PMP Study Guide CH01-CH12 Flashcards
Which organization has set the de facto standards for project management techniques?
A. PMBOK®
B. PMO
C. PMI®
D. PBO
C. The Project Management Institute (PMI®) is the industry-recognized standard for project management practices.
The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered which of the following?
A. Project initiation
B. Ongoing operations
C. A project
D. Project execution
B. Projects exist to create a unique product, service, or result. The logon screen in this question is not a unique product. A minor change has been requested, indicating that this is an ongoing operations function. Some of the criteria for projects are that they are unique, temporary with definitive start and end dates, and considered complete when the project goals are achieved.
Your company manufactures small kitchen appliances. It is introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. Which of the following is true?
A. This is a project because this new product line has never been manufactured and sold by this company before.
B. This is an ongoing operation because the company is in the business of manufacturing kitchen appliances. Introducing designer colors and features is simply a new twist on
an existing process.
C. This is an ongoing operation because the new product line will be sold indefinitely. It’s not temporary.
D. This is not a project or an ongoing operation. This is a new product introduction not affecting ongoing operations.
A. This is a project. The product line is new, which implies that this is a unique product—it hasn’t been done before. You can discern a definite start and end date by the fact that the new appliances must be ready by the spring catalog release.
Your company manufactures small kitchen appliances. It is introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. To determine the characteristics and features of the new product line, you will have to perform which of the following?
A. Fast tracking
B. Consulting with the stakeholders
C. Planning the project life cycle
D. Progressive elaboration
D. Progressive elaboration is the process of determining the characteristics and features of the product of the project. Progressive elaboration is carried out via steps in detailed fashion.
A project is considered successful when________.
A. The product of the project has been manufactured
B. The project sponsor announces the completion of the project
C. The product of the project is turned over to the operations area to handle the ongoing aspects of the project
D. The project achieves its objectives and meets the expectations of the stakeholders
D. A project is considered successful when it achieves its objectives and stakeholder needs and expectations are met.
The VP of customer service has expressed concern over a project in which you’re involved. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true?
A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should be revisited to examine the project plan and determine how changes can be made to accommodate customer service.
B. The conflict should be resolved in favor of the customer.
C. The conflict should be resolved in favor of the project sponsor.
D. The conflict should be resolved in favor of the VP of customer service.
B. Conflicts between stakeholders should always be resolved in favor of the customer. This question emphasizes the importance of identifying your stakeholders and their needs as early as possible in the project.
Which of the following applies a set of tools and techniques used to describe, organize, and monitor the work of project activities to meet the project requirements?
A. Project managers
B. The PMBOK® Guide
C. Project management
D. Stakeholders
C. Project management brings together a set of tools and techniques to organize project activities. Project managers are the ones responsible for managing the project management processes.
All of the following are true regarding multiphased relationships except for which one?
A. Planning for an iterative phase begins while the work of other phases is progressing.
B. Overlapping phases occur when more than one phase is being performed at the same time.
C. During sequentially phased projects, the previous phase must finish before the next phase can begin.
D. Phase reviews should occur at the end of every phase.
B. There are three ways phases can be performed in a multiphased project: sequential, iterative, and overlapping. Iterative is when more than one phase is being performed at the same time and overlapping occurs when one phase starts before the prior phase completes. All phases should perform a phase gate review.
All of the following statements are true except for which one?
A. Programs are groups of related projects.
B. Project life cycles are collections of sequential, iterative, and overlapping project phases.
C. A project may or may not be part of a program.
D. Portfolios are collections of interdependent projects or programs.
D. Portfolios are collections of projects and/or programs. The projects or programs do not have to be directly related or interdependent to reside within the portfolio.
You are a project manager for a large software development project. You are using an Agile approach to manage this project. The product owner has prioritized the backlog. How will team members be assigned this work?
A. They will choose items from the backlog list at the sprint planning meeting.
B. The project manager will assign work according to skill and availability.
C. They will choose items from the backlog list at the daily standup.
D. The Scrum master will assign work according to skill and availability.
A. Team members choose items from the backlog list to work on during the upcoming sprint at the sprint planning meeting.
You’ve decided to try your hand at project management in the entertainment industry. You’re working on a movie production and the phases are performed sequentially. The team
has just completed the storyboard phase of the project. Which of the following is true?
A. The storyboard is a deliverable that marks the end of the phase.
B. The storyboard phase marks the end of the Initiating process group, and the next phase of the project should begin.
C. The writing phase can begin once the majority of the storyboard phase is complete.
D. The division of phases and determining which processes to use in each phase is called tailoring.
A. The storyboard is a deliverable. Because the phases are performed sequentially, the deliverable must be approved before the next phase of the project can begin.
You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs. You’ve attempted to gain the cooperation of the business analyst working on this project, and you need some answers. She is elusive and tells
you that this project is not her top priority. What should you do to avoid situations like this in the future?
A. Establish the business analyst’s duties well ahead of due dates, and tell her you’ll be reporting on her performance to her functional manager.
B. Establish the business analyst’s duties well ahead of due dates, and tell her you are expecting her to meet these expectations because the customer is counting on the project meeting due dates to save significant costs on their annual mailings.
C. Negotiate with the business analyst’s functional manager during the planning process to establish expectations and request to participate in the business analyst’s annual performance review.
D. Negotiate with the business analyst’s functional manager during the planning process to establish expectations, and inform the functional manager of the requirements of the project. Agreement from the functional manager will ensure the cooperation of the business analyst.
