MRP2 Framework Flashcards
The four main functions in MRP2
Sales and Operations Planning [S&OP]
Master Production Planning/Schedule [MPS]
Material Requirements Planning [MRP]
Production Activity Control [PAC]
What is MRP2?
Hierarchical planning structure
Input for S&OP
Sales forecast
Output for S&OP
Production plan
Input for MPS
Production plan
Output for MPS
Mater plan
Input for MRP
Master plan
Output for MRP
Production and puschase order
Input for PAC
Production order
Output for PAC
Sequencing
Horizon for S&OP
1-5 years
Horizon for MPS
1/4 - 1 year
Horizon for MRP
1-6 months
Horizon for PAC
1-4 weeks
Period and re-scheduleing for S&OP
Quarter/Month
Period and re-scheduleing for MPS
Month/Week
Period and re-scheduleing for MRP
Week/Day
Period and re-scheduleing for PAC
Day/Hour
Level of function: S&OP
Strategical
Level of function: MPS
Tactical
Level of function: MRP
Operational
Level of function: PAC
Executional
Planning object for S&OP
Product groups and final products
Planning object for MPS
Final product