Predictive Plan-Based Methodologies Flashcards

1
Q

How is PERT calculated?

A

E=(O + 4M + P)/6
E=Estimate
O=Optimistic
M=Most likely
P=Pessimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Work breakdown structure

A

A deliverable-oriented grouping of the work involved in a project that defines the total scope of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is schedule variance calculated?

A

EV (Earned Value) - PV (Planned Value) = SV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is critical path method

A

Helps you identify which tasks must be completed on time in order for the project to meet deadlines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly