Project Finance Flashcards
(129 cards)
What are the typical Cost Manager responsibilities on a construction project?
- Manage risk allowance expenditure
- Initiate action to avoid overspend
- Prepare pricing documents for tendering
- Evaluate and analyse tender bids
- Prepare interim valuations
- Value variations and compensation events
- Assess the contractor’s financial claims
- Negotiate and agree final accounts
- Produce cost reports, estimates and forecasts
- Prepare and maintain the cash flow forecast
If you are producing estimates and cost plans, which measurement rules represent industry best practice?
NRM - New Rules of Measurement
Can you name the 3 documents in the NRM suite?
- NRM1 - Order of cost estimating and cost planning for capital building works
- NRM2 - Detailed measurement for building works
- NRM3 - Order of cost estimating and cost planning for building maintenance works
Why is it important to measure the works according to industry standards and best practice?
- To provide consistency and greater accuracy of pricing
- To ensure that all parties price on the same basis and tehrefore reduce the risk of dispute
What are the key headings for contractor preliminaries identified in the NRM2?
Employer’s Requirements:
- Site accommodation
- Site records
- Completion and post completion requirements
Contractor Cost Items:
- Management and staff
- Site establishment
- Temporary services
- Safety and environmental protection
- Mechanical plant
-Temporary works
- Site records
- Cleaning
- Insurances, bonds, guarantees and warranties
How is risk dealt with under NRM?
NRM recommends that risk allowances are not a standard percentage, but a properly considered assessment of the risk.
Can you tell me the 4 risk categories identified in NRM?
- Employer Change Risk
- Employer Other Risk
- Design Development Risk
- Construction Risk
How are professional fees presented in the order of cost estimate?
Fees can be presented as an item (if actual fees are known) or a percentage applied to the ‘works cost estimate’
Which RIBA Stage is the order of cost estimate typically produced?
RIBA Stage 1 - Preparation and Brief
What are the RIBA Stages of work?
Stage 0 - Strategic Definition
Stage 1 - Preparation and Brief
Stage 2 - Concept Design
Stage 3 - Spatial Coordination
Stage 4 - Technical Design
Stage 5 - Construction and Manufacturing
Stage 6 - Handover
Stage 7 - In Use
What is the difference between an order of cost estimate and cost plan?
- An estimate provides a possible cost based on the employer’s requirements and is the initial phase of the cost planning process. The estimate is usually completed using m2 areas.
- A cost plan is a more detailed elemental breakdown and shows how the costs are distributed across the project.
What is a cost plan?
- The cost plan is typically prepared by the cost consultant and provides an estimate of what the actual project cost is likely to be.
- The cost plan identifies the client’s agreed cost limit and how the money is allocated to the different parts of the project.
Other than predicting the final project cost, what other benefits does the cost plan provide to the project and project team?
- Designers are aware of the cost implications of their proposals which enables them to arrive at practical and balanced designs
- Provides information upon which the employer can make informed commercial decisions
Do you need a programme to complete the cost plan?
Prelims are typically presented as a weekly rate in developed cost plans, therefore a programme or at least some high level dates will be required.
Key info required is:
- Design and tendering periods
- Start on site date
- Construction period
- Completion date
How do you structure a cost plan?
NRM recommends a template to be followed.
What sources of cost information and data are available when preparing a new estimate or cost plan?
- Information produced by the BCIS (building cost information service)
- Published pricing books such as Spons and BCIS
- Pricing documents and info from previous projects
- Cost analysis and cost models produced in house
- Speaking to contractors, sub contractors and suppliers for cost information
- Existing client data - benchmarking from previous projects
How do you take account of the project location and why?
A location factor is usually applied to recognise differences in construction prices. For example, a project in London is typically more expensive than a similar project in Nottingham.
What is a cost plan risk allowance?
A sum included to cover unknown costs or unmitigated risks during the project.
What benefit does the client get out of accurate cost planning?
- The cost plan confirms to the client the scheme is affordable or not
- Cost planning places the client in an informed position to make commercial decisions
- The cost plan can act as a value management tool to ensure the client gets a building which meets their needs but also represents best value.
How would you deal with a cost plan that is over budget?
- Communicate the matter to the client and the project team in a clear and concise manner.
- Identify areas where potential savings can be made, possibly in terms of material specification or re-design.
How can the cost manager help control the design to keep the project within budget?
- Explain to the design team where the cost plan sits against the budget and discuss the limitations
- Identify and communicate areas of design which may not be economical
- Regular project risk reviews
- Explain how changes in design will impact the cost
- Contribute to VE sessions
What are some of the key reasons we have cost overrun on a project?
- Ambiguous client brief or changes in the later stages of the project
- Unrealistic cost estimates
- Project risk not properly managed
- Inadequate management control or processes
- Uncoordinated design
- Unknown external factors, e.g. global pandemic
- Unsuitable tendering/procurement strategy
- Statutory influences
- Inflation or changing market conditions
What is BWIC?
- BWIC stands for builder’s work in connection Necessary to allow other works to proceed.
Why is VAT usually excluded from the cost plan?
Employers may incur different levels of VAT or be exempt, therefore, VAT is usually excluded to ensure the incorrect tax rate is not applied.