Practical Aspects of Liquidated Damages in Construction Contracts Flashcards
(31 cards)
What is the definition of practical completion and why is it important in construction contracts?
Practical completion is a state of affairs in which works are “free from patent defects, other than ones not to be ignored as trifling.” It is important because it marks the stage when a project is considered substantially complete, triggering various contractual rights and obligations, such as the commencement of the rectification period, release of retention, and the potential liability for liquidated damages.
What are the procedural steps that must be followed in order to deduct liquidated damages from payments due to the contractor?
The steps include confirming a failure by the Contractor to complete the Works by the Completion Date, the Architect issuing a certificate under Clause 2.31, the Employer requiring the payment of liquidated damages in writing no later than the date of the Final Certificate, and giving three necessary notices: a Non-Completion Certificate, a notification that the Employer may require payment of or withhold/deduct liquidated damages, and a notice of deduction.
Explain the concept of sectional completion and its benefits.
Sectional completion is an optional provision that allows for the staggered completion of different sections of a project, enabling the employer to take possession of completed sections while work continues on other sections. It helps manage separate streams for each section, including date for completion, liquidated damages, rectification period, and retention.
What is the role of the Contract Administrator in relation to practical completion, defects, and making good procedures?
The Contract Administrator is responsible for certifying practical completion when works are free from patent defects, other than ones considered trifling. Their role is crucial in determining the rights and obligations of the parties, including the assessment of liquidated damages, defects, and making good procedures.
Describe the defects and making good procedure in a JCT contract post practical completion.
If a defect is identified post-Practical Completion, the Architect can issue instructions requiring the Contractor to make good the defect. The Architect can provide a schedule of defects at the end of the Rectification Period. The Contractor is required to make good the defects at no cost to the Employer, or an appropriate deduction will be made from the Contract Sum. Once the defects have been made good, the Architect shall issue a Certificate of Making Good, which affects the release of the second half of the retention and the timetable for the issue of the Final Certificate.
What is the significance of the Practical Completion Certificate in construction contracts?
The Practical Completion Certificate fixes the dates for the commencement of the Rectification Period, the commencement of the period of the final adjustment of the Contract Sum, the release of the first and second moieties of retention, the point at which the Contractor may first be potentially liable for damage to the Works, the release of the obligation to insure, and the point at which the Employer may assign the right to bring proceedings in its name.
What are the key ingredients for a liquidated damages clause to be effective, and what flaws might give the Contractor grounds to challenge the efficacy of the mechanism?
The key ingredients include a genuine pre-estimate of the damage likely to be suffered by non-completion, proper performance of the Architect’s duties regarding any necessary extension of time, issuance of a certificate under Clause 2.31, and proper notices given. Flaws in the process or deviations from these requirements might give the Contractor grounds to challenge the efficacy of the liquidated damages mechanism.
Explain the concept of partial possession and its implications in a construction contract.
Partial possession occurs when the employer takes possession of a part of the works with the contractor’s consent prior to practical completion. The Contract Administrator issues a written statement identifying the relevant part and date, and practical completion of the relevant part is deemed to have occurred, triggering rectification period commencement, insurance obligations, and proportionate reductions in liquidated damages and retention. It allows the employer to use portions of the project for their intended purpose while the remaining work is still ongoing.
What is the difference between the Certificate of Making Good and the Final Certificate in a JCT contract?
The Certificate of Making Good signifies that the contractor has remedied the defects identified during the rectification period, whereas the Final Certificate is issued within two months of the latest event (end of Rectification Period, issue of Certificate of Making Good, or Contract Administrator adjusts Contract Sum and ascertains loss/expense) and is conclusive regarding Contract Sum adjustment, Extension of Time, and loss/expense, unless a dispute resolution process is initiated within 28 days of the Final Certificate or arbitration/court proceedings within 28 days of an adjudication decision.
How can understanding the concepts of completion, sectional completion, and partial possession help parties manage their rights and obligations in relation to liquidated damages, defects, and making good procedures?
Understanding these concepts helps parties to manage their respective rights and obligations by ensuring that the project is completed to the required standard, by facilitating a well-drafted liquidated damages clause, clear definitions of completion, and a thorough defects and making good procedure, and by reducing the potential for disputes and ensuring a fair outcome for all parties.
How does sectional completion work in construction contracts, and what are its benefits?
Sectional completion is an optional provision that allows for the staggered completion of different sections of a project. It enables the employer to take possession of completed sections while work continues on other sections. Definition of sections is critical for establishing separate streams for each section, including date for completion, liquidated damages, rectification period, and retention. The benefits include increased flexibility, efficient project management, and potential cost savings.
