PMP Definitions Flashcards

1
Q

The agreement to be able to assign project resources, make project decisions, and spend project funding

A

Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The process of accumulating, finishing, and interpreting information to achieve completion of a phase or project

A

Administrative Closure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The process of formally receiving the work of the project: the work should be complete and fulfill the needs for which it was created.

A

Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A piece of the project that must be completed (performed); sometimes called a “task”; can be divided into smaller pieces; typically has an assigned resource, cost amount, and expected duration

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Represents the total costs that have actually been accrued up to a particular point in time; also known as actual cost of work performed

A

Actual Cost (AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The comparison of a current product to industry standards or past standards to attain a measurement or baseline

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The process of determining the availability of human resources and amassing the team needed to complete the project

A

Acquire Project Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A document created to define the project communication needs based on stakeholder needs

A

Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A data-generating technique which includes team members or subject matter experts for the purpose of solving project problems, identifying project risk, and planning-related activities

A

Brainstorming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The process of managing the relationship between buyer and seller

A

Administer Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A standard established by a company

A

Company Policy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Activities during which formal acceptance and completion procedures are attained from either a phase or the project itself

A

Closing Processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A request for a change on a project that has been approved via formal or informal change request

A

Approved Change Request (Output/Input)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Requirements that are defined to be completed before the work can be accepted

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A detailed list of activities that project team members use to know what work on the project they are responsible for completing

A

Activity List (Output/Input)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Process of using a previous project of similar characteristic (size, cost, scope) to estimate a new project

A

Analogous Estimates (Technique)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A role with a negative attitude toward the project

A

Aggressors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Tools and techniques used to create the foundation for information transfer on a project

A

Communications Infrastructure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Compensation in the planning for unknown items that could occur; typically schedule- or cost-related. Sometimes called reserve

A

Buffer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A formal document showing the hierarchy of components or pieces and their sub-components or sub-pieces that make up the product

A

Bill of Materials (BOM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The act of not providing certain confidential information to those who should not know about it

A

Confidentiality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A team-building technique in which team members are located together or as close to each other as possible

A

Co-location

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

An educated, logical guess about a variable when its details are unknown on a project or program

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Diagram that sorts and groups large numbers of brainstorming ideas for review and analysis

