procurement methods Flashcards

(27 cards)

1
Q

In a Traditional Contract, who handles design and construction?

A

The client handles design; the contractor handles construction only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the client’s involvement in a Traditional Contract?

A

Moderate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who bears the greater risk in a Traditional Contract—client or contractor?

A

Contractor (construction risks).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What defines a Single-Stage Design & Build method?

A

One entity is responsible for both design and construction from a single contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the client’s level of involvement in Single-Stage D&B?

A

Low.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What level of cost certainty is associated with Single-Stage D&B?

A

Moderate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What makes Two-Stage Design & Build unique?

A

Early contractor involvement during design, followed by a construction contract later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is the client most involved in Two-Stage D&B?

A

Early stages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What risk does the contractor face in Two-Stage D&B?

A

Post-contract risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the contractor’s role in Construction Management?

A

Providing management services, not direct construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a major client risk in Construction Management?

A

Cost overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How flexible is the Construction Management method?

A

High flexibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How involved is the client in a Custom Build method?

A

Very high involvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a key risk in Custom Build?

A

Customization risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What level of cost certainty does Custom Build offer?

A

Low

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the contractor’s role in Emerging Cost Contracts?

A

Managing and controlling costs efficiently.

17
Q

Who bears a high cost overrun risk in Emerging Cost Contracts?

18
Q

What is the cost certainty like in Emerging Cost Contracts?

19
Q

What characterizes Fast-Track Construction?

A

Design and construction phases overlap to save time.

20
Q

What is a key risk for the contractor in Fast-Track Construction?

A

Coordination risks.

21
Q

What level of client involvement is required in Fast-Track projects?

22
Q

What is a Guaranteed Maximum Price (GMP) contract?

A

A contract where the contractor agrees not to exceed a set maximum price

23
Q

What benefit does a GMP Contract provide the client?

A

Lower risk of cost overruns.

24
Q

What risk does the contractor face in a GMP Contract?

A

Risk of exceeding the GMP and absorbing additional costs.

25
In a Lump Sum Contract, what is the payment structure?
Fixed total price for the entire construction project.
26
Who bears more risk in a Lump Sum Contract?
The contractor (if costs exceed estimate).
27
What level of cost certainty does the client have in a Lump Sum
high