PM Documents Flashcards
Name the process each output document belongs to (37 cards)
Activity Attributes
Define Activities
Activity cost estimates
Estimate costs
Activity duration estimates
Estimate activity duration
Activity list
Define Activities
Activity resource requirements
Estimate Activity resources
Agreements
Conduct Procurements
Basis of estimates
Estimate Costs
Change Log
Perform Integrated Change Control
Change requests
All Execute and Control processes
Cost and Schedule forecasts
Control costs and Control schedule
Issue Log
Manage stakeholders
Milestone list
Define Activities
Procurement documents
Plan procurement
Procurement SOW
Plan procurement
Project calendars
Develop schedule
Project charter
Develop Project Charter
Project funding requirements
Determine Budget
Project schedule
Develop schedule
Project schedule network diagrams
Sequence Activities
Project Staff Assignments
Acquire Project Team
Project Statement of work
From sponsor
Quality checklists
Plan quality management
Quality control measurements
Control quality
Quality metrics
Plan quality management