Technical Flashcards

1
Q

What is the guidance note on dilapidations?

A

Dilapidations England and Wales

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what are the duties under PD for CDM 2015

A

Management of health and safety during design
identify an eliminate hazards
ensure designers carry out health and safety duties
review and update the health and safety file

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Under the building safety act 2022 what is the duty of the principal designer?

A

The principal design is to ensure that the works comply with the building regulations planning and managing and monitoring the design work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the British standard for construction hats?

A

BSEN397

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the meaning of integrity?

A

Integrity means to be honest and have strong moral principles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the dilapidation protocol?

A

Also known as the pre-action protocol for claims for damages in relation to physical state of a commercial property. The dilapidations is a set of guidelines guidelines in England and Wales outlines the conduct expected of landlords and tenants before proceedings in relations to a dilapidations claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the key aspects of the dilapidations protocol?

A

To encourage the exchange of early and full information of the claim and to avoid litigation
It applies to commercial property in England and covers claims for damages for breaching repair covenants
The law should serve the dilapidations within a reasonable time after the termination of tenancy typically within 56 days
The quantified demand the landlord should provide a detailed breakdown associated with the claim reaches
Response the tenant should respond to the claim within a reasonable time usually within 56 days of receiving the quantified demand
Schedule agreement cannot be reached. A schedule should be repaired detailing items in dispute.
ADR, the protocol encourages parties to consider ADR resorting resorting to lit
Valuation the landlord should consider whether they exceed the value of reversionary interest
Proportionality the cost of the works and associated professional fee should be in proportion to the breach
Superstition consider consideration should be given to whether the landlord intends to carry out the works or that would be superseded by the repairs claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the minimum and maximum rise for stair trades?

A

Part K of the building regulations state that the minimum height for each step is 150 mm
The minimum going/tread is 220 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When is building regulations required in an older building?

A

Number one change of use
Two major alterations
Three extensions
For electrical works
Five plumbing and heating
Six structural changes
Seven fire safety improvements
Seven accessibility modifications
Drainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the different types of single ply roofs?

A

EPM roofs GRP roofs and felt roofs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name three types of felt roofs

A

Torch on felt
Traditional built-up felt
Self adhesive felt roofing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name three roofing belts

A

Klober
TLX
IKO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Name some approved documents

A
  1. Approved document A struct.
    Approved document B fire safety
    Approved document, see site preparation
    Approved document D toxic substance
    Prove document resistance to passage of sound
    Approved document ventilation
    G sanitation hot water
    H drainage and waste disposal
    J combustion appliance and fuel storage system
    K document protection from falling collision and impact
    L Conservation of fuel and power
    M access and use of buildings

Oh overheating
P electrical safety
Q security
Seven materials and workmanship

T Toilet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the Client duties under CDM?

A

Appoint a principal contractor
Appoint a principal designer
Provide welfare
Prepare construction phase plan
Allow adequate time for works
Maintaining the health and safety file
Notify health and safety executive if required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Tell me about building safety at 2022

A

The building act came from the Hackett report which was from Greenfield Tower. This states all buildings and all sizes and talks about the competence in the industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Tell me about the building safety regulator

A

The building safety regulator overseas safety and performance of build
Helping built environment and BC comp
Leading a new regulatory framework
Applies to high-rise
Seven stories or one floor above 18 m
The building safety regulator is the building control body for high-rise buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is safety act 2022? Tell me about it?

A

Define safety act 2022 is the product of the grand Ford Tower it amends the regular reform order 2005

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does the fire safety act 2022 app

A

It applies to 2or more sets of residential premises
All multi occupied buildings
Structure
External walls
Common parts
The changes include for fire doors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the meaning of sustainability?

A

Focus focusing on the needs of today without compromising the needs of the future

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What does the building safety regulator do?

A

Overseas safety and performance
Helps the building built environment
New framework deleting
Considerations to high risk hospitals care homes, high-rise and any buildings 18 m or above seven stories

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the updates to the F fire safety act 2022?

A

The act now explicitly confirms external cladding and the front doors to individual flats and balconies are considered to be part of the fire risk assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the building regulations part B say about fire safety?

A

Fire Assessments are required
Fire service enforcement can be taken as action
Sprinklers are required for buildings above 11 m
Staircases must be protected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the definition of a responsible person under the fire safety act 2022?

A

Responsible person must assess manage and reduce the risk
Carry out fire risk assessments and proof of compliance
Fire services can take action if not done
Sprinklers are required for above 11 m
Suppression systems are required
Compartmentation of Protected stairs and floors 60 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are the ages of properties in the UK?

