Scheduling 13 Flashcards

0
Q
  1. How do you incorporate awkward procurement times into the construction network?
A

by adding a TASK BUBBLE between PROJECT START nd the CONSTRUCTION TASK needing the resource. Then you do the usual time calculations (Forward and Backward passes.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q
  1. In complex cases that include several resources with a negative start day, you should:
A

incorporate a new task representing each awkward procurement detail into the basic construction network. CRUCIAL PROCUREMENT ACTIVITIES SHOULD NOW BE CONSIDERED TO BE A PART OF THE CONSTRUCTION PROJECT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. The revised dates and floats from the updated schedule are then inserted back into columns #11 and #12 of the TICKLER SPREADSHEET and the events for the ordering process are updated. Then:
A

all the rows are rearranged so that the tasks with the earliest EST are first and the rest are in sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. An objective of RESOURCE LEVELING is to smooth out wide swings in the daily application of certain resources, esp. work crews.
A

Management’s objective is to achieve a steadily working crew by rescheduling certain tasks by altering or adding precedence links into the network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. When the schedule shows two tasks requiring the same piece of equipment at the same time, you decide which task should use it first by:
A

comparing the total float of both tasks, their FLOATS DETERMINE THEIR PRIORITIES.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. When two tasks start at the same time and require the same crew, and one has no float, you:
A

force the task with float to follow the other one by adding a SEQUENCING ARROW between their ACTIVITY CIRCLES.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is an alternative way to prioritize the tasks when a resource is needed at the same time?
A

to prioritize the tasks in order of their late start times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. THE REMAINDER OF THIS CHAPTER DEALS WITH SMOOTHING RESOURCES, WHICH DOES NOT APPLY AT THE MOMENT.
A

Skip to Ch 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly