PMP Formulas Flashcards
AC (Actual Cost)
ACWP (Actual Cost of Work Performed)
Definitive Estimate?
-5% to +10%
Variance (= s2))?
Variance = ((P-O)/6)^2
Internal Rate of Return (IRR)?
Net Investment / Avg. Annual Cash Flow.
Higher is better. Also called Hurdle Rate
Expected Monetary Value?
Probability * Impact
Schedule Performance Index (SPI)?
SPI = EV / PV
Less than 1 is behind schedule
Budget Estimate?
-10% to +25%
Communication Channel?
n(n-1)/2
Working Capital?
Current Assets - Current Liabilities
% Communication of a PM?
90%
Benefit Cost Ratio?
Benefit / Cost
(Higher is better, >1 has benefit)
Exam can call it Cost-Benefit Ratio, where lower is better.
PERT Mean Estimate?
PERT=(P+4m+O)/6 3 estimates for each task: . P: Pessimistic . M: Most Likely . O: Optimistic
Return on Assets (ROA)?
NEBT / Total Assets
OR
NEAT / Totals Assets
Sigma (o)?
1o = 68.27% 2o = 95.45% 3o = 99.73% 6o = 99.99985%
Rough Order of Magnitude (ROM)?
-25% to +75%
-50 to +100%
Arrow Diagramming Method (ADM)?
Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have “dummies”
Can analyze using either Three-Point Estimates or CPM
Scheduled Variance (SV)?
SV = EV - PV
Minus is behind schedule
GERT?
Allows loops and repetitive activities
Expected Monetary Value?
Probability * Impact
Variance at Completion (VAR)?
VAC = BAC - EAC
Budgeted Estimate?
-10% to +25%
To Complete Performance Index (TCPI)?
TCPI = (BAC - EV) / (BAC - AC)
Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete as less than planned. How efficient must the project team be to complete the remaining work with the remaining money.
ROI (Return on Investment)?
ROI = Earnings
Investment / Higher ROI is better
Payback period?
Time to recover cost of the project.
Lower payback period is better.