The Perform Integrated Change Control process occurs in which Process Group?
Monitoring and Controlling
Which item is an example of personnel assessment?
Focus group
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Project documents
The number of potential communication channels for a project with 5 stakeholders is
10
A project charter is an output of which Process Group?
Initiating
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Create WBS
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Product analysis
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Work performance information.
Which process in Project Time Management includes reserve analysis as a tool or technique?
Estimate Activity Durations
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Supportive
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Project charter
An input to the Manage Project Team process is:
Work performance reports.
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Cost management plan.
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
Perform Integrated Change Control
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
Estimate Activity Resources.
Which of the following is one of the Tools and Techniques of Control Quality Process?
a) Cost-benefit analysis
b) Meetings
c) Process Analysis
d) Inspection
d) Inspection
Which technique is used for determining the reason for variances between the baseline and actual performance?
a) Variance analysis
b) An organizational process asset
c) Earned value
d) Pareto Chart
a) Variance analysis
What is the schedule variance of a project if the earned value is 899 and the planned value is 1099?
– 200.000
Schedule Variance (SV) = Earned Value – Planned Value.
SV = 899-1099 = -200
You have just started a project for a retailer. The Project team members report that they are 20% percent complete with the project. You spent $5,000 of the $75,000 budget allocated for the project.
$15,000
Budget allocated multiplied by the % of the project completed.
20% X $75,000 = $15,000.
Based on the information provided in the table below, determine which task is on schedule and within the budget? Task (PV) (AV) (EV) A 100 150 100 B 200 200 200 C 300 250 280
Task B
SPI = EV / PV and CPI = EV / AC
Which of the following describes a work breakdown structure?
a) It is a statistical technique to measure quality
b) Is an environmental factor
c) It is a hierarchical decomposition of the total scope into manageable components
d) the resource requirement
c) It is a hierarchical decomposition of the total scope into manageable components
Which of the following is NOT one of the tools and techniques that are used in the Sequence Activities Process?
a) Leads and Lags
b) Dependency determination
c) Precedence Diagramming Method (PDM)
d) Critical Chain method
c) Precedence Diagramming Method (PDM)
Which of the following process does not fall under the Planning process group?
a) Control Costs
b) Plan resource management
c) Plan procurement management
d) Develop Schedule
a) Control Costs
You have been appointed as the Project manager of an upcoming internal project. Who will provide you with the Statement of work (SOW)?
Project Sponsor