PMP FORMULAS Flashcards

1
Q

PERT

A

(P+4M+O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

STANDARD DEVIATION

A

(P-O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

VARIANCE

A

[(P-O)/6]SQUARED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

FLOAT OR SLACK

A

LS (LATE START)-ES (EARLY START) AND LF (LATE FINISH)- EF (EARLY FINISH)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV (COST VARIANCE) FORMULA

A

EV (EARNED VALUE)-AC (ACTUAL COST)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV (SCHEDULE VARIANCE) FORMULA

A

EV (EARNED VALUE) -PV (PLANNED VALUE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI (COST PERFORMANCE INDEX) FORMULA

A

EV (EARNED VALUE)/AC (ACTUAL COST)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

ETC (EST TO COMPLETE) FORMULA

A

EAC (ESTIMATE AT COMPLETE) - AC (ACTUAL COST)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PERCENT COMPLETE

A

EV/BAC (BUDGET AT COMPLETE)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC (ESTIMATE AT COMPLETE) FORMULA

A

BAC/CPI
AC+ETC
AC+BAC-EV
AC+(BAC-EV)/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ETC (ESTIMATE TO COMPLETE)

A

EAC (EST AT COMPLETE)- AC (ACTUAL COST)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

VAC (VARIANCE AT COMPLETION)

A

BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPI (TO COMPLETE PERFORMANCE INDEX)

A

TCPI < 1.0 IS GOOD. EFFICIENCY TO COMPLETE IS LESS THAN PLANNED
(BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NPV (NET PRESENT VALUE)

A

BIGGER IS BETTER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

IRR (INTERNAL RATE OF RETURN)

A

BIGGER IS BETTER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

BENEFIT COST RATIO

A

BIGGER IS BETTER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

PAYBACK PERIOD

A

LESS IS BETTER

NET INVESTMENT/AVG ANNUAL CASH FLOW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

ORDER OF MAGNITUDE ESTIMATE

A
  • 25% + 75%

PMBOK -50% + 100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

BUDGET ESTIMATE

A
  • 10% + 25%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

DEFINITIVE ESTIMATE

A

-5% + 10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

COMMUNICATION CHANNELS

22
Q

EXPECTED MONETARY VALUE

A

PROBABILITY * IMPACT

23
Q

POINT OF TOTAL ASSUMPTION

A

(CEILING PRICE - TARGET PRICE)/BUYER’S SHARE RATIO + TARGET COST

24
Q

1SIGMA

25
2SIGMA
95.45%
26
3SIGMA
99.73%
27
6SIGMA
99.99985%
28
RETURN OF SALES (ROS)
NET INCOME BEFORE TAXES (NEBT)/TOTAL SALES OR NET INCOME AFTER TAXES (NEAT)/TOTAL SALES
29
ROA (RETURN OF ASSETS)
NEBT/TOTAL ASSETS OR NEAT/TOTAL ASSETS
30
ROI (RETURN OF INVESTMENT)
NEBT / TOTAL INVESTMENT OR NEAT / TOTAL INVESTMENT
31
SPI (SCHEDULE PERFORMANCE INDEX)
SPI = EV/PV (EARNED VALE / PLANNED VALUE)
32
% COMPLETE
EV / BAC X 100
33
TOTAL COST
CONTRACT INCENTIVES | ACTUAL COST + CONTRACT COST
34
CONTRACT COST
CONTRACT INCENTIVES | BONUS + FEE
35
BONUS
cONTRACT INCENTIVES | SAVINGS x PERCENTAGE
36
SAVINGS
CONTRACT INCENTIVE | TARGET COST - ACTUAL COST
37
MODE
THE "MOST FOUND" NUMBER
38
MEAN
AVERAGE
39
RANGE
LARGEST - SMALLEST MEASURE
40
MEDIUM
NUMBER IN THE MIDDLE OR AVERAGE OF 2 MIDDLE NUMBERS
41
COQ (COST OF QUALITY)
REVIEW EFFORTS + TEST EFFORTS + TRAINING EFFORTS + REWORK EFFORTS + EFFORTS OF PREVENTION/TOTAL EFFORTS) X 100%
42
PDM
P 177 | TAKE LONGEST DURATION OF EACH ACTIVITY AND ADD.
43
CRITICAL PATH
NO FLOAT AND LONGEST DURATION OF ACTIVITIES. | P 177
44
FOR ESTIMATING DURATION WITHOUT WEIGHT USE WHAT?
USE SIMPLE AVERAGE
45
ROR = Rate of Return
(total return/initial invenstment)*100/years
46
SPI formula
EV/PV
47
EV Formula
SPI*PV
48
EXPECTED PROFIT FORUMLA
EACH ALTERNATIVE =PERCENTAGE*DOLLAR AMOUNT OF PROFIT THEN ADD ALL ALTERNATIVES P 339
49
FFP = FIRM FIXED PRICE
CONTRACT TYPE FOR FIXED - SCOPE PROJECT
50
FPIF=FIXED PRICE INCENTIVE FEE
CONTRACT TYPE WHEN SCOPE IS FIXED BUTH NEED FLEXIBILITY FOR PERFORMANCE GOALS
51
COST REIMBURSABLE
CONTRACT TYPE WHEN SCOPE CANNOT BE PRECISELY DEFINED