Schedule Management

6.1 Plan Schedule Management

A

Planning

Determine how the project will be created, managed and controlled. What is the strategy?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Schedule Management

6.2 Define Activities

A

Planning

Identify the steps to complete the project work and deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Management

6.3 Sequence Activites

A

Planning

Determine the correct order & relationships between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Management

6.4 Estimate Activity Duration

A

Planning

Estimate how many work periods it takes to complete each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Management

6.5 Develop Schedule

A

Planning

Create the project schedule using the duration estimates and sequencing of each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Management

6.6 Control Schedule

A

M&C

Monitoring project work and managing changes to the planned Schedule baseline.