the health of a project by tracking,
reviewing, and reporting on actual
vs. expected progress.
True or False:

M/C • Integration Management • Monitor & Control Project Work

A
True
The focus of the Monitor and
Control Project Work process is
to maintain a clear understanding
of how the project is progressing
against the project baselines and
project plans.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which document, produced as a key
output of the Monitor and Control
Project Work process, summarizes
project performance and forecasts?

M/C • Integration Management • Monitor & Control Project Work

A

Work performance reports

Work performance reports
summarize work performance
information concisely and are
critical to keep stakeholders aware
of the project’s progress and to
generate decisions or action.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

_______are submitted to correct current and potential
project performance issues.

M/C • Integration Management • Monitor & Control Project Work

A

Change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How are work performance data translated into work performance information?

M/C • Integration Management • Monitor & Control Project Work

A
Data analysis
It is through data analysis that
the raw work performance data
are translated directly into work
performance information. This is
one of the primary activities that
occurs in the M/C Process Group.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the desired impact of the work performance reports generated as an output of the Monitor and
Control Project Work process?

M/C • Integration Management • Monitor & Control Project Work

A

To maintain stakeholder awareness

and generate decisions or action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
Which of the following is not a type
of action that would initiate a change
request?
A) Corrective actions
B) Preventative actions
C) Defect repairs
D) Progress updates

M/C • Integration Management • Monitor & Control Project Work

A
D) Progress updates
The three main drivers for change
requests to improve performance are
corrective actions, preventative actions,
and defect repairs. Progress updates
alone are not drivers for change requests,
but they may convey information that
drives the need for a change request.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Work performance information
provides insights into the
effectiveness in meeting project _______.

M/C • Integration Management • Monitor & Control Project Work

A
Objectives
Work performance information
indicates how the project is
performing in scope, schedule,
budget, quality, etc. These results
are compared against the project plan
to determine the degree of variance
from the plan and if preventative/
corrective actions are required.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which three types of documents
provide the baseline standards
and additional performance data
needed to assess project progress?

M/C • Integration Management • Monitor & Control Project Work

A

Project plans, project documents, and agreements

The project plans provide the expected plans and baselines by which progress is
evaluated.

The documents can provide progress reports, forecasts, logs, and
standards.

The agreements define what contractors must deliver.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which type of analysis identifies the difference between planned performance and actual performance?

M/C • Integration Management • Monitor & Control Project Work

A

Variance analysis

Variance analysis is a key tool
and technique used during the Monitor and Control Project Work process to determine the condition of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between root cause analysis and alternatives analysis?

M/C • Integration Management • Monitor & Control Project Work

A

Root cause analysis identifies the main reasons
for an issue or variance between planned and actual performance.

Alternatives analysis is used to evaluate and select
the best corrective or preventative action
to improve project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Any change request that potentially impacts a project baseline must be evaluated using the formal
process.

M/C • Integration Management • Perform Integrated Change Control

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In which process are the approved change requests implemented?

M/C • Integration Management • Perform Integrated Change Control

A

Direct and Manage Project Work

All approved change requests
flow back to the Direct and
Manage Project Work process as
inputs to be implemented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe the method by which change requests are recorded and submitted.

M/C • Integration Management • Perform Integrated Change Control

A
Change requests must be
recorded in written form
and entered into the change
management system in order to
be eligible for evaluation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Data analysis is used by the ________ to evaluate the impact of each change request.

M/C • Integration Management • Perform Integrated Change Control

A

Change control board (CCB)

All change requests submitted must be evaluated by a CCB. This
board evaluates the total impact of the proposed change and renders a decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Name the three options that the change control board has when evaluating a change request.

M/C • Integration Management • Perform Integrated Change Control

A

Approve, defer, or reject

Every change request must be
approved, deferred, or rejected
by the change control board
(CCB).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the three most common
decision-making techniques used by a
change control board to render a final
decision on a change request?

M/C • Integration Management • Perform Integrated Change Control

A
  • Voting,
  • autocratic decision making, and
  • multicriteria decision making
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Change requests can only be implemented after they are transformed into _____.

