21) True or False: Team members entered into the RFIs Responsible Party field will receive notification emails regarding the RFI.
b. False
38) True or False: Subcontracts with the status of Out for Bid or Out for Signature will be reflected on the budget.
False
32) True or False: Observations can only be created using an observation template.
b. False
2) Notifications are automatically sent to bidders when bid documents are updated.
a. True
b. False
False
8) If you see this icon next to a drawing, what does it mean?
a. The drawing has sketches associated with it
b. The drawing has related items associated with it
c. Markups have been added to the drawing
d. The drawing can be viewed in fullscreen mode
c. Markups have been added to the drawing
39) True or False: When creating a purchase order and filling out the contract company, you must select a vendor/company who exists in the project directory.
True
34) True or False: A Budget Modification allows you to move budgeted costs to different line items.
a. True
1) Bidders log in to ________ to view a bid package and submit a bid.
a. the project’s Bidding tool
b. the Company Level Planroom tool
c. their private email account
b. the Company Level Planroom tool
15) True or False: When you delete a specification from the Specifications list page, you will delete the specification and all of its revisions.
b. False
26) True or False: Punch List templates are only available for use on Procore’s mobile application.
a. True
23) True or False: You can only create follow-up meetings from a meeting in “Agenda” mode.
b. False
10) Who can view drawing markups on the “Personal” layer?
a. Only you
b. You and ‘Admin’ level users on the Drawings tool
c. You and the project’s architect
d. All users that have access to the drawing
a. Only you
9) True or False: When you click a project’s Drawings tool, you should expect to see the project’s “current set” of drawings. (i.e. The most recently uploaded revisions of each drawing.)
a. True
40) A purchase order with which of the following status will appear in the Committed Costs column on the budget?
a. Draft
b. Closed
c. Processing
d. Partially Received
e. Approved
e. Approved
33) True or False: You can upload your budget into Procore by using a designated import template.
a. True
25) Who can view a ‘Private’ punch list item?
a. The creator of the punch list item
b. The assignee of the punch list item
c. Users with ‘Admin’ permissions to the Punch List tool
d. Users that are on the punch list item’s Distribution list
e. All of the above
e. All of the above
6) How do you add a document to a project?
a. Send a file to the project’s unique email address
b. Upload a file using Procore’s Windows Desktop application, Procore Drive
c. Drag and drop a file into a folder’s designated “Upload Queue” section
d. Click the “Browse” button to select a file from your local computer
e. All of the above
e. All of the above
30) True or False: You can create an observation from an inspection item.
a. True
b. False
b. False
17) Who is the Submittal Manager? (select best answer)
a. The person who configured the Submittals tool on the project
b. A user who is in charge of contacting the external contractor when the submittal has been approved
c. The creator of the submittal
d. A user who is the gatekeeper of the submittal and is in charge of facilitating a submittals workflow making sure that it is collected and reviewed by all appropriate people.
d. A user who is the gatekeeper of the submittal and is in charge of facilitating a submittals workflow making sure that it is collected and reviewed by all appropriate people.
11) Which of the following can you do when viewing a drawing on a mobile device?
a. Search for text
b. Compare differences between two drawing revisions
c. View attachments that have been added to the drawing
d. B and C
e. All of the above
e. All of the above
18) What happens when the ball in court on a submittal switches to you?
a. You will receive an email notifying you that the submittal requires your attention
b. You will see a response box above the general information in the submittal
c. The submittal will appear in the “My Open Items” section on your home page
d. All of the above
d. All of the above
36) How do you create a schedule of values in Procore’s Prime Contract tool?
a. Import the schedule of values (SOV) from a CSV file
b. Copy the schedule of values from the Budget
c. Manually add each line item
d. All of the above
e. Both A and B
d. All of the above
42) True or False: A change event listed as “Out of Scope” means that the change falls within the scope of the original contract.
False
3) True or False: Only entire folders can be attached to the bid package.
False