Prequalification questionnaire, Single Stage Tender and Tender Returns and Analysis Flashcards
(36 cards)
751 What is a prequalification questionnaire? (231)
This is a pre tender exercise to ascertain if a company is suitable to tender of the works it asks questions about their level of experience, capacity and financial standing.
752 What is the purpose of a PQQ?
To whittle down the number of potential candidates to invite to tender. This saves time for both parties, the Client in having to tender to those it may not wish to work with and the contractors for work they are unlikely to win.
753 What might a PPQ ask for?
- Company details
- Relevant information about technical and professional ability
- Project case studies
- Financial information such as company accounts
- References
- Health and safety records and policy
- Environmental management policy
- Equality opportunities policy
- Insurance documents
754 A credit check is usually part of a PQQ. Where could you get this done?
Dun and Bradstreet report or credit agency like Experian.
Single Stage Tendering
755 What is single stage tendering?
A competitive tendering process where by all those tendering bid on the same information (usually RIBA stage 4, detailed design) in an attempt to win the work.
756 What are the key advantages of single stage tendering?
- Competitive pricing as all companies are in direct competition.
- Fixed price - Employer fixes the price at the end of the tender period
757 What are the key disadvantages of single stage tendering?
- Little to no buildability input from the contractors
- The price is only as good as the design information
- Contractors may be unwilling to tender in a good economic climate (too much competition)
757 What are the key disadvantages of single stage tendering?
- Little to no buildability input from the contractors
- The price is only as good as the design information
- Contractors may be unwilling to tender in a good economic climate (too much competition)
758 If you had a £25m new build project under D & B (single stage) how long would you allow for the tender period?
Depends largely on how complex the project is. There is time needed to develop the design and then actually price that design. Allow 10 – 12 weeks as a starting point and increase or decrease, as necessary.
759 What is two stage tendering? (239)
Stage one – The Client provides an outline project design and the contractors then compete for preferred status. Usually chosen on the quality of their bid, quality of their team, prelims & OH & P. The preferred contractor then joins the design team on a consultancy basis using a Preconstruction Services Agreement (PCSA)
Stage 2 – Once the design is sufficiently progressed the contractor enters into a detailed contract negotiation with the employer to agree the final price, contract conditions and programme.
760 What are the key advantages of two stage tendering?
- Overlaps design and construction. Early start on site may be possible
- Early appointment of the contractor can assist in buildability
- Employer may be involved in sub-contractor selection
- Opportunities to VE the contractors design
- Improved risk identification
761 What are the key disadvantages of two stage tendering?
- Contractor has less incentive to price the 2nd stage competitively
- Additional cost of the contractors PCSA fee
- Potential for the negotiation to fail and the parties do not go into contract
762 What is negotiated tendering?
This is single stage tender when a single contractor submits a tender return for the project. Both Parties then negotiate the contract price.
763 What are the key advantages of negotiated tendering?
- Simplicity
- Speed. Negotiated tenders can have programme advantages if undertaken in good faith.
- Client has flexibility in choosing who they want to work with.
- Time and cost saving from not having to prep the tender, wait for returns and then analyse
- Call allow ECI
764 What are the key disadvantages of negotiated tendering?
- May not be competitive. Might actually be at a premium
- Potential for delay of the negotiations become protracted
- Heavy reliance on trust
- Can be seen as anticompetitive and exclusive
765 How could you justify value for money on a Negotiated tender?
Insist on an open book approach when agreeing subcontract packages and a minimum of 3 quotes to be provided for each element (this would need to be agreed up front)
Tender Returns and Analysis
766 What is a form of tender?
This is a formal document that asks the bidder to confirm that they accept the terms and conditions of the tender and any other requirements that are stipulated. Will also ask them to confirm their price and programme.
767 What information is typically included in a form of tender? (247)
- Tender sum
- How long the price remains valid
- Construction period
- Confirmation that it is a bona fide tender
- Tenderer details and signature
- Acceptance of the terms and conditions
769 Once tenders have been submitted, what should be examined for compliance with the invitation to tender and tender instructions?
- Arithmetical and pricing errors
- Pricing method, check for front loading
- On a D & B compare against the ER
- Signed tender form, including all relevant details
- Resolve any qualifications
- Enquire about any items that have not been priced
770 What happens if a tender is submitted late?
Public sector – Generally it should not be opened, returned to the person named in the ITT and disqualified. However, proportionality needs to be considered. If there is an issue with the entity procuring the works system (be it digital or physical) this needs to be taken into consideration.
Leadbitter & Co Ltd v Devon County Council – Case where tender was uploaded before the deadline the bidder noticed some documents had been missed from the upload. They tried to upload them but the system wouldn’t allow this. They emailed the missing documents over 30 mins after the deadline. However, the council rejected and disqualified the tender because it was implicit in its tender instructions that it was the “tenderer’s responsibility to ensure that all relevant documents were upload and that an incomplete set of documents would render any submission invalid.” It was also stated that “any submission submitted outside of the portal would not be considered”
BAM PPP V NTMA – BAM were submitting a tender they had informed NTMA 15 minutes before the deadline that 8 documents (out of 280) were not ready for submission. NTMA ended up considering the tender and clearly set out their reasons for doing so:
The tender was complete by 18:13 (assume a 17:00 deadline)
BAM already had 7 of the 8 documents ready before the deadline i.e. only one contained new information.
The tender documents were not modified after 17:00 (assumed deadline)
NTMA was satisfied that no unfair advantage had been obtained by the late upload
Private sector – It should be discussed with the Client and understood if they wish to accept. The safest option is not to consider the bid as there may be the potential for fraud, collusion, bid-rigging risk etc.
771 Would you open a late tender submission for a school project?
The bid should not be opened and returned to the sender.
772 What is the danger of accepting an exceptionally low tender?
- That the bidder has misunderstood the project
- That elements have been missed/ arithmetical or pricing errors
- That the bidder is trying to undercut the competition/buy the work
- That they are expecting a large amount of change on the project and are expecting to make their money there
- Or the bidder is in financial difficulty and needs the work which could lead to problems down the line
773 How do you deal with qualifications within the tender?
Clear instructions must be given as part of the tender for qualifications. It could potentially lead to the big being disqualified. These must be resolved with the bidder before the contract is signed.
774 How do you deal with errors identified in the tender submissions?
As part of the tender you should state how errors will be dealt with. JCT has two ways of dealing with this – Tender Practice Note 2012
Alternative 1: Tenderer should be given the details of the errors and afforded the opportunity to confirm (as it stands) or withdraw.
If they withdraw the next lowest tender will be considered.
Alternative 2: Tenderer should be given the opportunity of confirming their offer or amending genuine errors.
NEC – No specific guidance on this. RICS Tendering Strategies 1st edition refers back to the JCT guidance.
As long as it is clearly stated in the tender how errors are dealt with, and that is adhered to then you shouldn’t have a problem.