M/C • Integration Management • Perform Integrated Change Control

A
Approved change
requests
Change requests can only be
implemented after they are
transformed into approved
change requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
Which portion of the project
management plan must be updated if a
change request is submitted, approved,
and results in additional costs?
A) WBS dictionary
B) Cost baseline
C) Schedule baseline
D) Communication plan

M/C • Integration Management • Perform Integrated Change Control

A
B) Cost baseline
The approved change request
authorizes the increase of
additional costs for the project.
The cost baseline must be
adjusted to reflect the increase.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
If a potential problem is identified
in a project, but the team does not
believe it justifies the creation of
a change request at the present
time, where should the information
be recorded?

M/C • Integration Management • Perform Integrated Change Control

A
Issue log
The issue log is used to record and
track issues of all magnitudes in the
project. While the issue identified
may not currently require a change
request, it is prudent to record it
on the issue log so that it may be
tracked going forward.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

_______ is the process of obtaining the customer’s formal acceptance of completed project
deliverables.

M/C • Scope Management • Validate Scope

A
Validate Scope
The purpose of the Validate
Scope process is to obtain the
customer’s formal acceptance
of the completed project
deliverables.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The verified deliverable that are produced as outputs by the _____________ process are the main inputs leveraged by the Validate Scope process.

M/C • Scope Management • Validate Scope

A
Control Quality
The verified deliverables
produced by the Control Quality
process are what are evaluated
for formal customer acceptance
in the Validate Scope process.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the difference between the
Control Quality and Validate Scope
processes?

M/C • Scope Management • Validate Scope

A

Control Quality confirms that
quality standards are met.

