Permits Flashcards
permit for extraction, removal, and disposition of quarry resources
Quarry Permit
give at least 5 quarry resources
any of these:
basalt, rhyolite, andesite, gabbro, diorite, granite, conglomerate, limestone, coral sand, marble, marl, rock phosphate, sandstone, shale, tuff, volcanic cinders, volcanic glass, red burning clays for potteries and bricks, serpentine
t or f: quarry permits are limited to Filipinos or Filipino-owned corporations
T
how many hectares does quarry permit cover
5 ha or less
term for quarry permit
5 year term ; renewable for like terms but not to exceed a total term of 25 years
large scale quarrying requires a _____
mineral agreement
permit for extraction, removal, and disposition of sand and gravel and other loose or unconsolidated materials
sand and gravel permits
t or f: sand and gravel permits are limited to Filipino or filipino-owned corporations
T
term for sand and gravel permits
1 to 5 year term ; renewable for like terms
only ___ permit for sand and gravel shall be granted to a qualified person in a municipality
1
permit for extraction, removal, and disposition of sand and gravel and other loose and unconsolidated materials necessitating the use of mechanical processing
Industrial Sand and Gravel Permit
term for industrial sand and gravel
5 year term ; renewable for like terms but not to exceed a total of 25 years
permit for extraction, removal, and disposition of sand and gravel and other loose or unconsolidated materials used in their natural state
commercial sand and gravel permit
areas covered by commercial sand and gravel
1 ha or less
areas covered by industrial sand and gravel
5 to 20 hectares
term for commercial SAG
1 year term renewable for like period
permit for the extraction and utilization of sand and gravel or loose/unconsolidated materials for construction of buildings and/or infrastructure for public use
Government Gratuitous Permit
to whom are Government Gratuitous Permit issued to?
any government entity / instrumentality
term for government gratuitous permit
co-terminus with the project but not to exceed 1 year
area covered by government gratuitous permit
2 ha or less in public/private land
government gratuitous permit requires submission of ____
project proposal
extraction and utilization of quarry, sand and gravel or loose/unconsolidated materials
Private Gratuitous Permit
to whom are Private Gratuitous Permit issued to?
any landowner in his/her private land
term for Private Gratuitous Permit
60 calendar days ; non-renewable