RICS Contract Admin & Contract Practice Flashcards
How is acceleration dealt with under NEC?
Acceleration is referred to in Core Clause 36. Under clause 36.1 the Project Manager may instruct the Contractor to submit an acceleration quotation. Project Manager cannot assess an acceleration quotation like they can with a CE. No obligation on Contractor to accelerate.
What is acceleration?
Either describes the completion of the works in a shorter time than that anticipated at tender or the act of recovery by the contractor if they are in delay
What is retention?
It is a percentage of each interim certificate deducted and retained by the employer from each interim payment to the contractor
- What is the purpose of retention?
- It provides an incentive for the contractor to complete the works promptly
- It provides some financial cushion to the employer in the event of contractor default
- What items do not have retention taken on them (Under JCT)?
- Loss and/or expense amounts
- Statutory fees and charges
- Some additional insurance premiums
- Opening up and testing costs
- Fluctuations Options A and B
- What is the employer’s interest in retention?
- As a trustee for the contractor
- What should employer do with retention if requested by the contractor?
- Place it in a separate bank account
- Label the account as being held in trust
- Provide the contractor with statements showing the payments and amount of money in there
- This should ensure that the money is available to the contractor in event of employer insolvency
- Who gets the interest accruing on retention money?
- The employer
When is the retention released to the contractor?
Half of the retention is released to the contractor after assessment is made at Completion of the whole of the works or in the next assessment after Employer has taken over the whole of the works if this is before Completion of the whole of the works.
Other half released when the Defects Certificate issued
- What is a retention bond?
- Provided by the contractor in lieu of taking retention from interim payments
- It should be to the same value as the retention deducted would have been
- Requirement should be stated in the contract
- What happens if the contractor does not maintain the retention bond?
The employer can deduct retention from interim payments
If the bond is subsequently taken out, the retention deducted must be repaid to the contractor
What happens to the retention bond if the contract sum increases?
Retention can either be deducted from interim payments on the additional amount or the value of the retention bond can be increased
- Why might a retention bond be used?
- May be used in difficult market conditions to aid the contractor’s cashflow
- What are the disadvantages of a retention bond?
- Employer would have to pay the premium for taking out the bond
- May reduce the contractor’s incentive to complete to standard and promptly
- Harms the employer’s cashflow
- The employer would not get the interest accruing on the amount of the retention bond
- What is a firm price contract?
- Where adjustments of the contract sum are limited to changes in statutory contributions, taxes and levies
- What is a fluctuating price contract?
- Where the contract sum is adjusted for changes in the costs of materials and labour as well as statutory contributions, taxes and levies
- When is the base date set?
- Usually 10 days before the tender return date
Where is fluctuations dealt with under NEC3?
Secondary Option Clause X1
What are the fluctuations options under NEC3?
If Employer decides to accept all this risk then X1 is selected. If not, left to the main option clauses - Option A and B contract is firm price, C and D shared via pain/gain share. E and F Employer carries all risks.
What is the completion date?
Fixed date stated in the Contract Data Part 1
- What does it mean when ‘time is at large’?
- There is no fixed completion date
- The contractor must only complete the works in a reasonable time
What is the NEC definition of Completion?
‘Completion’ in the ECC is a defined term, Clause 11.1.
Completion is when the Contractor has –
• Done all the works which the works information states he is to do by the Completion date
• Has corrected notified Defects which would have prevented the Employer from using the works and Others from doing their work
• If the work Contractor is to do by completion date is not stated in works information, Completion is when contractor has done all the work needed for Employer to use the work or Others to do their work
- What is sectional completion?
- The completion and handover of the works to the employer in agreed stages
- Do the works have to be totally completed before practical / sectional completion is achieved?
- completion is a vague concept
- It is reliant on the architect’s opinion that the works are complete
- It should not be conditional
- It is common practice for Completion to be granted when the works are substantially complete – i.e. there may be minor defects or omissions BUT nothing that would prevent the employer taking occupation