PMP Definitions Flashcards
The agreement to be able to assign project resources, make project decisions, and spend project funding
Authority
The process of accumulating, finishing, and interpreting information to achieve completion of a phase or project
Administrative Closure
The process of formally receiving the work of the project: the work should be complete and fulfill the needs for which it was created.
Acceptance
A piece of the project that must be completed (performed); sometimes called a “task”; can be divided into smaller pieces; typically has an assigned resource, cost amount, and expected duration
Activity
Represents the total costs that have actually been accrued up to a particular point in time; also known as actual cost of work performed
Actual Cost (AC
The comparison of a current product to industry standards or past standards to attain a measurement or baseline
Benchmarking
The process of determining the availability of human resources and amassing the team needed to complete the project
Acquire Project Team
A document created to define the project communication needs based on stakeholder needs
Communications Management Plan
A data-generating technique which includes team members or subject matter experts for the purpose of solving project problems, identifying project risk, and planning-related activities
Brainstorming
The process of managing the relationship between buyer and seller
Administer Procurements
A standard established by a company
Company Policy
Activities during which formal acceptance and completion procedures are attained from either a phase or the project itself
Closing Processes
A request for a change on a project that has been approved via formal or informal change request
Approved Change Request (Output/Input)
Requirements that are defined to be completed before the work can be accepted
Acceptance Criteria
A detailed list of activities that project team members use to know what work on the project they are responsible for completing
Activity List (Output/Input)
Process of using a previous project of similar characteristic (size, cost, scope) to estimate a new project
Analogous Estimates (Technique)
A role with a negative attitude toward the project
Aggressors
Tools and techniques used to create the foundation for information transfer on a project
Communications Infrastructure
Compensation in the planning for unknown items that could occur; typically schedule- or cost-related. Sometimes called reserve
Buffer
A formal document showing the hierarchy of components or pieces and their sub-components or sub-pieces that make up the product
Bill of Materials (BOM
The act of not providing certain confidential information to those who should not know about it
Confidentiality
A team-building technique in which team members are located together or as close to each other as possible
Co-location
An educated, logical guess about a variable when its details are unknown on a project or program
Assumption
Diagram that sorts and groups large numbers of brainstorming ideas for review and analysis
Affinity Diagram