Validate Scope confirms
the customer accepts the
deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
______________ is the formal document signifying that the customer has accepted a deliverable as complete and satisfactory. M/C • Scope Management • Validate Scope
Accepted deliverable
26
What must occur for a verified deliverable to become an accepted deliverable? M/C • Scope Management • Validate Scope
the customer must confirm that the acceptance criteria have been met. A formal signature confirming acceptance must be obtained from the customer.
27
``` Which document produced in the Planning Process Group links the project requirements to the deliverables that satisfy them? M/C • Scope Management • Validate Scope ```
``` Requirements traceability matrix The requirements traceability matrix produced in the Collect Requirements process visually displays the deliverables that must be satisfied. ```
28
Which two techniques are used to evaluate that verified deliverables meet acceptance criteria? M/C • Scope Management • Validate Scope
Inspection and decision making Inspection includes measuring, examining, and validating each deliverable. Decision making, often including voting, is the method by which a conclusion is reached.
29
``` The accepted deliverables produced by the Validate Scope process are forwarded to which process as an input? M/C • Scope Management • Validate Scope ```
Close Project or Phase
30
Define the primary purpose of the Control Scope process. M/C • Scope Management • Control Scope
``` The Control Scope process is focused on monitoring the status and managing changes to the scope baseline to prevent scope creep. ```
31
``` Which key output of the Control Scope process summarizes the actual scope performance against the scope baseline? M/C • Scope Management • Control Scope ```
Work performance information
32
__________ and project documents provide the facts required to identify significant variances between the scope performance and the performance baseline. M/C • Scope Management • Control Scope
Work performance data ``` Work performance data provide the raw materials that are analyzed within the Control Scope process to produce the work performance information. ```
33
``` Which analysis technique used during the Control Scope process determines if project performance is improving or deteriorating by examining historical results? M/C • Scope Management • Control Scope ```
Trend analysis
34
How does variance analysis work and what type of actions could it facilitate? M/C • Scope Management • Control Scope
Variance analysis compares the baseline to the actual results. If the variance exceeds a threshold, then corrective or preventative action may be developed. If the actions impact the baseline, then a change request will be generated.
35
The Control Scope process is conducted throughout the life of the project. True or False: M/C • Scope Management • Control Scope
``` True After the scope baseline is defined, the Control Scope process must be conducted throughout the entire project. This process is essential as it helps to monitor the success of the project and the prevention of scope creep. ```
36
``` Schedule-related work performance information, such as SV and SPI, are fed back (as inputs) into which process? M/C • Schedule Management • Control Schedule ```
Monitor and Control Project Work The Monitor and Control Project Work process tracks, summarizes, and reports on the overall project performance.
37
The ________ visually displays the amount of work completed and uncompleted over time. M/C • Schedule Management • Control Schedule
Iteration burndown chart
38
Define the primary purpose of the Control Schedule process. M/C • Schedule Management • Control Schedule
``` The Control Schedule process involves monitoring and maintaining an accurate schedule baseline throughout the completion of the project. ```
39
``` Which of the following is not a method to bring a project schedule back into alignment with the plan? A) Resource compression B) Resource optimization C) Leads and lags D) Schedule compression ``` M/C • Schedule Management • Control Schedule
A) Resource compression ``` Resource compression is not an actual technique. The three common methods are resource optimization, lead and lag analysis, and schedule compression. ```
40
How do schedule variance (SV) and schedule performance (SPI) differ when analyzing a project’s schedule performance? M/C • Schedule Management • Control Schedule
Schedule variance defines the amount a project is ahead/behind the schedule baseline. Schedule performance defines how efficiently the team is completing the work.
41
By which standard is the actual schedule performance evaluated during the Control Schedule process? M/C • Schedule Management • Control Schedule
``` Schedule baseline The schedule baseline is the standard by which schedule progress is evaluated during the Control Schedule process. ```
42
``` The Control Costs process centers on understanding both the total amount spent and the of the money spent to complete project activities. M/C • Cost Management • Control Costs ```
``` Effectiveness Analysis conducted during the Control Cost process determines the effectiveness of the money spent on a project by analyzing the total amount spent and the value generated from the spend. ```
43
``` ________ integrates scope, schedule, and cost to answer the question, “Has the plan been effective in delivering the desired results?” M/C • Cost Management • Control Costs ```
``` Earned value management (EVM) EVM integrates the cost, schedule, and scope performance and evaluates it against the baseline. ```
44
Which variable defines the total budget amount allocated for the project? M/C • Cost Management • Control Costs
Budget at completion (BAC)
45
``` Planned value (PV) defines the value of work that _______ done. ``` M/C • Cost Management • Control Costs