What is the role of the contract administrator in certifying practical completion and addressing defects in a construction contract?
The contract administrator, such as an architect, has the responsibility to certify practical completion when works are free from patent defects, other than ones considered trifling. Their role is crucial in determining the rights and obligations of the parties, including the assessment of liquidated damages, defects, and making good procedures.
What are the consequences if a liquidated damages sum is not a genuine pre-estimate of the damage likely to be suffered by non-completion?
If the liquidated damages sum is not a genuine pre-estimate of the damage likely to be suffered by non-completion, it may be unenforceable as a penalty. In this case, the Employer would have to prove their actual losses.
In a JCT contract, what happens if a defect appears after the Certificate of Making Good is issued?
If defects appear after the Certificate of Making Good is issued, the Architect has no power to issue further instructions but can adjust any further certificate. The Employer may also claim damages for any consequential losses that arise due to the defects.
How can parties to construction contracts manage their risks and achieve a successful outcome by being aware of their rights and obligations in relation to practical completion, defects, and making good procedures, as well as the implications of standard form contracts, such as JCT and NEC contracts?
By understanding their rights and obligations in relation to these issues, parties can proactively manage their risks through effective communication, negotiation, and collaboration. This includes ensuring a well-drafted liquidated damages clause, clear definitions of completion, and a thorough defects and making good procedure, which can reduce the potential for disputes and ensure a fair outcome for all parties involved. Additionally, being familiar with standard form contracts like JCT and NEC can help parties to navigate the specific contractual provisions and procedures more effectively.
What is the primary purpose of a liquidated damages clause in construction contracts?
The primary purpose of a liquidated damages clause is to provide a predetermined sum as compensation for a breach of contract, often used in construction contracts to compensate for delays in completion.
How does partial possession work in construction contracts, and what are its benefits?
In partial possession, the employer may take possession of any part of the works before practical completion with the contractor’s consent. The contract administrator issues a written statement identifying the relevant part and date, and practical completion of the relevant part is deemed to have occurred. This triggers the commencement of the rectification period, insurance obligations, and proportionate reductions in liquidated damages and retention. The benefits include increased flexibility for the employer and the ability to use portions of the project for their intended purpose while the remaining work is still ongoing.
What are some of the key procedural steps that must be followed by the Employer and/or the Contract Administrator to deduct liquidated damages from payments otherwise due to the contractor?
Key procedural steps include confirming the contractor’s failure to complete the works by the completion date, issuing a certificate under the relevant contract clause, requiring the payment of liquidated damages in writing no later than the date of the final certificate, and providing necessary notices such as a non-completion certificate, a notification that the employer may require payment of or withhold/deduct liquidated damages, and a notice of deduction.
What is the Certificate of Making Good in a JCT contract, and why is it important?
The Certificate of Making Good signifies that the contractor has remedied the defects identified during the rectification period. It is important because it affects the release of the second half of the retention and the timetable for the issue of the Final Certificate.
What factors should parties consider when drafting a liquidated damages clause to ensure it is enforceable and reduces the potential for disputes?
What are some key differences between the JCT and NEC standard form contracts in relation to liquidated damages and completion?
The JCT contracts use the term “practical completion” and do not provide a definition, whereas NEC contracts use the term “Completion” and define it as the point at which the works are complete and without defects that would prevent the employer from using them for their intended purpose. The JCT contracts also typically provide separate liquidated damages clauses for each section, while the NEC contracts often use delay damages with a single total amount for the whole project.
In the context of JCT contracts, what is the significance of the Final Certificate?
The Final Certificate, issued within a specified timeframe after the end of the Rectification Period, affects the release of the remaining retention amount and signifies the conclusion of the contractual relationship between the parties. It also serves as conclusive evidence regarding adjustments to the Contract Sum, Extension of Time, and loss or expense, unless a dispute resolution process is initiated within a specified period.
What is the role of the Architect/Contract Administrator in relation to defects and making good procedures under the JCT contracts?
The Architect/Contract Administrator is responsible for identifying defects during the rectification period, issuing instructions to the contractor for making good the defects, providing a schedule of defects, and ultimately issuing a Certificate of Making Good once the defects have been remedied.
In the case of Walter Lilly & Co Ltd v Mackay [2012], how did the court interpret the concept of practical completion in the context of a construction contract?
The court held that de minimis snagging is not a bar to practical completion unless it prevents the building from being used for its intended purpose.