A

Affinity Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
A network diagramming method in which activities are shown on arrows and connected at nodes to show the sequence of activities. Also known as ADM, AOL
Activity-on-arrow (AOA)
26
Estimate/plan that the project tries to achieve (cost, scope, time, etc.)
Baseline              
27
A predictable source of variation in a system
Common Cause
28
Deliver needed project information to stakeholders in an appropriate timeframe
Distribute Information
29
Compensation in the planning for unknown items that could occur; typically schedule- or cost-related; also commonly called buffer
Contingency Allowance
30
A type of power that can involve using a middle person to negotiate for the Project Manager
Attitude Power
31
A situation in which an individual or company engages in behavior that is inappropriate, but not necessarily illegal (it could be illegal)
Conflict of Interest         
32
Analyze variances between actual performance and planned performance to effect improvements
Control
33
A technique to determine if the project assumptions are accurate, consistent, and complete and, if not, the resultant risks to the project
Assumption Analysis     
34
An approach in which a previous project of similar characteristic is used to obtain the values (duration, resources, budget, etc.) for the current project being planned
Analogy Approach          
35
A network diagramming method in which activities are shown on the boxes or circles of the network diagram and connected via arrows. Also known as PDM
Activity-on-node (AON)               
36
A detailed estimating approach that usually involves team input - As the team builds the pieces of the estimate, they build the total estimate from the bottom up.
Bottom-Up Estimating  
37
Creation and delivery of a product that has met the specified requirements and conformance (or functionality) of use
Conformance   
38
A role that interrupts information flow on the project
Blockers 
39
A report that includes significant variations from the planned activities
Exception Report            
40
Pre-established actions that the team executes if a known risk event occurs on the project
Contingency Plans          
41
A demand for consideration, under the terms of a contract, by a buyer from a seller or by a seller from a buyer
Claim    
42
The process that protects the ownership rights of writing, songs, and other "creative" works; can include software, music, physical and electronic media.
Copyright           
43
Standards to which project variables are compared for acceptability
Criteria
44
The formal or informal process of reviewing changes associated with a project; will result in approval or rejection of changes
Change Control
45
An approach in which the team or at least the Project Manager is involved in deciding on and estimating the individual pieces of the project to create the summary estimate
Bottom-up Approach    
46
A network diagramming method that calculates the late start (LS) and late finish (LF) dates for each activity
Backward Pass 
47
The total amount of money expected to be spent on a project based on the original cost estimates plus any approved changes
Budget
48
The point where the project and product meet the standards of the written specifications defined at project inception (or modified through change control)
Conformance to Requirement  
49
A role that helps focus on making sure people on the project understand what the details of the project entail
Clarifiers             
50
Estimates related to future project performance that are based on historical information and current project knowledge
Forecasts            
51
Reserves that can help mitigate schedule or cost issues (risk), in the case of changes with the scope or quality on the project
Contingency Reserves (Output/Input)  
52
The process of completing the contract; includes settlement on any open items
Close Procurements      
53
The standards we use to determine what is right and wrong; varies for everyone
Ethics   
54
The individual, group, or company that will own the work of the project when it is complete
Customer
55
A group of people formally recognized to approve or reject requested changes on a project
Change Control Board (CCB)      
56
A technique used with groups to generate a large number of ideas
Brainstorming   
57
A chart that shows a time relationship between the activities of the project; also commonly called a Gantt chart
Bar Chart (Tool)               
58
Total project budget; amount of money planned to be spent by the time the project is complete; sum of all planned value (PV)
Budget at Completion (BAC)      
59
A graph of data that shows the measurement of a process over elapsed time
Control Chart 
60
A type of power that uses negative approaches including threatening and punishment to get people to do things they don't want to do
Coercive/Penalty Power   
61
The process of identifying all people or entities that are impacted by the project and detailing their involvement and impact on the project
Identify Stakeholders   
62
The product of multiplying the monetary value impact and probability of the risk event; helps an organization make decisions based on potential outcome and impact
Decision Tree Analysis (Technique)         
63
The process of receiving proposals, quotes, and bids, selecting a seller and establishing a contract for goods or services
Conduct Procurements
64
An attitude that one's group is superior to others
Ethnocentrism 
65
A company, business, or other formal structure that encompasses a business function
Enterprise
66
A documented, formal process that manages change associated with the project
Change Control System
67
The process of documenting the needs of the stakeholders that align with the project objectives
Collect Requirements   
68
A model for parallel programs with ingoing (inclusive) and outgoing (excusive) links
BiPert   
69
An estimate used to put money into a company's (or project's) budget
Budgetary Estimate       
70
The area of measurement three standard deviations (or Sigma) from the mean on a control chart
Control Limits   
71
A type of power that uses commitment via alliances and partnerships on the project team to tackle challenges to the project as they arise; has a potential connection with referent power
Commitment Power      
72
A meeting used to initiate the start of the project; typically attended by all the key stakeholders; can be done when Initiating or Planning is complete depending upon the organization
Kickoff Meeting               
73
The product of multiplying the monetary value impact and probability of the risk event
Expected Monetary Value (EMV) (Analysis)       
74
A mutually binding agreement that requires the services provider to supply the specified services or goods and requires the buyer to pay for them per the terms of the document
Contract              
75
An organization that represents and manages an area.  The area can be a city, state, or country.  In the United States, the federal government runs the country.  Each state is responsible for operating the state.  There can be city, state, or federal laws.
Government     
76
Any internal or external organization variables that can influence the project success Examples: company culture, the business market, technology, and personnel
Enterprise Environmental Factors (Output/Input)
77
The process of maintaining and adjusting the scope of the project as approved
Control Scope   
78
The separation (or divergence) of activities on a network diagram from a central node
Burst    
79
A structure used to monitor project cost that usually aligns with a company's accounting system and WBS of the project or program
Chart of Accounts (Tool)              
80
A type of power that maximizes involvement in the project or idea in the form of competition to help enhance the commitment of those involved to work toward a more successful outcome of the project or idea
Competition Power       
81
The process of communicating with the stakeholders to determine their expectations and addressing issues in a timely manner
Manage Stakeholder Expectations          
82
A type of plan created for risks with a great impact on project goals, to be executed if attempts to minimize the risk are not successful
Fallback Plans   
83
A contract in which the supplier receives payment for allowable costs plus a fixed fee typically based on estimated cost