C. The best answer to this question according to the PMBOK ® Guide is to negotiate with the functional manager to participate in the business analyst’s annual performance review.
Option D is an appropriate response but doesn’t include the direction that the project manager should participate in the performance review.
The amount of authority a project manager possesses can be related to all of the following except which one?
A. The organizational structure
B. The key stakeholder’s influence on the project
C. The interaction with various levels of management
D. The project management maturity level of the organization
B. The level of authority the project manager has is determined by the organizational structure, interactions with various management levels, and the project management maturity level of the organization.
What is one of the advantages of a functional organization?
A. All employees report to one manager and have a clear chain of command.
B. All employees report to two or more managers, but project team members show loyalty to functional managers.
C. The organization is focused on projects and project work.
D. Teams are co-located.
A. Advantages for employees in a functional organization are that they have only one supervisor and a clear chain of command exists.
You have been assigned to a project in which the objectives are to direct customer calls to an interactive voice response system before they are connected to a live agent. You are in charge of the media communications for this project. You report to the project manager in charge of this project and the VP of marketing, who share responsibility for this project.
Which organizational structure do you work in?
A. Functional organization
B. Weak matrix organization
C. Project-oriented organization
D. Balanced matrix organization
D. Employees in a balanced matrix often report to two or more managers. Functional managers and project managers share authority and responsibility for projects. There is a balance of power between the functional managers and project managers.
You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. This project is producing deliverables in short periods of time. You work with the product owner. Your project team holds daily standup meetings and they hold retrospective meetings at the end of the working period. What methodology does this describe?
A. Iterative
B. Adaptive
C. Agile
D. Incremental
C. This question describes the Agile methodology, which uses daily standups, sprint planning meetings, and retrospectives, and works with a Scrum master and product owner.
What are the five project management process groups, in order?
A. Initiating, Executing, Planning, Monitoring and Controlling, and Closing
B. Initiating, Monitoring and Controlling, Planning, Executing, and Closing
C. Initiating, Planning, Monitoring and Controlling, Executing, and Closing
D. Initiating, Planning, Executing, Monitoring and Controlling, and Closing
D. Remember the acronym that sounds like syrup of ipecac: IPECC (Initiating, Planning, Executing, Monitoring and Controlling, and Closing).
You have been assigned to a project in which the objectives are to expand three miles of the north-to-south highway through your city by two lanes in each direction. You are interested in implementing a new project process called Design-Build in order to speed up the project schedule. The idea is that the construction team will work on the first mile of the highway reconstruction at the same time the design team is coming up with plans for the third mile of the reconstruction rather than completing all design before any construction begins. This is an example of which of the following?
A. Managing the projects as a program
B. An iterative phase relationship
C. Progressive elaboration
D. Handoffs
B. An iterative phase relationship allows you to work more than one phase at a time.
During which project management process group are risk and stakeholder’s ability to influence project outcomes the highest?
A. Planning
B. Executing
C. Initiating
D. Monitoring and Controlling
C. The Initiating process group is where stakeholders have the greatest ability to influence outcomes of the project. Risk is highest during this stage because of the high degree of unknown factors.
All of the following are true regarding a PMO except for which one?
A. There are three types of PMOs: supportive, controlling, and collaborative.
B. The PMO is often responsible for implementing the OPM.
C. The key purpose of the PMO is to provide support to project managers.
D. The PMO facilitates communication within and across projects.
A. The three types of PMOs are supportive, controlling, and directive.
Which of the following statements is not true regarding EEFs and OPAs?
A. OPAs are external to the organization.
B. EEFs are outside the control of the project team.
C. Resource availability is an example of internal EEF.
D. Change control processes are an example of an OPA.
A. OPAs are internal to the organization. EEFs can be internal or external to the organization but they are always outside the control of the project team.
You’ve been hired as a manager for the adjustments department of a nationwide bank based in your city. The adjustments department is responsible for making corrections to customer accounts. This is a large department, with several smaller sections that deal with specific accounts, such as personal checking or commercial checking. You’ve received your first set of management reports and can’t make heads or tails of the information. Each section appears to use a different methodology to audit their work and record the data for the management report. You request that a project manager from the PMO come down and get started right away on a project to streamline this process and make the data and reports consistent. This project came about as a result of which of the following? A. Technological advance B. Organizational need C. Customer request D. Legal requirement
B. This came about because of an organizational need. Staff members were spending unproductive hours producing information for the management report that wasn’t consistent or meaningful.
What are the inputs to the Develop Project Charter process?
A. Agreements, business documents, EEFs, and OPAs
B. Business case, benefits management plan, and OPAs
C. Agreements, EEFs, and OPAs
D. Business case, benefits management plan, EEFs
A. Develop Project Charter has four inputs, and they are business documents, agreements, enterprise environmental factors, and organizational process assets.
You work for a large manufacturing plant. Your firm is thinking of initiating a new project to release an overseas product line. This is the company’s first experience in the overseas
market, and it wants to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions is the next best step the project sponsor should take?
A. The project sponsor should document the project’s high-level requirements in a project
charter document and recommend that the project proceed.
B. The project sponsor knows the project is a go and should document the description of the product in the business case.
C. The project sponsor should document the business need for the project and recommend that a feasibility study be performed to determine the viability of the project.
D. The project sponsor should document the needs and demands that are driving the project in a business case document.
C. The most correct answer is to perform a feasibility study. Because this project is taking the company into a new, unknown market, there’s lots of potential for error and failure. A feasibility study would help the stakeholders determine whether the project is viable and cost effective and whether it has a high potential for success.