A

Georgian properties are 1714 to 1830
Victorian properties are 1837 to 1901
Edwardian properties are 1900 to 1920
Into war 1920 to 1930
Postwar is 1945 to 1970

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is subrogation?
Subrogation is a third-party is negligent then ensure it will go after the third-party
26
When is a payment due under the JCT600 minor works 2016?
Seven days after evaluation 14 days after DRP
27
What is novation?
Simply novation is when one party leaves and a new party joints the remaining party stays the same An architect may design something and then they pass it on during a design and billed contract. The contractors are architect will now take on the design responsibility known as novation.
28
Tell me about basement grades
Grade one car park Grade 2, no leaks Grade 3 habitable archive
29
What is tesserai
When water that gets behind the tiles and causes failure to the additions
30
What is diminution of the reversion?
Diminution in value quantifies the landlords loss and is done by specialist valuer
31
What are the two limbs of the landlord and tenant act 1927?
Limb one The amount of damages for breach of a repairing covenant shall not exceed the difference between the valuation of the landlords reversion with repairs done and be the value of landlords reversion interest without the repairs done Limb 2 No damages should be recoverable if it shown that the premises would have been a demolished be such structural alterations would make them render value less the repair
32
What is a part 36 offer?
A formal offer for settlement on part 36 of the civil procedures rules in England and Wales The purpose is to encourage early settlements of disputes and to protect the offering party from Can be made by the landlord Must be writing and state it’s a part 36 offer Part 36 usually remains open for 21 days
33
Why use without prejudice when approaching a dilapidations?
It is used in negotiations to protect the contents of discussion being used as evidence in court encourages open and honest settlement discussions This also prevent statements made during negotiations from being used by the party in court Speak freely without words being used against them It also promotes settlement
34
what is the difference between without prejudice and save as to cost?
The purpose of without prejudice save as close as doing encourage settlement preserving the ability to refer to offers when determining cost Same as can be shown in court after the main issues are decided Without prejudice can never be disclosed As to cost can be disclosed after main judgement during considerations Without prejudice as the cost is often used for part 36 offers
35
Liquidated damages be measured
Liquidated damages should be measured. As a genuine pre-estimate of loss. Delated damage should be proportional and the amount should be proportionate to the legitimate interest being protected He shouldn’t be high compared to the actual loss
36
What is a formula used to work out liquidity damages in the past?
Generally, I use the landlords loss of rent per week so if it was six weeks it could be times six weeks times 2500
37
In relation to the dilapidations claim at unit four way what items could superstition not have been included to?
The lighting may have helped fell part of the claim as test undertaken and the lighting was in poor. state of condition
38
What is a critical path works progress and quality management?
The critical part is the longest sequence of dependent tasks in a project that must be completed on time for the project meeting is deadline Delay in on the critical part directly impact the project completion day Consider items such as float or slack Identify the issue you should look at all activities and determine dependencies between activities and estimate times for each part Progress identifies crucial for completion and helps prioritise resourcing and attention Progress also allows for effective scheduling and planning You can use GANT and critical path method software
39
What is regulatory board Rics?
The purpose of the relative bodies to oversee regulatory and disciplinary functions of the RSCS showing members are due to professional standards and ethical Operates independently from the Rics governing body to maintain impartiality and regulating matters The radiator board consist of both RSTS members and independent members ensuring a balance perspective Responsibilities are developing implementing regulated policies Pollis Insuring compliance with professional standards Projecting the matter relating to the surveying platform The board has authority to impose sections of members breach RSS standards rules of conduct
40
What is the RSCS financial benchmarking?
Purpose of benchmarking is to provide insights into business performance and identified areas of improvement and to support strategic business decision-making Items included as such a Revenue per fee earner Profit margins Overhead cost Working progress
41
What is typically in your terms and conditions?
The agreement Definitions Client obligations Scope of services Payment terms Confidentiality Copyright Termination Liability Data protection Force majeure
42
What is a dewpoint?
The dewpoint is the temperature of which the air becomes saturated with water vapour causing water to condense into a liquid form Once This has done, the air can no longer hold all of his water vapour so it starts to form water liquid droplets
43
When does condensation occur?
Condensation occurs when warm warm moist air comes into contact with the cooler service that is at all below the dewpoint temperature When the surface temperature drops below the dewpoint of the surrounding air vapour in the air condenses into liquid water on surface
44
What is the minimum EPC requirements?
The current minimum EPC in the UK is E or higher and is due to increase to see by 2030