Cost-plus-fixed-fee (CPFF) Contract       
84
Money or other items of value that are "earned" via improper activities
Inappropriate Compensation    
85
The coordination of personnel and additional resources to implement the project management plan and create the deliverables of the project
Executing Processes
86
The process of finalizing all project activities to formally complete a project or phase
Close Project or Phase  
87
The process of dividing deliverables and work into smaller components for easier management
Create WBS       
88
The smallest time unit used in project schedules such as minutes, hours, shifts, days, weeks, months, quarters
Calendar Unit   
89
A numbering system used in project management to identify pieces of the work breakdown structure
Code of Accounts (Tool)              
90
Cost associated with not meeting quality expectations of the project or product
Cost of Nonconformance            
91
A conflict resolution technique in which a solution involves (typically) a little of what everyone is proposing for a solution
Compromise     
92
An integrated scope-schedule-cost plan that is used as the basis for execution measurement and performance management
Performance Measurement Baseline    
93
The process of determining which risks can impact a project and the documentation of their properties or characteristics
Identify Risks    
94
A contract in which the supplier receives payment for allowable costs, as well as a pre-negotiated fee and an incentive fee (if incentives are met)
Cost-plus-incentive-fee (CPIF) Contract               
95
Ideas and concepts created by an individual or company, typically eligible for copyright or patent, thus providing ownership properties
Intellectual Property     
96
A manager of a department or unit in a functional organization entity whose personnel are most directly involved in performing the work of the project
Functional manager
97
A process which verifies that the products of the project are complete and accurate
Configuration Management   
98
The process of breaking down work of the project into smaller controllable pieces
Decomposition (Technique)
99
The process of monitoring and updating the progress of the project and managing changes to scope
Control Schedule
100
A point where scope, time, budgeted cost, and actual cost come together to measure performance on a project - The control account is sussed at multiple interface points on the project. 
Control Account (Tool)
101
Cost of conformance to requirements and non-conformance
Cost of Quality (CDQ) (Technique)
102
Directing dealing with a conflict via problem-solving techniques so that the parties can work through any disagreement 
Confrontation
103
The collection and interpretation of performance data; can include status, progress, and forecast reports
Performance Reporting (Output/Input)
104
The process of monitoring known risks, reducing any risks, identifying any new risks, and monitoring risk reduction over the life of the project
Monitor and Control Risks
105
A contract that reimburses the seller for cost, plus a negotiated percentage of the total costs
Cost-plus-percentage of Cost (CPPC) Contract
106
A standard created by a government (e.g., city, state, or country) that requires people and companies to follow it or the behavior is illegal
Law
107
The processes required to develop the activities to attain an objective
Planning Processes
108
A plan that defines the process for controlling change to configurable items that require formal change control
Configuration Management Plan
109
The process of developing a project scope statement
Define Scope
110
A duration compression technique in which more people are added to critical path activities to shorten the duration of the critical path or other impacted areas of the schedule
Crashing
111
The process of controlling changes to the budge and monitoring project spending Cost Management Plan. The document that explains how to handle cost estimations, budgeting, variances, and other cost-related items on the project. 
Control Costs
112
A problem or error in the creation of the work of the project
Defect
113
The process of defining a communications approach for the project
Plan Communications
114
A technique used to simulate the outcome of a project many times to determine the range of possible outcomes and the probability of their occurrence
Monte Carlo Analysis     
115
A contract in which a supplier is paid for direct and indirect cost actually incurred on the project
Cost-reimbursable (CR) Contract         
116
A document signed by the owner of intellectual property and those who view it when it is not generally exposed to the public, or if it is a new idea, before it is displayed to the public
Non-disclosure Agreement (NDA)
117
The process of improving the project management team to optimize project performance
Develop Project Team   
118
A report that states what has been accomplished in a specific amount of time on the project (but not the entire project)
Progress Report                 
119
Perform Qualitative Risk Analysis             
Perform Qualitative Risk Analysis             
120
Analyze risks and determine the priority of their effects on the project
Analyze risks and determine the priority of their effects on the project
121
A contract in which the seller provides products or services based on a well defined scope of work for a set price
Firm-fixed-price (FFP) Contract
122
A legal device which gives ownership of an idea or design to an individual or company that creates the idea or design
Patent  
123
Managing various portfolios that include the projects and programs of which they consist; can include prioritization, authorization, and management
Portfolio Management (Techniques)       
124
Actions on a project that will correct a component of the project that is out of alignment with the baseline
Corrective Actions       
125
A technique to attain consensus within a group of experts; typically used to gain vision about future direction or development
Delphi Technique
126
The series of activities that shows the overall duration of the project; can change as the project evolves
Critical Path      
127
A ratio that shows the current efficiency of money being spent on the project; Formula: EV/AC - A value of one means you are getting out what you put in (which is good); less than one is bad; greater than one is good.
Cost Performance Index (CPI)     
128
A process that examines which variables have the greatest outcome on a process or product
Design of Experiments (DOE)      
129
A role that contradicts popular views or opinions about the work of the project
Devil's Advocate                
130
The processes required to ensure that project information is amassed and distributed in a timely and appropriate manner to the appropriate parties
Project Communications Management
131
Measure the probability and impact of the risks and estimate the impact on the project
Perform Quantitative Risk Analysis
132
A contract that pays a seller a fixed price for a well defined or detailed product or service
Fixed-price Contract
133
A standard that PMI requires candidates to agree to before they take the PMP Examination
PMI Code of Ethics and Professional Conduct 
134
The generally sequential phases of a product
Product Life Cycle             
135
The process of developing the project charter
Develop Project Charter           
136
Decision made via one individual
Dictatorship          
137
A network analysis method used to calculate total project duration
Critical Path Method (CPM) (Technique)           
138
The difference between what has been built (EV) and what the cost was to build it (AC); Formula: EV-AC - A value of zero (0) means the project is creating what it should for the cost as planned.  A negative value means you are over budget; a positive value means you are under budget. 
Cost Variance (CV)            
139
A process that analyzes every failure mode in every piece of a product - The analysis is then reviewed for impact on every aspect of the system. 
Failure Mode and Effect Analysis (FMEA)              
140
A role that consumes project communication and focus with their own views without considering others
Dominators       
141
A reporting method in which future performance is estimated based on past performance of the project
Project Forecasting