Process Groups & Knowledge Areas Flashcards

(61 cards)

1
Q

What are the 10 project management knowledge areas?

I Saw The Cat. Quick! He Can Run Pretty Swiftly

A
Project Integration Management
Project Scope Management
Project Time Management
Project Cost Management
Project Quality Management
Project Human Resources Management
Project Communications Management
Project Risk Management
Project Procurement Management
Project Stakeholder Management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 8 processes in the Executing Process Group?

A
Direct and manage project work.
Perform Quality Assurance
Acquire Project Team
Develop Project Team
Manage Project Team
Manage Communications
Conduct Procurement
Manage Stakeholder Engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between tools and inputs?

A

Tools are tangible items used in the performance of an activity to produce a result.

Inputs are those items required by a process in order for that process to proceed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

According to PMI, what is a process?

A

A systematic series of activities directed towards causing an end result such that one or more inputs will be acted upon to create one or more outputs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you best describe the aspirational requirement related to fairness?

A

Demonstrating complete transparency in your decision-making process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you best describe the aspirational requirement related to responsibility?

A

Do what you say you will do.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do mandatory standards describe?

A

Firm requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which 4 groups of people does the PMI Code of Ethics and Professional Conduct apply to?

A

All PMI Members
Nonmembers who hold a PMI certification
Nonmembers who apply for a PMI certification
Nonmembers who serve PMI in a volunteer capacity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 4 processes of Project Procurement Management?

A

Plan Procurement Management
Conduct Procurements
Control Procurements
Close Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which Project Communication Management process occurs in the Monitoring and Controlling Process Group?

A

Control Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you best describe the aspirational requirements related to honesty?

A

The duty to seek the truth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you best describe the aspirational requirements related to respect?

A

The duty to inform yourself about norms and customs of others and avoid engaging in behavior that others might consider disrespectful.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you best describe the mandatory requirements related to responsibility?

A

The duty to take ownership for the decisions you make, or fail to make.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 4 values of the PMU considers most important for the project management profession?

A

Responsibility
Respect
Fairness
Honesty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which Project Procurement Management process occurs in the Executing Process Group?

A

Conduct Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which Project Risk Management processes occur in the Planning Process Group?

A
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which Project Communication Management process occurs in the Planning Process Group?

A

Plan Communication Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which Project Human Resource Management process occurs in the Planning Process Group?

A

Plan Human Resource Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which Project Quality Management process occurs in the Planning Process Group?

A

Plan Quality Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the 4 processes of Project Cost Management?

A

Plan Cost Management
Estimate Costs
Determine Budget
Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which Project Scope Management processes occur in the Monitoring and Controlling Process Group?

A

Validate Scope

Control Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which Project Integration Management process occurs in the Closing Process Group?

A

Close Project or Phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Which Project Integration Management process occurs in the initiating Process Group?

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the 2 processes in the Closing Process Group?

A

Close Project or Phase

Close Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Which Process Group do these processes belong to: Develop Project Charter Identify Stakeholders
Initiating Process Group
26
What are tools and techniques?
Actions applied to the inputs to create outputs; examples of tools and techniques are measuring, planning, applying a skill, templates, software, etc.
27
How would you best describe the mandatory requirement related to honesty?
The duty to understand the truth and always act in a truthful manner.
28
How would you best describe the mandatory requirement related to respect?
The duty to show a high regard for the resources entrusted to you.
29
What are the consequences for project management professionals who do not meet the mandatory standards?
Disciplinary action
30
Which Procurement Management process occurs in the Planning Process Group?
Plan Procurement Management
31
What are the 6 processes of Project Risk Management?
``` Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Control Risks. ```
32
What are the 3 processes in Project Communications Management?
Plan Communication Management Manage Communications Control Communications
33
What are the 4 processes in Project Human Resource Management?
Plan Human Resource Management Acquire Project Team Develop Project Team Manage Project Team
34
What are the 3 processes in Project Quality Management?
Plan Quality Management Perform Quality Assurance Control Quality
35
Which Project Time Management process occurs in the Monitoring and Controlling Process Group?
Control Schedule
36
Which Project Scope Management processes occur in the Planning Process Group?
Plan Scope Management Collect Requirements Define Scope Create WBS
37
Which Project Integration Management processes occur in the Monitoring and Controlling Process Group?
Monitor and Control Project Work | Perform Integrated Change Control
38
What are the 6 processes of Project Integration Management?
``` Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase. ```
39
What are the 11 processes in the Monitoring and Controlling Process Group?
``` Monitor and Control Project Work Perform Integrated Change Control Validate Scope Control Scope Control Schedule Control Costs Control Quality Control Communications Control Risks Control Procurements Control Stakeholder Engagement ```
40
What are the 5 Process Groups in A Guide to the PMBOK- 5th Edition?
``` Initiating Planning Executing Monitoring and Controlling Closing ```
41
What are inputs?
Any items, whether internal or external to the project that is required by a process before that process proceeds. May be outputs from predecessor processes.
42
Which Project Integration Management process occurs in the Executing Process Group?
Direct and Manage Project Work
43
What are the 6 processes of Project Scope Management?
``` Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope ```
44
Which Project Time Management processes occur in the Planning Process Group?
``` Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule ```
45
Which Project Cost Management process occurs in the Monitoring and Controlling Process Group?
Control Costs
46
Which Project Quality Management process occurs in the Monitoring and Controlling Process Group?
Control Quality
47
What are outputs?
Products, results, or services generated by a process. May be inputs to a successor process.
48
What are the 24 processes in the Planning Process Group?
See Yellow Card
49
How does A Guide to the PMBOK describe these 3 major documents? Project Charter Project Scope Management Project Management Plan
Project Charter: Give formal authorization to the project. Project Scope Statement: Describes the work that needs to be accomplished and the specific deliverables that the project is to produce. Project Management Plan: Describes how the project work will be performed. It is a collection of smaller component plans and documents.
50
Which Project Integration Management process occurs in the Planning Process Group?
Develop Project Management Plan
51
How would you describe Project Scope Management?
Includes the processes required to ensure that the project includes all work required, and only the work required, to complete the project successfully.
52
What are the 7 processes of Project Time Management?
``` Plan Schedule Management Define Activities Sequence Activites Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule ```
53
Which Project Cost Management processes occur in the Planning Process Group?
Plan Cost Management Estimate Cost Determine Budget
54
Which Project Quality Management process occurs in the Executing Process Group?
Perform Quality Assurance.
55
Which Project Human Resources Management processes occur in Executing Process Group?
Acquire Project Team Develop Project Team (developing a project team occurs in every phase. If given a choice on the test, the better answer is that this process occurs throughout the life of the project. Manage Project Team
56
Which Project Communication Management process occurs in the Executing Process Group?
Manage Communications
57
Which Project Risk Management process occurs in the Monitoring and Controlling Process Group?
Control Risks
58
Which Project Procurement Management process occurs in the Monitoring and Controlling Process Group?
Control Procurement
59
How would you best describe the mandatory requirement related to fairness?
The duty to make fair decisions, act impartially, and objectively.
60
What do aspirational standards describe?
Conduct you aspire to achieve.
61
What are the 2 types of standards outlined in each section of the PMI Code of Ethics and Professional Conduct?
Mandatory | Aspirational