Section 6 & 7 Flashcards

Inspection & Materials

1
Q

Who can perform the routine in-service inspections?

A

Anyone knowledgeable of the operations, the tank, and product stored in the tank

API 653 par 6.3.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What membrane stress is that is required to cause a brittle fracture?

A

7 ksi (7000 PSI)

API 653 par 5.3.7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often must the routine-in-service inspection by performed?

A

At least MONTHLY

API 653 par 6.3.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who is required to perform external inspections?

A

Authorized Inspector

API 653 par 6.3.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the required inspection interval for an external inspection?

A

Lesser of 5 years or RCA/4N

API 653 par 6.3.2.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who determines the extent of thickness measurements?

A

Owner/Operator

API 653 par 6.3.3.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the maximum interval for taking thickness measurements, when the corrosion-rate is not known?

A

5 years

API 653 par 6.3.3.2a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the required interval for taking thickness measurements, when the corrosion-rate is known?

A

Lesser of 15 years or RCA/2N years

API 653 par 6.3.3.2b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When is it acceptable to not take thickness measurements?

A

If the Internal Interval is shorter than the thickness monitoring internal

API 653 par 6.3.3.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Surveys of the cathodic protection system is performed in accordance with what code?

A

API 651

API 653 par 6.3.4.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the required internal for performing cathodic protection surveys?

A

Annual

API 653 par 6.3.4.1 & API 651 par 11.3.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How often must the sources of impressed current be checked on a cathodic protection system?

A

At least every two months

API 653 6.3.4.1 & API 651 par 11.3.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who must conduct the internal inspection and supervise the collection of data?

A

Authorized inspector

API 653 par 6.4.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When can an on-stream inspection be perofrmed in lieu of visual internal inspection of the tank?

A

When the inspection is being performed to determine the condition of the tank bottom

API 653 par 6.4.1.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

By what date must the tank owner/operators have to be in compliance with API 653

A

January 2017

API 653 par 6.4.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the longest initial internal inspection internal allowed by API 653?

A

30 years (10 year base interval plus 10 years RPB plus 10 years for SS bottom) See Table 6.1

API 653 par 6.4.2.1.1

17
Q

What is the longest initial internal inspection interval allowed by API 653 for an oil storage tank without safeguards or RPBs?

A

10 years

API 653 par 6.4.2.1.1

18
Q

What is the maximum internal inspection interval, if an RBI was not performed and no other special condition is applicable?

A

10 years

API 653 par 6.4.2.1.2

19
Q

A tank that contains a highly viscous materal which will solidify above what temperature is not required to meet the maximum internal inspection interval requirement?

A

< 110°F

API 653 par 6.4.2.1.2(1)

20
Q

What is the longest subsequent internal inspection interval allowed by API 653 for an oil storage tank with remaining corrosion allowance that is greater than 150 mils?

A

20 years

API 653 par 6.4.2.2.1

21
Q

What is the longest subsequent internal inspection inteval allowed by API 653 for an oil storage tank without safeguards and remaining corrosion allowance is greater than 150 mils?

A

20 years

API 653 par 6.4.2.2.1

22
Q

How often must a RBI assessment be reviewed?

A

Every 10 years or sooner if warrnated by process, equipment or consequence changes

API 653 par 6.4.2.2.2

23
Q

When is it allowed to not scan the tank bottom during an internal inspection to determine external thickness loss?

A

When the bottom thickness can be determined by external means

API 653 par 6.5

24
Q

What type of records is the owner/operator required to maintain?

A

Construction, inspection, and repair/alteration records

API 653 par 6.8.1

25
Who must write the external and internal reports?
Authorized Inspector ## Footnote API 6.9.1
26
How long must external and internal inspection reports be kept?
Life of the tank ## Footnote API 653 par 6.9.1
27
What test must be performed if adequate identification is not available for shell or bottom plates?
Chemical analysis, and mechanical testing (Charpy and Tension test) ## Footnote API 653 par 7.3.1.2