Process - Managing a stage boundary Flashcards

(4 cards)

1
Q

Purpose

A

To enable the project manager to
provide the project
board with sufficient information to be able to:
* review the success of the current management stage;
* approve the next stage plan;
* review the updated project plan ;
* confirm continued business justification and
acceptability of the risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Objectives of managing
a stage boundary

A

1> Assure
project
board
2> Prepare
stage or
exception
plan
3> Provide
information
to assess
viability
4> Review and
update the
PID
5> Record
information
to help later
stages or
projects
6> Request
authorization
to start the
next stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Context

A
  • Business
    justification should
    be reconfirmed at
    the end of each
    stage
  • The project can
    be redirected or
    stopped if
    necessary
  • Provides a means
    for implementing
    an exception
    procedure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Overview

A

Picture saved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly