Tendering Documentation and Evaluation Flashcards

1
Q

What is included in the Coordinated Project Information?

A
  • drawings
  • specifications (preambles)
  • BoQs
  • activity schedules
  • BIM models.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the uses of a BoQ?

A
  • used in tender invites or evaluations
  • used to value tenders
  • help in obtaining subcontractor’s quotes
  • used to negotiate further contracts
  • for ordering materials
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 6 sections of a BoQ?

A
  • preliminaries
  • preambles
  • measured works
  • provisional sums
  • prime cost sums
  • day works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are preliminaries in a BoQ?

A

-nature, location and scope
- names of parties involved
- project info
- requirements and obligations
- specific requirements to be priced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are preambles in a BoQ?

A
  • used to shorten the main body of the BoQ
  • descriptions of expected standard of materials and workmanship.
  • includes BS references.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are measured works in a BoQ?

A
  • all the items of work
  • divided into appropriate headings.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a provisional sum in a BoQ?

A
  • a sum to cover the work which can’t be described using normal measurements.
  • used for when the scope of work is unknown.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the prime cost sum in a BoQ?

A

-Sums included in the BoQ for subbie works or materials / plant provided by a nominated supplier.
- basically anything done by a specialist firm.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are dayworks in a BoQ?

A

Any work that can’t be properly measured and valued.
Rates are the prices prevailing at the time of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the activity schedule?

A
  • Each activity given in the works information / accepted program is broken down into steps.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the tender documents?

A
  • Formal invitation / instructions
  • the form of tender method
  • the form of contract and its conditions
  • a pricing doc (activity schedule, BoQ etc.)
  • employers requirements and contractors proposals (if D&B)
  • Employers info for BIM
  • Design drawings / BIM
  • specifications
  • H&S file
  • tender return slip
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where are errors often found in tenders?

A
  • Contract period
  • pricing (inc. strategies)
  • Units, decimal places, items left unpriced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Cover Pricing?

A
  • When one company finds out what others are pricing their bid and make theirs higher so it isn’t chosen.
  • Because there is a belief that if they don’t submit a tender when invited they won’t be asked again.
  • Happens in competitive tendering.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Front/ Back end loading?

A
  • Costs are applied disproportionally at the start or end of the project to help cash flow.
  • The end price of the contract is still the same.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How can the contractor alter their prices to benefit themselves?

A

-Front end loading
- Back end loading
- Cover pricing
- Contractors will budget for current market prices but will submit a tender with lower prices so they’re chosen. Then they charge the client the actual prices and they have to pay. This must be spotted at tender stage by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is approach 1 for the correction of errors in tenders?

A

Tenderer is given the opportunity to confirm or withdraw. If they withdraw, the second best tender is chosen.

17
Q

What is approach 2 for the correction of errors in tenders?

A

Tenderer is asked to confirm if errors are to be corrected. If the tender is still the best then errors can be corrected and it is used, if not then the next best tender is checked for errors.

18
Q

What modifications can be added to a tender so a client accepts it?

A

Bill of reduction: expensive materials are replaced with cheaper ones and specifications are lowered.
Addenda Bills: Additional works are added to the design as the price quoted was below budget.