What is Jet 2’s engine failure procedure following a missed approach for rwy 26?
At 1600ft turn left to BIA and hold on track 255 degrees (left hand hold)
What is Jet 2’s engine failure procedure following a missed approach for rwy 08?
At 1600ft turn right to BIA and hold on track 255 degrees (left hand hold)
How has booking of IFR training changed?
Scheduled traffic and A340 movements have been collated and the training sheets are now greyed out for periods where IFR training is not permitted.
What has changed with regards to Helicopter training at EGHH?
There is no longer any HTA or space on the airfield for hover training and this will remain the case once the northside works have been completed.
Helicopters must use the runway for all arrivals/departures and hover training
Why are we giving extra traffic information to vehicles and a/c on the runways?
Because of a fuel vehicle having a panic when cleared to cross 08 when a helicopter was given take-off rwy 08 from the 26 thres so was fine but vehicle driver didn’t get what was happening
What extra job do we need to do for runway crossings?
We are keeping a tally owing to the extreme number of crossings by European vehicles/bowsers
What has changed in regards to laser strikes?
A quick use guide has been procured kept on the GMC desk next to the FR24 computer
In what circumstances do we call the ADM?
A/c emergencies
Wx related issues
Diversions
Runway obstructions with the potential to cause delay
Security incidents
Sensitive flights
A/c returning to stand
Significantly delayed a/c
What extra job is there regarding a/c arriving with a missing estimate?
Irrespective of the reason for the missing estimate complete the ‘Missing Inbound Estimates’ log sheet
What are Jet 2’s procedures arriving to the airport?
Solent open- expect RV from the STARs from Solent and then Bournemouth
Solent closed- Expect RV from Bournemouth Radar, direct routing may be accepted under a TS or DS. Crews also ask for expected routings to be given when clearance requested (for deps).
Procedural Service- A/c to fly a procedural approach, no direct routings to be accepted
What is the contingency procedure for the failure of the VCCS in Rdr?
A BT line and Solent direct line are wired in white contingency phones above the RAD 2 position. A silence switch will require activating in the event of VCCS total failure.
What is the contingency procedure should the main and standby radios fail on the VCCS?
Use the ICOM standby radios and inform duty ATE, use this radio is to be used to make the situation safe as these radios only have a battery life of 1 hour. The ringer silence switch will need to be deselected in the event of total VCCS failure.W
Where is the alarm for the VCCS panel shown?
In the ILS monitor panel labelled VCS, a visual and audible alarm will trigger
What is the new TORA for 26X for an a/c departing from E?
1963m
What is the new TODA for 26X for an a/c departing from E?
2023m
What is the new ASDA for 26X for an a/c departing from E?
1963m
What is the new TORA for 26?
2026m
What is the new TODA for 26?
2086m
What is the new TODA for 08?
2576m
What is the new LDA for 26x?
1970m
What is the new TODA for 26x?
2271m
What is the new TORA for 26x?
2211m
What is the new ASDA for 26x?
2211m
What is the new ASDA for 26?
2086m