Project Termination Flashcards

(6 cards)

1
Q

What are the four positive aspects of project termination?

A
  1. Environmental Protection: Preventing ecological harm
  2. Community Advocate: Amplifying local voices
  3. Economic Reallocation: Redirecting resources to feasible or more realistic projects
  4. Learning Opportunities: Improving future project planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the four negative aspects of project termination?

A
  1. Financial Losses: Sunk costs and unrealised benefits
  2. Missed Opportunities: Economic and Social Potential
  3. Reputation Damage: For governments and organisations
  4. Stakeholder Dissatisfaction: Legal disputes and broken trust
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the lessons learned from terminated projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is modern slavery?

A

Keeping individuals in servitude and forcing them to work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you answer this question regarding project termination and modern slavery?

A
  1. List the positives and negatives of project termination to show general understanding
  2. The project should continue
  3. Why?
    * Following 3 years of work, the cost of terminating the project is very high for investors.
    * Cancelling the project also admits to the public that my businesses was responsible for the modern slavery on site, which it was not.
    * At the same time, my company has made a mistake in not identifying that the specialised sub-contractor was using modern slaves in their workforce and not maintaining a safe site. This is unacceptable, and requires an apology to the press, the public, and environmental groups.
    * Victims familes should be reached out to directly with apologies for company failures in not identifying the wrongdoing of the subcontractor, issuing generous subsidy packages.
    * The communications to the press should ensure that the subcontractor takes full blame for hiring modern slaves, however we accept responsibility and should be deeply apologetic for not reconising these issues.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why do people hesitate to terminate projects and why is this angle wrong?

A
  • We always think about sunk costs
  • However, it is always lower cost to terminate a project now than in the future