Questions Q2 Flashcards
Who has the responsibility for informing the final deliverable to all stakeholders?
a. Project Manager
b. Management
c. Team Lead
d. Sponsor
a. Project Manager
A contract obligates the seller to provide the services to the buyer, and it requires the buyer to pay the seller upon receipt of the services. A contract remains valid unless
a. The contract contains clauses that will violate existing laws and regulations
b. The buyer cannot pay the seller because of unforeseen financial difficulties
c. The seller does not have the financial resources to deliver the service
d. One party’s legal department cancels the contract with sufficient notice
a. The contract contains clauses that will violate existing laws and regulations
After preparing the risk management plan, the project manager identified the project risks and documented the in the risk register. What has the project manager done wrong?
a. Risks should be identified with stakeholders
b. Risks should be documented in the risk management plan
c. The risk management plan can only be defined once the risks have been identified
d. Risks should be identified by the team
a. Risks should be identified with stakeholders
You are coaching a new team member in your project. One of her functions is to recommend corrective actions to increase the effectiveness and efficiency of the organization.This falls under the Perform Quality Assurance process. This list of actions that results from carrying out this process is documented as
a. Recommended preventive actions
b. Organizational process assets updates
c. Change requests
d. Project management plan updates
c. Change requests
Project managers for international projects should recognise key issues in cross-cultural settings and place special emphasis on….
a. Establishing and following production schedules for information distribution to avoid responding requests for information between scheduled communications
b. Establishing a performance reporting system
c. Using translation services for formal, written project reports
d. Using good communication planning
d. Using good communication planning
You are the project manager for the Construction Project. John, a project team member, is confused about what QA is. Which of the following best describes QA?
a. QA is quality acceptance according to scope verification
b. QA is quality assurance for the project stakeholders
c. QA is quality assurance for the overall project performance
d. QA is quality assurance for the project deliverable
c. QA is quality assurance for the overall project performance
Fearing airlines strikes, your company has decided to cancel all onsite meetings scheduled for the month of April. Web meetings have been scheduled instead. What type of risk response strategy has been used?
a. Accept
b. Mitigate
c. Avoid
d. Transfer
c. Avoid
A simple performance report provides information on
a. Scope creep
b. Percent complete
c. Customer satisfaction
d. Unacceptable variances
b. Percent complete
You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on?
Select one:
a. Control Stakeholder Engagement
b. Plan Stakeholder Management
c. Manage Stakeholder Engagement
d. Identify Stakeholders
b. Plan Stakeholder Management
The Project Procurement Management includes:
a. All of the above
b. Solicitation
c. Procurement planning Incorrect
d. Solicitation planning
a. All of the above
Which of the following BEST describe the project manager’s role during the procurement process?
a. The project manager should supply an understanding of the risks of the project
b. The project manager should tell the contract manager how the contracting process should be handled
c. The project manager should be the negotiator
d. The project manager has only minor involvement
a. The project manager should supply an understanding of the risks of the project
A team member has been given the task of identifying which quality standards are relevant to this project and determining how to satisfy these standards. In which of the following activities is she engaged?
a. Perform Quality Assurance
b. Perform Quality Control
c. Quality Improvement
d. Plan Quality
a. Perform Quality Assurance
You are working on a project with 15 stakeholders. The number of communication channels on this project is
a. 15
b. 14
c. 210
d. 105
d. 105
The key benefits of ____________ process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and environment changes.
a. Identify Stakeholders
b. Control Stakeholder Engagement
c. Plan Stakeholder Management
d. Manage Stakeholder Engagement
b. Control Stakeholder Engagement
The plan risk responses process includes:
a. Prioritising risks
b. Developing contingency plans and identifying the response’s triggers
c. Determining risk causes
d. Preparing a risk breakdown structure
b. Developing contingency plans and identifying the response’s triggers
One purpose of the communication management plan is to provide information about the?
a. methods that will be used for releasing team members from the project when they are no longer needed
b. methods that will be used to convey information
c. Experience and skill levels of each team
d. project organisation and stakeholder responsibility relationships
b. methods that will be used to convey information
You are building a dam across a river. The dam would cause a number of villages to be flooded. The villagers do not want the dam to be constructed. Should you consider these villagers as Stakeholders - choose the BEST answer
a. No - stakeholder is anyone who is involved in the project
b. Yes - anyone who is positively or negatively impacted by the project is a stakeholder
c. Yes - stakeholder is anyone who can be positively or negatively impacted or can impact the project
d. No - stakeholder is anyone who can influence the project
c. Yes - stakeholder is anyone who can be positively or negatively impacted or can impact the project
Procurement audits are structured reviews that recognize good practices and identify questionable items during the preparation and administration of procurement contracts. Which Project Procurement Management process uses procurement audits as a tool or a technique?
a. Conduct Procurements process
b. Plan Procurements process
c. Administer Procurements process
d. Close Procurements process
d. Close Procurements process
You are the project manager for the KOY Project, which requires quality that maps to federal guidelines. To ensure that you can meet these standards, you have elected to put the project team through training specific to the federal guidelines your project must adhere to. The costs of these classes can be assigned to which of the following?
a. Cost of non-conformance
b. The cost of doing business
c. Cost of adherence
d. Cost of quality
d. Cost of quality
A project risk is a(n) _____________________occurrence that can affect the project for good or bad
Select one:
a. Potential
b. Uncertain
c. Known unknown
d. Known
b. Uncertain
As part of your company’s ISO-compliant project management processes, a project quality auditor visits all large projects at least once a month. The project auditor visited your project for five consecutive months and found it to be in compliance with the company’s project management processes, but the project auditor did not show up last month. What would be an appropriate course of action?
a. Report the project quality auditor to the quality management office immediately
b. Do not worry about it because the project has been compliant in the past
c. Wait until the next month because the audit is not adding any value to the project
d. Contact the project quality auditor and ask him/her to perform the monthly project audit as planned
d. Contact the project quality auditor and ask him/her to perform the monthly project audit as planned
Project managers can present project information in many different ways.Which one of the following is not a method a project manager can use to present project performance?
a. S-curves
b. Histograms
c. Bar charts
d. RACI matrix
d. RACI matrix
You are negotiating with a contractor for additional staff augmentation - a number of software developers and a few testers .As a buyer you don’t quite have the exact statement of work ready. What kind of contract is MOST appropriate for this kind of work?
a. Cost plus fixed fee - CPFF
b. Fixed Price Incentive Fee Contracts - FPIF
c. Time and Materials - T & M
d. Firm Fixed Price Contract – FFP
c. Time and Materials - T & M
……is an assessment performed by an unbiased individual or entity to determine if project activities conform to the organization and project policies and procedures
a. Process analysis
b. Change control system
c. Quality audit
d. Configuration management system
c. Quality audit