PMI Lexicon of Project Management Terms Flashcards
(145 cards)
A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria
A distinct, scheduled portion of work performed during the course of a project.
Activity
The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost
A technique for estimating the duration or cost of an activity or a project, using historical data from a similar activity or project.
Analogous Estimating
An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. (Note: Apportioned effort is one of three earned value management [EVM] types of activities used to measure work performance.)
Apportioned Effort
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Assumption
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison.
Baseline
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-up Estimating
The sum of all budgets established for the work to be performed.
Budget at Completion
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected.
Change Control
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating such decisions.
Change Control Board
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Change Control System
A formal proposal to modify any document, deliverable, or baseline.
Change Request
A numbering system used to uniquely identify each component of the work breakdown structure.
Code of Accounts
A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated.
Communication Management Plan
A limiting factor that affects the execution of a project, program, portfolio, or process.
Constraint
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.
Control Account
An intentional activity that realigns the performance of the project work with the project management plan.
Corrective Action
A component of a project or program management plan that describes how costs will be planned, structured, and controlled.
Cost Management Plan
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Performance Index
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Cost Variance
A technique used to shorten the schedule duration for the least incremental cost by adding resources.
Crashing
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Critical Chain Method