Q

The distance from the cup of a hoist’s top hook to the cup of the hoist hook when it is at its upper limit of travel.

A

Headroom

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A ___ is a socket that is compressed onto the end of a wire rope.

A

Swage Socket

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Choker hitches put extra stress on a sling at the point of the choke, which reduces the slings rated load.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Multiple-leg chain slings are also known as ___ slings

A

bridle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The strength of a shain and shain attachments depend on the steel alloys from which they are made.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A ___ prevents the hoist from lifting a load that is over its rated capacity

A

Slip clutch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Web sling safety factor indicates the fraction of total tensile strength that may be used for lifting load

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

___ Treatment can be used to develop the desired combination of strength and durability in a metal/

A

heat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The rules for Hoisting personnel are different from the rules for hoisting loads.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

____ is the tension at which a material is expected to break.

A

Breaking Strength

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Because of their inherit design, synthetic ropes and slings will not rot, mold, or mildew

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Chain slings are fabricated in single-leg and multiple-leg configurations?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A sling must be immediately removed from service if the warning yarns are visible?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

___ is the ratio of a components breaking strength to its rated load.

A

Safety Factor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

-In general, a crane inspection consists of a ___ inspection.

A

hoist, platform, positioning component. (All of the above)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

___ is the distance between a hoist hook’s upper and lower limits of travel.

17
Q

Using the ___ procedure involves considering the load as a group of smaller sections, each with its open weight and CG.

A

Section CG(Center of Gravity)

18
Q

What must be determined so that a load remains stable and level when lifted?

A

load’s center of gravity.

19
Q

Written inspection record are required for hardware

20
Q

To prevent its inadvertent use, damaged equipment must be properly ___ as suck until it can be destroyed or repaired.

21
Q

-Nonstandard hand signals are permitted only if the standard hand signal set is not practical

22
Q

The Rated load of a web sling depends on the ___

A

Number of plies, webbing class, hitch type (All of the Above)

23
Q

The rated load is the ___ that a rigging component may be subjected to while maintaining an appropriate margin of safety.

A

Maximum tension.

24
Q

OSHA section 29 CFR 1910 and 29 CFR 1926 apply to general industry and construction respectively.

25
The Typical safety factor for web slings is ___?
5
26
___ Loads always tilt toward the center of gravity.
Unbalanced
27
Knots in web slings should be untied only if they have not yet been pulled tight under load.
True
28
A ___ is a category of knots that are used to tie the ends of two ropes together.
Bend
29
Dirt is particularly likely to get into the weave of synthetic rope and slings and may cause damage.
True
30
In a block-and-tackle assembly, the number of sheaves is assumed to equal the number of parts.
True
31
A rope with a break in an entire strand must be removed immediately.
True
32
If signs of damage are discovered that do not yet excess allowances, the equipment is ___ to remain in service
Permitted.
33
___ are used between the load and the rigging components.
Softeners
34
If a two-part reeve is used to lift a load 24 inches and the lead line must be pulled 48 inches this is a ratio of ___.
2:1
35
___ is the maximum tension that a crane or hoist may be subjected to while maintaining the appropriate margin of safety.
Rated Capacity