Schedule Management Knowledge Area Flashcards

1
Q

Define Project Scheduling

A

represents how and when the project will deliver services, products and resulted defined in the project scope and aids with performance reporting and communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do schedule considerations differ in an agile/ adaptive framework?

A

often short cycles are used to start work allowing for rapid feedback and manifest as on-demand (such as Kanban) and iterative schedules (with a backlog)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Project Schedule Network Diagram

A

a graphical depiction of the relationships among project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define Precedence Diagramming Method

A

a network diagramming method using rectangles (nodes) to represent activities and arrows to show logical relationships between the activities; AKA Activity-on-Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the (4) types of Dependencies

A

Finish to Start
Finish to Finish
Start to Start
Start to Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Lead

A

Starting an activity prior to completion of the preceding activity; getting a head-start on an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define Lag

A

Delaying the start of an activity after the completion of a preceding activity; delaying an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define Bottom-Up Estimating

A

breaking a project or activity down in smaller components that are easier to estimate, then aggregating those costs or durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Analogous Estimating

A

using a previous project or activity as a starting point to estimate activity costs or activity durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Parametric Estimating

A

using statistical relationship to calculate cost or duration; typically involves multiplying the number of units by a cost or duration per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

3 Point Estimating

A

a weighted average method used to increase estimation accuracy; uses Optimistic, Pessimistic and Most Likely estimates to calculate the estimated activity cost or duration

Beta Distribution Formula (PERT) and Triangular

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Beta Distribution Formula?

A

AKA PERT

(O+4*ML+P)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Triangular Distribution Formula?

A

(O+ML+P)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define Reserve Analysis

A

contingency reserves used to account for schedule or cost uncertainty (risks)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define Critical Path

A

the path of activities along which any delays will cause the project to be delayed; the longest duration path through the schedule network diagram; the chain of tasks which all have the least amount of float (normally zero)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define Total Float (Slack)

A

the amount of time an activity can be delayed without delaying the project completion date

17
Q

Define Free Float

A

the amount of time an activity can be delayed without delaying the earliest following (successor) activity

18
Q

Define Critical Path Method

A

a schedule analysis method calculating the shortest path for the project, float for each activity, and possible start and finish dates for each activity

19
Q

What are (2) schedule compression techniques?

A

Crashing: add resources, results in higher costs

Fast tracking: doing activities in parallel, which increases risk

20
Q

Define resource leveling

A

used to adjust the resource schedule when resources have been over-allocated; often lets the schedule slip in order to level out resource utilization; a histogram (bar chart) is the tool used to do this

21
Q

Define resource smoothing

A

used to adjust the activities within the schedule to keep resources from exceeding limits; with resource smoothing, the completion date is not delayed

22
Q

Define schedule baseline

A

the accepted and approved version of the project schedule

23
Q

Inputs, T&Ts, Outputs of Plan Schedule Management

A

Inputs: Project charter, project management plan, EEF/OPAs

T&Ts: expert judgment, data analysis, meetings

Outputs: schedule management plan

24
Q

Inputs, T&Ts, Outputs of Define Activities

A

Inputs: Project management plan, EEF/OPAs

T&Ts: Expert judgment, decomposition, rolling wave planning, meetings

Outputs: Activity list, activity attributes, milestone list, change requests, project management plan updates

25
Inputs, T&Ts, Outputs of Sequence Activites
Inputs: project management plan, project documents, EEF/OPAs T&Ts: precedence diagramming method (PDM), dependency determination and integration, leads and lags, project management information system Outputs: project schedule network diagrams, project documents
26
Inputs, T&Ts, Outputs of Estimate Activity Durations
Inputs: Project management plan, project documents, EEF/OPAs T&Ts: expert judgment, analogous estimating, parametric estimating, three-point estimating, bottom-up estimating, data analysis, decision making, meetings Outputs: Duration estimate, Basis of estimates, project documents updates
27
Inputs, T&Ts, Outputs of Develop Schedule
Inputs: Project management plan, project documents, Agreements, EEF/OPAs T&Ts: schedule network analysis, critical path method, resource optimization, data analysis, leads and lags, schedule compression, project management information system, agile release planning Outputs: schedule baseline, project schedule, schedule data, project calendars, change requests, project management plan updates, project documents updates
28
Inputs, T&Ts, Outputs of Control Schedule
Inputs: Project management plan, project documents, work performance data, OPA T&Ts: data analysis, critical path method, project management information system, resource optimization, leads and lags, schedule compression Outputs: work performance information, schedule forecasts, change requests, project management plan updates, project documents updates
29
What refers to the most recent schedule with notations to indicate updates, completed activities, and started activities as of the indicated data date?
Project Schedule