Terms Flashcards
(155 cards)
Acceptance Criteria
A set of conditions that are met before deliverables are accepted by the customers or sponsors
Activity
A distinct, scheduled portion of work performed during the project. Usually stored in an activity list.
Actual Cost (AC)
The actual cost incurred for the work performed on an activity during a specific time period
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Also known as top-down estimating.
Assumption
A factor in planning processes considered to be true or real without proof or demonstration.
Backward pass
A critical path method technique for computing the late start and late finish dates by working backward through the schedule model from the project end date.
Baseline
The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results.
Bottom-up estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the workbreakdown structure.
Budget at Completion (BAC)
The amount of all budgets established for the work to be performed.
Change control
A process whereby changes to documents, deliverables, or baselines related with the project are identified, documented, approved or rejected
Change Control Board
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions.
Change Control System
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled.
Change request
A formal proposal to change any document, deliverable or baseline in the project management plan.
Communications management plan
A component of the project management plan that describes how, when, and by whom information will be administered and distributed.
Configuration management system
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Constraint
A restrictive feature that affects the execution of a project.
Contingency reserve
Time or money assigned in the schedule or cost baseline for known risks with response strategies.
Corrective action
A planned activity that restores the performance of the project work with the project management plan.
Cost baseline
The approved version of work packages cost estimates and contingency reserve that can be changed using formal control procedures.
Cost Management Plan
A component of a project management plan that defines how costs will be planned and controlled.
Cost Performance Index (CPI)
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Cost Variance (CV)
The amount of budget shortfall or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
Crashing
A schedule compression technique used to shorten the schedule duration by adding resources. This will generally increase the cost of the project.
Critical Chain Method
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources.