Study Guide Definitions Flashcards

1
Q

Includes description, point of contact and dates of action

A

Action Item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The number which represents the average cost of the project by hour, day, or week.

A

Burn Rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A plan that identifies key assumptions, beyond the project manager’s control, and their probability of occurrence. The plan identifies alternative strategies for achieving the project success. It is considered part of risk management.

A

Contingency Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project element that is considered a unit for the purpose of configuration management. This includes such items as software modules, version of software system, the project design document, and the project plans.

A

Control Item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A process that provides a mechanism to document, research and resolved issues that arise during t project planning and execution.

A

Issue Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A valuable closure mechanism for team members regardless of the project’s success. Includes
- Project Team
- Stakeholder representation – including external project oversight
- Executive Management
- Maintenance and Operation Staff

A

Lessons Learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A significant event in the project (key item or key event).

A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The act of defining strategies in terms of scope, budget, schedule, or quality to reduce uncertainty on the project.

A

Mitigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PERT

A

Program Evaluation and Review Technique. Communicates project critical path. Can also be used to estimate the range of potential costs and timeframes of any given project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PIER

A

Post Implementation Evaluation Report. A report generated during close-out activities. Documents lessons learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Developed during the concept phase and finalized in the planning phase. Includes
- Business problem
- Statement of work
- Objectives
- Success factors
- Project dependencies
- constraints

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A graphical representation of predicted tasks, milestones, dependencies, resource requirements, task duration, and deadlines.

A

Project Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

During start-up the project manager assesses the skills of the available people for the project.

A

Project Staffing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Scope, definition, and objectives. Defines the project charter. High level approach
First task in the definition phase.

A

Project Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Planned and systematic process for evaluating the satisfaction of the project.

A

Quality Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Systematically determining the impact of identified risks on the project.

A

Risk Analysis

17
Q

Implementing an alternative series of task to accomplish a specific objective. Often done to get a project back on schedule. Generally raises the overall cost of the project. Only for activities on the critical path.

A

Crashing

18
Q

Activities or phases normally done in sequence are performed in parallel for at least a portion of the project. Risk is increased and rework may result. Only works if activities can be overlapped to shorten the project duration.

A

Fast Tracking