45
How to calculate liquidated damages
Liquidated damages is any rate predefined and agreed on by both parties
46
What are the main GCT contract sections?
Articles of agreement Particulars Conditions Schedule Contract documents Supplementary provisions Any amendments Appendices Attestation
47
Was the asbestos roof sheets on this project notifiable
The asbestos cement roof sheets were not notifiable under the controller of asbestos regulations as these asbestos cement sheets were considered nonfriable materials meaning their less likely to release asbestos fibres
48
Was the asbestos roof sheets on this project notifiable
The asbestos cement roof sheets were not notifiable under the controller of asbestos regulations as these asbestos cement sheets were considered nonfriable materials meaning their less likely to release asbestos fibres
49
What are the conditions of non-notifiable work?
The work is sporadic and of low intensity Exposure to asbestos is not likely to exceeded the control limit The control limit is 0.15 as per cubic centimetre of average of a average over a four hour period
50
What are the exceptions of non-notifiable asbestos?
If the asbestos cement is in poor condition will be subject to aggressive mechanical treatment. The works may become notifiable.
51
What is notifiable asbestos works?
Works with asbestos that must be notified to relevant enforcing authority before you comm These are likely to expose workers to asbestos fires over the control limit He works for license from the health and safety executive
52
What are the three asbestos criteria for health and safety executive?
Notifiable non-licence work None Notifiable asbestos works notifiable asbestos works
53
what is non-notifiable license works?
These words do not require a licence, but still needs notification
54
Give me some examples for non-notifiable asbestos
We’re moving small amounts of intact as best of cement products During holes in asbestos material using gels or shadow vacuum Encapsulating with ceiling as materials in good condition Collecting samples
55
Give me some examples of notifiable work
Removing spray coatings Removing install Large scale removal of texture of decorating coatings Extensive work of cement and poor condition
56
What are the requirements for non-notifiable asbestos work
Risk assessment is required Appropriate training for workers Use of PPE Disposal of asbestos waste
57
What are the requirements for notifiable licensed asbestos works?
Notification the HSE within 14 days in advance Works carried out by licensed contractor Detailed plan of works Health surveillance for workers Recordkeeping
58
What are the key differences between non-notifiable and notifiable asbestos
The key difference is the level of risk involving as best as fibre release Notifiable requires formal notification to the health and safety executive
59
What is the pros and cons of a base system which is steel versus concrete?
Concrete is quicker than steel in terms of manufacturing Still would still need foundations and that the concrete pad would be sent Maintenance work required for concrete and there’s no need to cut the concrete
60
What attributes makes steel a strong candidate as a base material?
Still has high strength High durability Good structural integrity Design flexibility Still does not contribute to the fires
61
What do you take to ensure health and safety of personnel involved in the project?
Risk assessments Method statements Reconstruction information review of the contractors health and safety plan
62
Works progress and quality management what are the Rics guidance notes?
Rics guidance note on construction quality management
63
How to effectively manage works progress
Building surveyor must create a detail project plan with critical milestones, deadlines and key deliverables They should also oversee the project schedule and keep stakeholders informed with the process
64
What items would you prioritise in a plan maintenance report?
I will prioritise health and safety items and statutory items
65
Photo review for a plan maintenance report
I would review risk assessments for example fire risk assessment, general risk assessments. And operation manuals.
66
When is AGCT designing build contract used?
One of the reasons could be for the client to transfer design liability over to the contractor
67
How can fire safety principles be applied to minimise the risk of fires?
Ensuring adequate escape routes, installing smoke detectors and fire extinguishers, implementing fire prevention methods
68
How can fire safety principles be applied to minimise the risk of fires?
Ensuring adequate escape routes, installing smoke detectors and fire extinguishers, implementing fire prevention methods
69
Regulatory reform order 2005
It sets out the duties and responsibilities of the responsible person. This could be the employer owner and occupier to assess and manage fire safety risk in the premises.
70
What is the building regulations part B state
It applies to the design construction and alteration of the bill of buildings in England and Wales It provides your requirements for fire safety measures such as fire escape fire resistance, fire detection fire alarms, and firefighting facilities
71
Tell me about the housing act 2004
This legislation applies to the houses of HMOs in England and set up the fire safety requirements specific to these types of properties
72
What is the building at 1984 outline?
It’s outlines of requirement for construction alteration and maintenance
73
What do building regulations 2010 provide
Improvised technical guidance on construction standards, including structural and fire safety
74
What does the lead consultants role contain?
The key characteristics of the lead consultant is the main clients main point of contract Design manager who caused the main part of the project design