Questions Q1 Flashcards
Which of the following is controlling changes to the budget.
a. None of them is the correct answer
b. Control Costs
c. Determine Budget
d. Estimate Costs
b. Control Costs
You are the project manager of the ABC Project. This project will create a walking bridge across the Parramatta River. You’ve been asked to start the process of creating the project scope statement and you need to gather the elements for this process. Which one of the following is not needed to define the project scope?
a. Requirements documentation
b. Organizational process assets
c. A risk management plan
d. A project charter
c. A risk management plan
Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider?
a. Costs that have been authorized and incurred
b. Cost estimates from similar projects
c. Project schedule
d. WBS
a. Costs that have been authorized and incurred
You’ll use the scope management plan to define the project scope statement. You’ll also use this plan to build the scope baseline. Which two items are parts of the scope baseline for the project?
a. The project scope management plan and project charter
b. The project scope management plan and the WBS
c. The WBS and WBS dictionary
d. Time and cost baselines
c. The WBS and WBS dictionary
While setting up a project schedule plan- you need to schedule shifts such that no shift should end before the next shift is at work - what is the dependency between the shifts?
a. Start to Start
b. Finish to Start
c. Finish to Finish
d. Start to Finish
d. Start to Finish
A project is defined as
a. An endeavour, which is NOT planned
b. An endeavour, which is planned, executed, and controlled; performed by people and constrained by limited resources
c. A process of considerable scope that implements a plan
d. A temporary endeavour undertaken to create a unique product or service
d. A temporary endeavour undertaken to create a unique product or service
You and the project team have created the work breakdown structure based on the project scope and requirements. Your next step is to create the project’s activity list. Which one of the following will NOT be included in the activity list created with the project management team?
a. Physical terms, such as linear feet of pipe to be installed
b. Quality control activities
c. Activities that are not part of the project scope
d. Activities to create the work packages
c. Activities that are not part of the project scope
A graphic display of resource usage hours is called a/an_________________.
a. WBS
b. Organizational chart
c. Histogram
d. Responsibility matrix
c. Histogram
All of the following are outputs of Estimate Costs process EXCEPT
a. Documented constraints
b. Cost baseline
c. Activity cost estimates
d. Basis of estimates
b. Cost baseline
During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a ————————- for the second half of the project?
a. Staffing management plan
b. Responsibility assignment matrix
c. Work breakdown structure
d. Resource histogram
a. Staffing management plan
Of the following, which is the logical order of the project management processes?
a. Initiating, planning, monitoring and controlling, executing, closing
b. Planning, initiating, monitoring and controlling, executing, closing
c. Planning, initiating, executing, closing, monitoring and closing
d. Initiating, planning, executing, monitoring and controlling, closing
d. Initiating, planning, executing, monitoring and controlling, closing
The project scope statement addresses and documents all the following items EXCEPT:
a. The relationship between the deliverables and the business need
b. Project exclusions
c. Product scope description
d. Project management methodology (PMM)
d. Project management methodology (PMM)
Which time estimating tools estimate the basis for activity duration can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
a. Reserves analysis
b. Funding limit reconciliation
c. None of the above
d. Parametric estimating
d. Parametric estimating
To complete the project charter, a project manager will need to use information provided by the
a. Project initiator or sponsor
b. Organizational process assets
c. Project scope department
d. Enterprise environmental factors
a. Project initiator or sponsor
To construct a residential complex - you need to estimate the amount of high grade cement in tonnes that would be required. In which Process Group are you likely to do this activity?
a. Estimate Cost
b. Estimate Activity Resources
c. Determine Budget
d. Estimate Activity Duration
b. Estimate Activity Resources
Which of the following project document is best suited for tracking costs of resources?
a. Work breakdown structure
b. Resource breakdown structure
c. Organizational breakdown structure
d. Risk breakdown structure
a. Work breakdown structure
On your project, you need to assign costs to the time period in which are incurred. To do this, you should
a. Use the project schedule as an input to determine budget
b. Identify the project components so that costs can be allocated
c. Prepare a cost performance plan
d. Prepare a detailed an accurate cost estimate
a. Use the project schedule as an input to determine budget
A project is in the middle of the executing process when a stakeholder suggests a major new change. This change will cause the third major overhaul of the project. At the same time, the project manager discovers that a major work package was not completed because a team member’s boss moved him to another project that had a higher priority. Which of the following is the BEST person for the project manager to address these issues with?
a. The customer
b. The team
c. The sponsor
d. Senior management
c. The sponsor
Project Human Resource Management processes include ____________.
a. HR planning, Acquire Project Team, Develop Project Team and Manage Project Team
b. Staff recruitment, project staff planning and team building
c. Staff acquisition, staff training, and staff deployment
d. Rewarding, salary reviews and penalties
a. HR planning, Acquire Project Team, Develop Project Team and Manage Project Team
When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?
a. Bottom-up estimating
b. Parametric estimating
c. Analogous estimating
d. Top-down estimating
b. Parametric estimating
Complete this sentence: Project scope management is primarily concerned with defining and controlling…….
a. Changes to the configuration management system
b. What is and is not included in the product
c. What is and is not included in the project
d. Changes to the project scope
c. What is and is not included in the project Correct
You prepared cost baseline has changed because of a major scope change on your project. Your next step should be to
a. Estimate the magnitude of the scope change
b. Document lessons learned
c. Execute the approved scope change
d. Issue a change request
d. Issue a change request
The cost variance is the same as the schedule variance and both numbers are greater than zero, then
Select one:
a. the cost variance is due to the schedule variance
b. The schedule variance can be easily corrected
c. The variance is favourable to the project
d. Labour rates have escalated since the project began
c. The variance is favourable to the project
Mike, a project manager in your company, is falling behind on the project schedule. He has elected to crash the project. What is crashing?
Select one:
a. Removing all unneeded project deliverables
b. Adding additional project resources to the project work
c. Adding lag time between all project activities Incorrect
d. Adding lead time between all project activities
b. Adding additional project resources to the project work