``` Should be Planned value (PV) defines the value of the work that should be done. This creates the standard by which progress will be measured. ```
46
``` Earned value (EV) defines the value of work that _____ done. M/C • Cost Management • Control Costs ```
``` Is Earned value (EV) defines the value of the work that is done. This is often used to calculate the project’s completion percentage. ```
47
``` Schedule variance (SV) determines the amount a project is ahead/behind the schedule baseline. What does a negative schedule baseline indicate? M/C • Cost Management • Control Costs ```
``` Project is behind schedule A negative SV indicates that a project is behind schedule, while projects with positive SVs are ahead of schedule. ```
48
At the completion of a project, what will the SV value be? M/C • Cost Management • Control Costs
``` Zero The schedule variance will always be zero at the end of the project because all of the work planned is completed. ```
49
``` Your project team has been more efficient than originally projected in completing the project work. What would you expect the SPI value to be? M/C • Cost Management • Control Costs ```
``` Above 1 SPI values above 1 indicate that more work has been completed than planned at the period of time (indicating that the team has been more efficient than expected). ```
50
``` The _________ variable determines if the project is ahead or behind the budget defined in the cost baseline. M/C • Cost Management • Control Costs ```
``` Cost variance (CV) The cost variance (CV) determines the amount of budget deficit or surplus at a given time. ```
51
State the only difference between the CV and CPI equations. M/C • Cost Management • Control Costs
``` A division symbol The equations for CV and CPI are nearly identical in structure. The only difference is that there is a division symbol in the CPI equation: CV = EV - AC CPI = EV / AC ```
52
``` Which EVM variable calculates the expected total cost of the project at the completion of all project work? M/C • Cost Management • Control Costs ```
``` Estimate at completion (EAC) EAC determines the expected total cost at the completion of all project work. ```
53
``` The estimate to complete (ETC) calculates the expected cost to finish all the remaining project work. True or False: M/C • Cost Management • Control Costs ```
``` True Estimate at complete (ETC) calculates the expected cost to finish all the remaining project work. ETC = EAC - AC ```
54
``` The _________ variable determines the CPI that must be achieved with the remaining resources to meet a specific management goal. M/C • Cost Management • Control Costs ```
``` To-complete performance index (TCPI) TCPI evaluates the current performance and determines the CPI rate that must be maintained to hit a defined management goal. Two equations exist to calculate the TCPI to meet the management goals of BAC or EAC. ```
55
Is a TCPI above or below 1 more difficult to meet? M/C • Cost Management • Control Costs
``` Above 1 TCPI values above 1 are more difficult to meet because the team must perform at a level more efficient than originally planed in the project cost baseline. ```
56
Which type of analysis evaluates the amount of management and contingency reserves still remaining? M/C • Cost Management • Control Costs
``` Reserve analysis Reserve analysis is used during the Control Costs process to track the amount of reserves remaining. ```
57
What is the purpose of the Control Quality process? M/C • Quality Management • Control Quality
ensure project outputs are complete, correct, and satisfactory to customers by monitoring and recording quality results.
58
``` Control quality determines if the project outputs do what they were intended to do. True or False: M/C • Quality Management • Control Quality ```
``` True The Control Quality process determines if the project outputs (deliverables) do what they were intended to do. ```
59
``` The Control Quality process is generally performed before the Validate Scope process, although the two processes could be performed in _____ . M/C • Quality Management • Control Quality ```
Parallel
60
What is the primary output of the Control Quality process? M/C • Quality Management • Control Quality
Verified deliverable Verified deliverables confirm that the project deliverables do what they were intended to do.
61
``` Which data gathering technique uses a smaller sample to measure quality and infer the total quality of a larger population? M/C • Quality Management • Control Quality ```
Statistical | sampling
62
``` Name the simple, yet powerful, data gathering technique used to gather attribute data while performing inspections (ie: defects). M/C • Quality Management • Control Quality ```
Check sheets
63
When a quality issue is identified, which type of data analysis technique is often leveraged to investigate the cause? M/C • Quality Management • Control Quality
``` Root cause analysis Root cause analysis aims to identify the core problem driving an issue so that it can be eliminated ```
64
``` The team has used a chart to determine whether or not a process is stable. Which chart have they leveraged? M/C • Quality Management • Control Quality ```
Control chart
65
Which quality tool is used to help identify the possible root cause driving a defect? M/C • Quality Management • Control Quality
``` Cause-and-effect diagram Also known as a fishbone or Ishikawa diagram, the cause-andeffect diagram helps to identify the root cause of a defect. ```
66
What is the goal of the Control Resources process? M/C • Resource Management • Control Resources
``` Right resources, right place, right time The goal of the Control Resources process is to ensure that the right resources are available at the right place and time and in the right quantity. ```
67
The Control Resources process is focused on coordinating both physical and team resources. True or False: M/C • Resource Management • Control Resources
