PX Random Flashcards
(144 cards)
The consultant’s involvement is planned out during _______, and billing is first reviewed and approved in _______ design.
Which interior design service is specific to the contract administration phase of a project?
Programming
Schematic
Review Shop drawings - the vendor’s
The 3-part technical sections in the CSI MasterFormat specs refer to?
General, products, and execution
What are the three phases of the design process?
the analysis phase (Pre-design/Programming)
the synthesis phase (Schematic Design)
the implementation phase
-The three areas of the implementation phase of a project include: the construction drawings, written specifications
What is one of the most important reports used by an interior design firm to monitor project progress, revenue and expenses and can be used to take corrective action for finances?
project progress report.
What are the three areas of the implementation phase of a project?
What are these three components referred to as?
the construction drawings, written specifications
contract documents
An all-air system
can be subdivided into as many individually controlled areas as needed.
When an addendum is issued, it is sent to all bidders no later than ________ days before receipt of bids to give all bidders ample opportunity to study the document and modify their proposals accordingly.
4 days
Project Notebook vs Project Manual?
Do not confuse the project NOTEBOOK (Project Management) with the PROJECT MANUAL (Construction Specifications).
-PROJECT NOTEBOOK - For design team/PM (PM will typ. have). Punch list (substantial completion), submittals and shop drawings (they receive these from GCs and consultants), budget, fees, General reference (names/contacts), programming, job communication (forms (submittals/addenda, etc.), meetings notes, etc.). It does have contracts, for reference, to make sure they are upheld.
For filing purposes!
-PROJECT MANUAL - For contractors and vendors, anything that they would need to know! Bid requirements, contracts, bonds (they have to pay/adhere to - GC gives to owner), Insurance documents, General Conditions, specs (this is basically a spec book), NO DRAWINGS.
Typ. for larger projects.
The interior designer does not keep a copy of the bonds as they are not the interior designer’s responsibility.
What is a Bulletin?
A bulletin is used to formally issue changes to the construction documents, including drawings and specifications, after the construction contract has been issued. Revisions issued via a bulletin may have a cost impact and become change orders.
This is similar to an addendum, which is a change before the contract is awarded.
A bulletin may include what is referred to as an ASI — Architect’s Supplemental Instruction.
A bulletin directs the contractor to provide pricing for the proposed changes. The contractor proceeds if the client accepts the pricing. Changes to drawings issued in a bulletin are clouded and noted with a number (within a Delta symbol) and date.
A typical bulletin includes:
Letter of transmittal listing all items sent with the bulletin
REVISED drawings sheets, not the entire drawing set
REVISED specifications sheets, not the entire spec book
Sheet-by-sheet narrative of the changes
The requirements for how bidders should propose a substitution is found in the
For bidding, the procedure a contractor must follow to propose a substitution is in the instructions to bidders.
After the contract is awarded, the specification requirements can be found in the General Requirements.
There is no such document as “bidding procedures”.
An allowance is for?
What is a contingency?
An allotment for bids when you cannot determine the actual cost of a product.
Part of a project’s budget put aside to cover any unforeseen costs, risks, events, or changes in scope that may affect the project’s cost over the course of it’s life.
This money is on reserve and is not allocated to any specific area of work.
Substantial Completion vs Certificate of Occupancy?
Substantial Completion - ISSUED BY THE DESIGNER
-The date certified by the architect or interior designer when the contracted work is sufficiently complete, in accordance with the contract documents, so that the owner may occupy it for the intended use.
-Upon issuing a certificate of substantial completion, the final application for payment is processed. The designer will review the last payment application from the GC and issue the final certificate for payment. Warranties and utility and maintenance responsibilities shift at this point.
Certificate of Occupancy - ISSUED BY AHJ/ local building office
- Issued after substantial completion. The contractor gives this to the owner with the warranties, drawings, extra material, etc.
Who has the authority to stop construction?
Who has the authority to reject work that does not conform to contract documents?
Only the owner.
The interior designer.
Claims and change orders.
-A construction claim is simply a demand for something due. The most common residential construction claims are filed for delay, payment disputes, unforeseen site conditions and damages.
-During a construction project, a “Claim” typically refers to a formal request by one party (usually the contractor or the owner) for compensation or other relief due to change in circumstances that arose during the work or after the parties entered into a contract.
-A change or modification made after the contract is awarded should be documented with a change order. Once accepted and signed by the appropriate parties, change orders become a part of the contract documents. A change order (CO) requires the signatures of the owner, the architect/designer, and the contractor.
-Interior designers should not allow any changes without a written change order issued to all necessary parties.
Packing list vs Bill of Lading?
Packing List -Item descriptions and quantities in a shipment that is attached to one of the items shipped- given to the truck driver at the factory.
Bill of Lading -Lists the contents of a shipment from a manufacturer or vendor.
-The two should be compared once the product is delivered to make sure that they match.
Who is responsible for providing any lab tests, inspections, and reports required by the contract documents?
When additional testing is required?
The owner.
The contractor.
Parameter method vs Detailed quality takeoff?
Using the totaled unit pricing per material type (when you have a general idea of product and what things cost)
Utilized for a more exact budget (when actual products have been selected)
Maximum allowable slope for an accessible ramp?
For an accessible ramp, what is the maximum rise allowed between landings?
1:12
30”
What two situations require the construction of a fire barrier?
-Separation of different occupancies
-An enclosure where there are vertical exits
The usage classification assigned to a building or an interior space determines?
The various types of fire hazards and the life-safety characteristics of various uses.
Two main factors in determining if a space requires two exits rather than just one?
Occupancy and it’s occupant load.
What is another term for a Sales Agreement (furniture) between ID and client?
A proposal (contract) - remember this is between ID and client!
Not the same as a PO!
Which occupancy group is the most restrictive?
Assembly, because it contains large groups of people
IAQ is dependent upon?
Limiting pollution sources and on proper ventilation.