PMP - Performance Flashcards
(15 cards)
Examples of Performance reports
Milestone - Updated milestone charts and activity sequences
Dashboards -
Work performance reports
Variance analysis reports
Quality reports
Earned value Graphs management (EVM) reports
Burndown Chart
shows the amount of work left/remaining vs. the work done
tracks the work to be completed in the iteration, used to analyze variance to ideal
keep it at the end date
Parkinson’s law - people are motivated closer to end of a project
Burnup Chart
aka feature complete graph
show accumulated progress of completed work
update after each iteration
another line with the total backlog
velocity chart
team’s estimate rate of work compared to actual completed work
goal to achieve constant velocity
limiting work in process to make sur we dont get behind
* never compare teams
task board (agile)
to do, work in progress, done
move stickies across the three columns
continous/cummulative flow diagram
shows backlog, WIP, and done over time
Earned Value Management
planned value
earned value
actual cost
budget at comparison – bac
graph that can show that even if you are underbudget you might be underproducing.
Schedule Variance Forumula
schedule variance = Earned value - planned value
SV = EV - PV
SV = 0 – project on schedule
negative – behind
positive ahead
schedule performance index
Schedule Performance index = earned value / planned value
SPI = EV - PV
SPI = 1 – project on schedule
less than 1 - behind schedule
more than 1 - ahead of schedule
estimate at completion (EAC)
EAC = BAC/CPI
estimate at completion = budget at completion / current spending efficiency
what will the project cost in total?
estimate to completion (ETC)
ETC = EAC - AC
estimate to completion = estimate at completion - actual cost
how much more money you need from today to end of the project
Data representation for quality control
cause and affect diagram
scatter diagrams
control charts
histograms
pareto chart - 80/20 rule
4 change request types
corrective action plan
preventive action
defect repair
update
contract change control system
separate system just for changing contracts
separate organizational system