Develop Project Charter
Project Charter, Assumption Log
Develop Project Management Plan
Project Management Plan
Direct & Manage Project Work
Deliverables, Work Performance Data, Issue Log, Change Requests
Manage Project Knowledge
Lessons Learned Register
Monitor & Control Project Work
Work Performance Reports, Change Requests
Perform Integrated Change Control
Approved Change Requests, Change Log
Close Project or Phase
Final Product/Service, Final Report, Lessons Learned Register
Plan Scope Management
Scope Management Plan
Collect Requirements
Requirements Documentation, Requirements Traceability Matrix
Define Scope
Project Scope Statement
Create WBS
Scope Baseline
Validate Scope
Accepted Deliverables
Control Scope
Work Performance Information, Change Requests
Plan Schedule Management
Schedule Management Plan
Define Activities
Activity List, Activity Attributes
Sequence Activities
Project Schedule Network Diagram
Estimate Activity Durations
Duration Estimates, Basis of Estimates
Develop Schedule
Project Schedule, Schedule Baseline
Control Schedule
Work Performance Information, Schedule Forecasts, Change Requests
Plan Cost Management
Cost Management Plan
Estimate Costs
Cost Estimates, Basis of Estimates
Determine Budget
Cost Baseline, Project Funding Requirements
Control Costs
Work Performance Information, Cost Forecasts, Change Requests
Plan Quality Management
Quality Management Plan, Quality Metrics