``` False The Control Resources process is focused only on the coordination of physical resources, not team resources. ```
68
The act of monitoring and analyzing the actual vs. planned resource allocation, during the Control Resources process, produces __________ that can highlight gaps in resources availability. M/C • Resource Management • Control Resources
Work performance | information
69
``` Throughout a project, the team recognizes two examples of extremely effective resource utilization. Where should this information be recorded? M/C • Resource Management • Control Resources ```
Lesson learned | register
70
``` Name two critical “soft skills” that are often used to obtain additional resources and solve problems during the Control Resources process. M/C • Resource Management • Control Resources ```
Negotiation and influence
71
Which project document shows when resources are available to the project? M/C • Resource Management • Control Resources
Resources | calendar
72
``` What type of data analysis is used during the Control Resources process to better understand the economic impacts of a decision? M/C • Resource Management • Control Resources ```
Cost-benefit | analysis
73
Define the purpose of the Monitor Communications process. M/C • Comm. Management • Monitor Communications
evaluation of actual communications and initiates changes to improve results when needed.
74
``` What are four ways in which the team achieves the goal of ensuring each stakeholder’s communication needs are met? M/C • Comm. Management • Monitor Communications ```
1) Monitoring the actual communications delivered by the Manage Communications process 2) Evaluating the effectiveness of communications 3) Understanding changes in stakeholder needs 4) Triggering changes to the communications plan
75
``` The ___________ matrix provides the desired stakeholder engagement level that the communications management plan was designed to achieve. M/C • Comm. Management • Monitor Communications ```
Stakeholder | engagement matrix
76
``` During which process was the stakeholder engagement matrix, which defines the current vs. desired engagement levels, created? M/C • Comm. Management • Monitor Communications ```
Plan Stakeholder Engagement (13.2) process
77
``` Which project document should be updated to record engagement and communications issues uncovered during the Monitor Communications process? M/C • Comm. Management • Monitor Communications ```
Issue log
78
If a change request was submitted and approved to modify the approach, frequency, or method of communicating information, which document or plan would be least likely to be updated? A) Communications management plan B) Stakeholder engagement plan C) Requirements traceability matrix D) Lessons learned register M/C • Comm. Management • Monitor Communications
C) Requirements traceability matrix ``` Updates to the methods of communication would most likely be recorded in the communications management plan, stakeholder engagement plan, and lessons learned register. ```
79
How does the Monitor Risk process differ from the Implement Risk Responses process? M/C • Risk Management • Monitor Risk
The Monitor Risks process evaluates the effectiveness of risk responses initiated during the Implement Risk Responses process.
80
``` The __________ communicates whether or not the contingency reserve remaining is sufficient to meet the risk remaining. M/C • Risk Management • Monitor Risk ```
Burndown chart
81
``` The risk-related _________ generated as the key output of the Monitor Risks process is fed back (as an input) into the Monitor and Control Project Work process. This process tracks, summarizes, and reports on overall project performance. M/C • Risk Management • Monitor Risk ```
Work performance | information
82
``` Which of the following is not one of the key objectives of the Monitor Risk process? A) Monitor the implementation of risk response plans B) Track identified risks C) Identify and analyze new risks D) Assign individuals to implement new corrective actions to eliminate new risks identified M/C • Risk Management • Monitor Risk ```
``` D) Assign individuals to implement new corrective actions to eliminate new risks identified ```
83
``` Name the technique commonly used to determine if the risk management processes are followed and effective. M/C • Risk Management • Monitor Risk ```
Audits
84
Which two types of data analysis are used during the Monitor Risk process to compare the scheduled vs. actual technical accomplishments and to evaluate the impact of risk on contingency reserves? A) Qualitative risk analysis and quantitative risk analysis B) Technical performance analysis and contingency analysis C) Technical performance analysis and reserve analysis D) Risk categorization and quantitative risk analysis M/C • Risk Management • Monitor Risk
C) Technical performance analysis and reserve analysis Technical performance analysis compares technical accomplishments during project execution with what was scheduled. Reserve analysis is used to determine if the remaining reserve is adequate.
85
``` _______ is the term that describes the approaches and contingencies that project managers build into their project’s risk processes. M/C • Risk Management • Monitor Risk ```
Project resilience
86
What type of reserve has been established to account for knowable-unknowns? M/C • Risk Management • Monitor Risk
Contingency | reserves
87
``` The Control Procurements process focuses on all of the following, except: A) Establishing contracts with buyers B) Ensuring that both parties meet contractual obligations C) Confirming that the appropriate buyer parties approve deliverables D) Resolving all conflicts in a positive manner M/C • Procurement Management • Control Procurements ```
``` A) Establishing contracts with buyers The Control Procurements process evaluates contract progress and results and manages the procurement relationship to improve the likelihood of project success. The establishment of contracts is accomplished in the Conduct Procurements process. ```
88
``` Changes to procurements require adherence to the company’s internal change request process. True or False: M/C • Procurement Management • Control Procurements ```
False Changes to procurements must adhere to the change control terms defined in the contract
89
``` The Controlling Procurements process generates _____________ and __________ that must be documented in project documents/plans. M/C • Procurement Management • Control Procurements ```
Work performance information and change requests
90
Describe the process required to close a procurement. M/C • Procurement Management • Control Procurements
To close the procurement, formal written notice that the contract has been completed must be obtained. The process is formally defined in the contract terms and is usually completed by the authorized procurement administrator.
91
When conflicts/issues occur in the fulfillment of a contract, what is the most optimal method of action? M/C • Procurement Management • Control Procurements
Negotiations Negotiations are the optimal method of resolving contractual issues.
92
If negotiations are unable to rectify contractual issues, what method should be leveraged? M/C • Procurement Management • Control Procurements
``` Alternative dispute resolution (ADR) Negotiations are the optimal method to handle conflict. If issues cannot be resolved, the project manager must follow the ADR defined in the contract. ```
93
What are the key outputs of the Control Procurement process? M/C • Procurement Management • Control Procurements
``` Closed procurements, work performance information, change requests, document updates The goal of the Control Procurements process is to continually evaluate the progress of the procurements and make proper adjustments so that the contract can be completed on time and budget. The closed procurements signify the successful completion of the contract. ```
94
``` What two methods are used to monitor that the deliverables produced meet the requirements defined in the contract? M/C • Procurement Management • Control Procurements ```
Inspections and audits In the most simple terms, you inspect things and you audit processes.
95
``` As a project evolves, it is often necessary to modify the methods used to engage stakeholders. True or False: M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement ```
``` True The primary goal of the Monitor Stakeholder Engagement process is to maintain or increase the efficiency and effectiveness of stakeholder engagement activities. To accomplish this, it is often necessary to adjust the strategies by which each stakeholder is engaged. ```
96
``` The Monitor Stakeholder Engagement process aims to _______ and _______ engagement activities as the project evolves. M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement ```
``` Adapt; improve As with the Monitor Communications process, the Monitor Stakeholder Engagement process constantly gauges results and quickly initiates changes to improve the effectiveness of stakeholder engagement. ```
97
The team can improve the effectiveness of stakeholder engagement activities by completing all of the following, except: A) Collecting work performance data generated by the Direct and Manage Project Work process B) Evaluating if the desired engagement levels are obtained (actual vs. desired) C) Removing stakeholders who resist project progress D) Generating changes to improve the effectiveness of engagement activities M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement
C) Removing stakeholders who resist project progress Stakeholders are only removed from the stakeholder register if they are no longer impacted by the project. It is not acceptable to remove stakeholders who resist the project. The primary goal of the Monitor Stakeholder Engagement process is to adjust the strategies used in order to improve the engagement of stakeholders, especially those resistant
98
``` On which data representation document would it be easy to see which stakeholder currently has a gap between the actual and desired engagement level? M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement ```
Stakeholder engagement matrix ``` The stakeholder engagement matrix, created in the Manage Stakeholder Engagement process, maps the actual vs. desired engagement level for each stakeholder. This document must be updated throughout the project to reflect changes. ```
99
_______ involves listening and then using your words to clarify and confirm the message that was heard. M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement
Active listening
100
``` Which two interpersonal and team skills must be leveraged when cultivating strong stakeholder engagement on international projects? M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement ```
``` Cultural awareness and political awareness When developing strong stakeholder engagement it is extremely important to be aware of the cultural and political environments of the different stakeholders on your project. ```
101
``` The completion of stakeholder analysis has determined that the planned engagement activities have failed to deliver the desired level of engagement for a key stakeholder. What should the team do next? M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement ```
Complete root cause and then alternatives analysis Root cause analysis helps define the reasons for a lack of engagement and alternatives analysis develops options to eliminate the variances.
102
__________ provide insights necessary to understand each stakeholder’s level of engagement. M/C • Stakeholder Mgmt. • Monitor Stakeholder Engagement
``` Work performance data Work performance data define the project status of the type of engagement delivered, which stakeholders are supportive, and the levels of support. Work performance data and project documents are key inputs to the Monitor Stakeholder Engagement process. ```