Organising Flashcards

(10 cards)

1
Q

Purpose of the organizing practice

A

The purpose of the organizing practice is to
define and establish the project’s structure of
accountability and responsibilities (the

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The three principal project
interests

A

Business
User
Supplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The business
The
executive represents the business
interests on the project.

A

Meet a business need
Ensure value for money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The user
Senior user(s)
is needed to represent user
interests on the project.

A
  • will use the
    outputs of the
    project to realize
    the benefits
  • will operate,
    maintain, or
    support the
    project’s
    outputs
  • the
    outputs of
    the project will
    impact them.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The supplier
Senior supplier(s)
is needed to represent
supplier interest on the project.

A
  • The creation of the project’s outputs will need resources with
    certain skills.
  • The supplier viewpoint should represent those who will
    provide the necessary skills and produce the project product.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project manager

A

The project manager is
responsible for day-to-day
management of a project.
Has authority to run the project
on behalf of the project board
within agreed project
tolerances and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Team manager

A
  • Responsible for delivering the work to agreed
    specifications and within the tolerances and
    constraints agreed with the project manager.
  • The project manager allocates work to a team
    manager through work package descriptions, in
    line with the commercial management approach.
  • Manages relationships in their teams and
    interfaces with other teams.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project assurance

A
  • Project board members
    accountable for assurance
    of respective areas
  • May appoint separate
    individuals, but not project
    manager, team members
    or project support
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project support

A
  • Includes services such as
    administrative support,
    guidance on project tools,
    planning etc
  • Responsibility of project
    manager but may be
    delegated
  • A project office may be
    established
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Management products

A

1> Commercial
management approach
Describes the
procedures,
techniques, and
standards and the
responsibilities for
effective commercial
management.
Covers the approach to
secure, service, and
maintain all commercial
agreements required for
the project to be a success.

2> Project management
team structure
Defines
who is involved in
the project, their
relationships , and how
they will work together.

3> Role descriptions
Describes the
roles of
those in the project
management team
and their specific
responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly