MRP2 Framework Flashcards

1
Q

The four main functions in MRP2

A

Sales and Operations Planning [S&OP]
Master Production Planning/Schedule [MPS]
Material Requirements Planning [MRP]
Production Activity Control [PAC]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is MRP2?

A

Hierarchical planning structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Input for S&OP

A

Sales forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Output for S&OP

A

Production plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Input for MPS

A

Production plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Output for MPS

A

Mater plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Input for MRP

A

Master plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Output for MRP

A

Production and puschase order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Input for PAC

A

Production order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Output for PAC

A

Sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Horizon for S&OP

A

1-5 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Horizon for MPS

A

1/4 - 1 year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Horizon for MRP

A

1-6 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Horizon for PAC

A

1-4 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Period and re-scheduleing for S&OP

A

Quarter/Month

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Period and re-scheduleing for MPS

A

Month/Week

11
Q

Period and re-scheduleing for MRP

12
Q

Period and re-scheduleing for PAC

13
Q

Level of function: S&OP

A

Strategical

14
Q

Level of function: MPS

15
Q

Level of function: MRP

A

Operational

16
Q

Level of function: PAC

A

Executional

17
Q

Planning object for S&OP

A

Product groups and final products

18
Q

Planning object for MPS

A

Final product

19
Planning object for MRP
Article component
20
Planning object for PAC
Operation
21
Decision aspects for S&OP
Planning strategy
22
Decision aspects for MPS
CODP, delivery LT, products
23
Decision aspects for MRP
Specific units, specific resources, produc structure
24
Decision aspects for PAC
Decentralised control, feedback, evaluation, specific units and resources
25
Upper left corner in MRP2 image
Demand Administration Forecast Customer order
26
Bottom left corner going from MRP in the MRP2 image
Material source
27
Bottom line in the MRP2 image
Raw materials - Work in process - Finished goods inventory
28
Parts going out of S&OP in the MRP2 image
Resource planning (right) Master Planning Schedule (down)
29
Parts going out of MPS in the MRP2 image
Rough Cut Capacity Planning (right) Material Requirements Planning (down)
30
Parts going out of MRP in the MRP2 image
Capacity Requirements planning (right) Product activity control (down)
31
Parts going out of PAC in the MRP2 image
Order release control (right) Work in process (down)
32