Planning & Managing Deployment 2/2 Flashcards
(53 cards)
What is an OBS
An organisational breakdown structure (OBS) details the organisation and resources available for a project. The OBS outlines tasks that can be allocated to the resources defined, helping to clarify roles for people. An OBS also makes escalation of issues clear, which helps with any resource problems that may need escalating.
What is a RAM
(responsibility assignment matrix)
The RAM is a communication device to guarantee that the people involved in doing the work are informed of the work they have to do and their position in the project organisation. Resource or BAU managers (these may be line managers) also consult the RAM. They use the RAM to understand and agree the work that has been distributed to their people.
What does RACI stand for
Responsible, accountable, consulted, or informed (RACI)
Describe a RACI
Responsible, accountable, consulted, or informed (RACI)
It is best practice for one person to be responsible and one person to be accountable. The project manager is accountable for the work packages/deliverables as they are responsible for the delivery of the project up to transition.
To deliver the project objectives successfully to the agreed acceptance criteria, labour and non-labour items are needed. resources are categorised into what four types:
Human
Materials
Plant or equipment
Facilities
what is the difference between resource levelling and resource smoothing
Resource levelling: is used where a fixed amount of resources are available, and the end date of the project can be delayed.
- It answers the question: with the resources available, when will the work be finished.
- Can be achieved through redefining scope and/or specifications, increasing task durations, increasing resources earlier on to bring activities forward, or moving non-critical activities to a different time.
Resource smoothing: is used when time is more important than cost, answering the question: what resources do I need to deliver the work within the fixed timescale?
- It looks to protect the end date of the project.
- Smoothing can be achieved through reducing task durations, by adding more resources, avoiding peaks and troughs of resource demand, or changing the order of activities where the logic used originally was optional to run activities in parallel rather than in sequence.
How are resources categorised and allocated to linear life cycle schedules?
- Resources are categorised according to their type (human resources, materials, equipment, financial resources).
- Resources are allocated to specific project tasks or work packages. A work breakdown structure can be used to identify work needed and then the resources can be allocated.
- It involves upfront planning and estimation to determine resources needed.
Resources categorised and allocated to linear life cycle schedules; Why would this approach to resource allocation be challenging for iterative life cycle schedules?
- As iterative life cycles have more flexibility/less structured, resource requirements can be more uncertain/fluctuating/changing.
- As iterative life cycles have fixed/pre-allocated resources, it can be difficult to adapt to the project requirements/needs.
- As iterative life cycles have fixed/pre-allocated resources, it could lead to under/over-utilisation of resources depending upon the project requirements/needs.
How is the end date of a project impacted by:
resource smoothing?
resource levelling?
resource smoothing impacts the end date of a project:
The end date stays the same/is maintained/is not impacted.
The end date is prioritised.
The time of the project is not impacted.
resource levelling impacts the end date of a project:
The end date may change/is impacted/is not maintained.
The end date is not prioritised.
The time of the project is impacted
When are estimates used?
- enable budget setting and considerations of affordability.
- assist judgements on value for money for the solution chosen.
- provide an essential input into creating a resource schedule, which then, in turn, provides the cost view of the project.
What factors should you consider when budgeting?
- The different types of costs involved and when they will hit the project to know when money will be needed to budget accordingly i.e., funding drawdowns at the right time to cover payment milestones.
- Information required from external sources, such as supplier costs, and how these align with the plan to enable budgeting.
- The assumptions being made on the project and how they are underpinning the cost estimates so they can be understood, validated, and budgeted for.
What is used to create the CBS
The work breakdown structure (WBS) is used to create the cost breakdown structure (CBS)
What does the CBS identify
The CBS identifies all activity that has a cost associated with it, both labour and non-labour, in each work package. These costs can then be collected, recorded, monitored, and controlled as part of the financial reporting system. Costs can be attributed to:
people.
equipment.
materials.
other resources required.
Describe the four different types of cost planning.
- Fixed: A set monthly cost is agreed for the resources with the supplier regardless of the actual requirement of the supplier in that month, which is likely to fluctuate over the course of the project life cycle.
- Variable: Resources or materials are paid for as and when they are required or delivered meaning the cost could fluctuate from month to month.
- Recurring: Some costs are frequent enough that they reoccur at set periods and require regular payments, for example, software licenses.
- Non-recurring: Often one-off requirements like equipment set-up costs. Non-recurring won’t always be at the start of the project but will be for resources or materials that incur a single charge.
Project managers use cost control techniques to achieve what?
- minimise costs where possible.
- identify areas of overspend.
- correct unacceptable levels of overspend.
- inform future projects by providing insight into lessons learnt.
Describe Cost and schedule performance indicators
The efficiency of spend is looked at through the cost performance indicator (CPI) and productivity through the schedule performance indicator (SPI).
E.g. if tracking earned value for project progress on a graph, with time on the x-axis and cost on the y-axis. There would be three lines plotted:
Actual cost
Budget
Earned value
Actual cost and earned value are plotted to present time (time now). Budget, is the estimate for the whole project timeline, which increases in line with the lines for actual cost and earned value, sitting between the two.
monitor progress against baselined budgets, timelines, and success criteria is completed in what forms
Decision gates
Benefit reviews
Stage reviews
Audits
What is included within reporting
actual costs versus forecasted costs.
actual spend versus forecasted spend against a set spend curve.
actual spend versus actual work achieved by looking at the efficiency of spend (earned value analysis).
estimated project budget and the forecasted cost overrun based on planned completion dates.
cashflow and drawdown requests.
resource costs.
change request costs.
contingency drawdown requests.
financial benefit realisation.
What is required when closing down finances
Reassign resources
Formally close contracts
Accounting and management systems updated
Surplus funding returned
You are the project manager for a project due to go into definition phase. Your task is to complete a project budget, including a cost breakdown structure (CBS).
Explain what a cost breakdown structure is
Identifies all activity within a project that has a cost associated with it.
Breaks down project activity into work packages and assigns costs to each work package.
Breaks down a high-level project budget into individual costs associated with the work required to produce deliverables.
You are the project manager for a project due to go into definition phase. Your task is to complete a project budget, including a cost breakdown structure (CBS).
Explain: four types of costs that could be included in a CBS.
Fixed cost – supplied at a fixed price, no matter the level of resource used.
Variable cost – these vary according to the level of resource used.
Recurring cost – these recur at set periods within a project / are event-driven and recur throughout a project.
Non-recurring cost – these happen once in a project and contribute a single cost to the project.
Direct cost – these are directly related to the production of the project outputs.
Indirect cost – these are associated with the cost of operating the business, not specific to the project
State two review points during a project where it would be appropriate to report on financial performance
Decision gates
Benefit reviews
Stage reviews
Audits
Post-implementation reviews
A key step in closing down project finances is to _______(a)_______ to make sure that the project is not over-charged.
If there is any surplus budget at the end of a project, it should be _______(b)_______…
(a) Reassign resources
(b) Returned to the business
What is Risk management
Risk management ensures that overall or individual risk events can be understood and managed effectively.