PMP_Process_Domain_Additional_Brainscape Flashcards

1
Q

What are the three types of project life cycles?

A
  1. Predictive (Waterfall)
  2. Iterative/Incremental
  3. Adaptive (Agile)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key output of Develop Project Charter?

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the main purpose of a Project Charter?

A

Authorizes the project and gives the project manager formal authority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are Organizational Process Assets (OPA)?

A

Internal policies, procedures, templates, and historical data that influence project execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Enterprise Environmental Factors (EEF)?

A

External conditions like laws, culture, and industry standards that impact the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Rolling Wave Planning?

A

Progressive elaboration technique where details are planned as work progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the three types of reserves in cost and schedule management?

A
  1. Contingency Reserve (Known risks)
  2. Management Reserve (Unknown risks)
  3. Schedule Reserve (Time buffer)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the key output of Control Costs?

A

Work Performance Information, Cost Forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the key formula for Cost Variance (CV) in Earned Value Management?

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the key formula for Schedule Variance (SV) in Earned Value Management?

A

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the key formula for Cost Performance Index (CPI)?

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the key formula for Schedule Performance Index (SPI)?

A

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does CPI > 1 indicate?

A

Project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does SPI < 1 indicate?

A

Project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the five conflict resolution techniques?

A
  1. Withdraw/Avoid
  2. Smooth/Accommodate
  3. Compromise/Reconcile
  4. Force/Direct
  5. Collaborate/Problem-Solve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the five stages of Tuckman’s Team Development Model?

A
  1. Forming
  2. Storming
  3. Norming
  4. Performing
  5. Adjourning
17
Q

What is the key output of Control Resources?

A

Work Performance Information, Change Requests

18
Q

What is the primary tool for decision-making in Procurement?

A

Make-or-Buy Analysis

19
Q

What is the key output of Control Procurements?

A

Closed Procurements

20
Q

What are the two types of procurement documents?

A
  1. Request for Proposal (RFP)
  2. Invitation for Bid (IFB)
21
Q

What are the four types of probability & impact matrices?

A
  1. Low Probability / Low Impact
  2. Low Probability / High Impact
  3. High Probability / Low Impact
  4. High Probability / High Impact
22
Q

What is Risk Appetite?

A

The degree of uncertainty an organization is willing to take on.

23
Q

What is Risk Tolerance?

A

The measurable amount of risk an organization can withstand.

24
Q

What is a Probability and Impact Matrix used for?

A

Prioritizing risks based on likelihood and consequence.

25
What is a Stakeholder Engagement Matrix?
Classifies stakeholders by their level of engagement: Unaware, Resistant, Neutral, Supportive, Leading.
26
What is the primary tool for engaging stakeholders?
Stakeholder Engagement Plan
27
What are the four primary project baselines?
1. Scope Baseline 2. Schedule Baseline 3. Cost Baseline 4. Performance Measurement Baseline
28
What is Change Control used for?
Ensures all project changes are properly reviewed and approved before implementation.
29
What is a Work Authorization System?
A system that ensures work is only performed when authorized.
30
What is a Lessons Learned Register?
A document capturing project insights for future reference.