Scheduling Flashcards

(41 cards)

1
Q

Network Diagram

A

A graph that shows the activities, duration, and interdependencies of tasks within a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Node

A

Represents the start or end of an activity in a sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Early Finish

A

Used in a networking diagram, this represents the earliest date that the activity can finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Early Start

A

Used in a networking diagram, this represents the earliest date that the activity can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Precedence Diagramming Method (PDM)

A

A technique used to create the network diagram. It constructs a schedule model in which activities are represented by nodes (Activity on Node - AoN) and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a schedule model?

A

A schedule model is a representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule. [PMBOK® Guide 7th edition, Page 249] (Domain: Process, Task 6)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

schedule management plan

A

A schedule management plan documents the schedule management processes on a project but not the schedule model itself. [PMBOK® Guide 7th edition, Page 249] (Domain: Process, Task 6)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What 4 steps make up the Schedule planning process?

A

Define activities,
Sequence activities
Estimate activity durations
Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lag

A

In dependencies, refers to the amount of time whereby a successor activity will be delayed with respect to a preceding activity on the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lead

A

In dependencies, refers to the amount of time whereby a successor activity can be advanced (started) with respect to predecessor activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Baseline

A

The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis of comparison to actual results. It is one of the main project documents that should be created before the project starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Compression

A

A method used to shorten the schedule duration without reducing the project scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule Forecast

A

Estimates or predictions of conditions and events in the project’s future based on information and knowledge available at the time the schedule is calculated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Schedule Management Plan

A

A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Schedule Performance Index (SPI)

A

Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio of earned value over planned value. Less than 1 = behind schedule. Greater than 1 = ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Variance (SV)

A

A measure of schedule performance is expressed as the difference between the earned value and the planned value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Slack

A

Used in the critical path method. Amount of time that a task can be delayed without affecting the deadlines of other subsequent tasks. (same as Float)

18
Q

Backward Pass

A

Technique for calculating the late start and late finish dates of the schedule activities. This is part of the critical path method and is paired with forward pass to determine activity and schedule float along with the critical path.

19
Q

Bar Chart

A

A graphic display of schedule-related information. In the typical bar chart, schedule activities or WBS components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. See also “Gantt Chart”.

20
Q

Critical Path

A

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.

21
Q

Critical Path Method (CPM)

A

A technique of schedule analysis in which schedule activities (Activity on Arrow - AoA) are evaluated to determine the float or slack for each activity and the overall schedule. To calculate critical path, use the forward and backward pass along with float analysis to identify all network paths, including critical.

22
Q

Forward Pass

A

Technique for calculating the early start and early finish dates of the schedule activities. This is part of determining critical path and is paired with backward pass to determine activity and schedule float along with the critical path.

23
Q

Resource Leveling

A

Resource Leveling is a resource optimization technique which IMPACTS the critical path. Adjustments are made to the project schedule to help with over or under allocation of resources.

24
Q

Resource Smoothing

A

Resource Smoothing is a resource optimization technique which does NOT affect the critical path in which free and total float are used to even out the allocation of resources across a project schedule.

25
Resource Optimization Techniques
Techniques in which activity start and finish dates are adjusted to balance demand for resources with the available supply. Either resource smoothing or leveling.
26
Resource Breakdown Structure
A hierarchical representation of resources by category and type.
27
Resource Calendar
A calendar that identifies the working days and shifts for which each specific resource is available.
28
Resource Histogram
A bar chart that represents when a resource will be needed in the project.
29
Free Float
The amount of time that a scheduled activity can be delayed without impacting the early start date of any subsequent scheduled activity. (same as Free Slack)
30
Negative Float
The amount of time that must be saved to bring the project to completion on time. (same as negative Slack) Indicates the schedule must be adjusted.
31
Total Float
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. (same as Total Slack)
32
When a project is seriously lagging behind schedule and an extension of time is not an option, you are left with the option of crashing the project. You are concerned that crashing the project might over-allocate resources and want to apply resource leveling and smoothing to the crashed schedule. What is the difference between resource leveling and smoothing?
Resource Leveling can cause the project's critical path to change, while Resource Smoothing doesn’t alter the project’s critical path. [PMBOK7 p238] (Domain: Process, Task 6)
33
Schedule Crashing
Schedule Crashing is when the project sponsor approves extra funding and resources to expedite delivery of activities
34
Resource Fast Tracking
Resource Fast Tracking is when some activities on the critical path currently in sequence can be done in parallel
35
Project Schedule Network Diagram
A graphical representation of the logical relationships among the project schedule activities including project tasks, dependencies, and sequencing to visualize the project schedule and critical path. An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources. See also “Network Diagram”.
36
Name the Schedule Management process steps in sequential order
Plan Schedule Management Define Activities Sequence Activities Estimate Activity Durations Develop Schedule Control Schedule
37
You are auditing a project that has recently delivered a new capability to the business. The purpose of the audit is not only to review the efficiency of the applied project management processes but also revaluating the delivered business value. You are looking for a summary milestone schedule for the project. Which of the following documents can provide you this?
Project charter NOT Project scope statement The summary milestone schedule is normally included as part of the project charter, which documents the business need, understanding of customer's needs, and other high-level items. [PMBOK7 p184] (Domain: Process, Task 17)
38
Sally, a project manager, was reconciling expenditure of funds with funding limits on the commitment of funds for the project. She found a large variance between the funding limits and planned expenditures. As a result, she decided to reschedule work to level out the rate of expenditures. This is known as:
Funding limit reconciliation NOT Funding limit constraints NOR Funding limit expenditure NOR Funding limit appropriation This is known as funding limit reconciliation. It can be accomplished by placing imposed date constraints for work into the project schedule. [PMBOK7 p62] (Domain: Process, Task 5)
39
You are managing a construction project with the following schedule network (See photo - all durations given in months). If activity D gets delayed by 7 months, what will be the impact on the schedule?
Activity H will get delayed by a month but the activity G will not get impacted. NOT Both activities G and H will get delayed by a month. NOR: None of the activities will get impacted by this delay. NOR: Activity G will get delayed by a month but the activity H will not get impacted. Activity D has a total float of 6 months. A 7-month delay will have an impact on the network. A seven-month delay means that the activity D will now complete by the 21st month. Since activity H was scheduled for the 21st month, this will get delayed by a month. However, there will be no impact on activity G since it has a late start of the 26th month. [PMBOK7 p238] (Domain: Process, Task 6
40
Which document includes a summary milestone schedule for a project?
Project Charter​. NOT Project scope statement. The summary milestone schedule is normally included as part of the project charter, which documents the business need, understanding of customer's needs, and other high-level items.
41
If an activity has a total float of 6 months and is delayed by 7 months, what is the impact?
It could delay some subsequent activities beyond their float, affecting the schedule, but not activities with more than 7 months of float.